Attachment_7_Contractor_QA_0001.pdf
PDF 87 KB Posted
- Attached to
- BIBLE CREEK ROAD CULVERT PROJECT Federal contract opportunity
- Solicitation number
- 140L0621R0013
About this file
This document contains answers to contractor questions about the Bible Creek Road Culvert Project solicitation. The solicitation is for replacing culverts along Bible Creek Road and has an estimated value between $1-5 million. The project will replace all culverts except for the 96-inch diameter pipe with plastic pipes. Work can only occur between July 1st and August 15th due to in-water restrictions. The road will be fully closed for the duration of construction which is 180 calendar days. The pre-bid site visit was not mandatory but encouraged and an attendance list was provided in amendment 00001. The anticipated start date is April 1st, 2022 and there is no set liquidated damages figure included.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_5_Pricing_Worksheet_0002.xlsx | XLSX spreadsheet | |
| Sol_140L0621R0013_Amd_0002.pdf | ||
| Attachment_6_SF1442_Continuation_pages_4___39_of_the_Solicitation_0001.pdf | ||
| Attachment_8_Pre-Solicitation_Site_Visit_0001.pdf | ||
| Sol_140L0621R0013_Amd_0001.pdf | ||
| Attachment_5_Pricing_Worksheet.xlsx | XLSX spreadsheet | |
| Attachment_4_USACE_Permit.pdf | ||
| Sol_140L0621R0013.pdf | ||
| Attachment_1_Specifications.pdf | ||
| Attachment_2_Drawings.pdf | ||
| Attachment_3_DOL_Wage_Determination.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # 140L0621R0013
Project Title: Bible Creek Culverts
Attachment 7 Contractor QAs
1. What is the in water start date?
Answer: July 1, 2022 – August 15, 2022 as stated in the specifications. It does not preclude people to work on the project. Section 107 of the specifications discusses the water work window.
2. Will the road be allowed to be closed the entirety of construction?
Answer: Yes.
3. What is the estimated magnitude of construction?
Answer: $1 – 5 million.
4. The only pipe that is going to be metal is 96” one. The rest should be plastic.
Answer: Correct.
5. Is there a set liquidated damage figure for this project?
Answer: No.
6. When is the anticipated start date for this project?
Answer: April 1, 2022.
7. Is the duration of this project (180 days) being counted as “working days” or “calendar days”?
Answer: 180 Calendars Days as stated in block 11 of the SF-1442.
8. Was attendance taken at the pre-bid meeting for the Bible Creek Road Culvert project? IF so, may I get a copy of the pre-bid meeting attendance list, or will the list be posted online?
Answer: Please see amendment 00001 Attachment 7 Pre-Solicitation Site Visit.
9. Can you tell me if the site visit was mandatory? And can we still bid on this project if we did not attend the site visit?
Answer: The site visit is not mandatory but highly encouraged. Since it is not mandatory you can still provide a proposal for this project.
File details come from the government source that posted it. Updated .