Attachment_7_Contractor_QA_0001.pdf

PDF 87 KB Posted

Attached to
BIBLE CREEK ROAD CULVERT PROJECT Federal contract opportunity
Solicitation number
140L0621R0013
Issued by
Department of the Interior Bureau of Land Management National Office

About this file

This document contains answers to contractor questions about the Bible Creek Road Culvert Project solicitation. The solicitation is for replacing culverts along Bible Creek Road and has an estimated value between $1-5 million. The project will replace all culverts except for the 96-inch diameter pipe with plastic pipes. Work can only occur between July 1st and August 15th due to in-water restrictions. The road will be fully closed for the duration of construction which is 180 calendar days. The pre-bid site visit was not mandatory but encouraged and an attendance list was provided in amendment 00001. The anticipated start date is April 1st, 2022 and there is no set liquidated damages figure included.

View the file

Other files for this federal contract opportunity

Other files attached to BIBLE CREEK ROAD CULVERT PROJECT, newest first.
File Type Posted
Attachment_5_Pricing_Worksheet_0002.xlsx XLSX spreadsheet
Sol_140L0621R0013_Amd_0002.pdf PDF
Attachment_6_SF1442_Continuation_pages_4___39_of_the_Solicitation_0001.pdf PDF
Attachment_8_Pre-Solicitation_Site_Visit_0001.pdf PDF
Sol_140L0621R0013_Amd_0001.pdf PDF
Attachment_5_Pricing_Worksheet.xlsx XLSX spreadsheet
Attachment_4_USACE_Permit.pdf PDF
Sol_140L0621R0013.pdf PDF
Attachment_1_Specifications.pdf PDF
Attachment_2_Drawings.pdf PDF
Attachment_3_DOL_Wage_Determination.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation # 140L0621R0013

Project Title: Bible Creek Culverts

Attachment 7 Contractor QAs

1. What is the in water start date?

Answer: July 1, 2022 – August 15, 2022 as stated in the specifications. It does not preclude people to work on the project. Section 107 of the specifications discusses the water work window.

2. Will the road be allowed to be closed the entirety of construction?

Answer: Yes.

3. What is the estimated magnitude of construction?

Answer: $1 – 5 million.

4. The only pipe that is going to be metal is 96” one. The rest should be plastic.

Answer: Correct.

5. Is there a set liquidated damage figure for this project?

Answer: No.

6. When is the anticipated start date for this project?

Answer: April 1, 2022.

7. Is the duration of this project (180 days) being counted as “working days” or “calendar days”?

Answer: 180 Calendars Days as stated in block 11 of the SF-1442.

8. Was attendance taken at the pre-bid meeting for the Bible Creek Road Culvert project? IF so, may I get a copy of the pre-bid meeting attendance list, or will the list be posted online?

Answer: Please see amendment 00001 Attachment 7 Pre-Solicitation Site Visit.

9. Can you tell me if the site visit was mandatory? And can we still bid on this project if we did not attend the site visit?

Answer: The site visit is not mandatory but highly encouraged. Since it is not mandatory you can still provide a proposal for this project.