Attach_11_-_Amend_0003_Questions_Answers_0003.pdf

PDF 115 KB Posted

Attached to
NEIBER FIRE FENCES
Solicitation number
140L0621R0007
Issued by

About this file

This document contains questions and answers regarding Solicitation Number 140L0621R0007 from the Department of the Interior Bureau of Land Management for NEIBER FIRE FENCES. Due to current materials lead times of 18-20 weeks, 140 additional calendar days have been added to the period of performance, extending it from 120 to 260 total calendar days to accommodate the increased lead time. The document confirms this schedule change in response to a question about materials delays potentially preventing completion within the original timeframe and asks about any penalties for missing the completion deadline.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEIBER FIRE FENCES

Solicitation No: 140L0621R0007 – Amendment 0003 Questions & Answers

Questions & Answers

1. We are being told that all products ie. Wire, posts etc are a minimum of 18-20 weeks out. Would this cause an issue? That would put work starting in November more than likely. This would cause issues on the completion date specified. How would we go about rectifying this issue? What are the penalties if the job is not completed in the allotted time frame?

The government confirmed that current materials lead time is 18-20 weeks and as a result 140 additional days have been added to the period of performance to accommodate this increase in lead time. The period of performance is now 260 total calendar days.