Sol_140G0325Q0122_Amd_0001.pdf
PDF 99 KB Posted
- Attached to
- Media Production Aleutian Cruise
- Solicitation number
- 140G0325Q0122
About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a media production project aboard the Research Vessel Atlantis. The amendment extends the offer receipt deadline to 06/03/2025 and includes a comprehensive set of questions and answers for potential contractors. Key details include a media production contract for documenting a USGS deep sea exploration cruise from June 13 to July 4, 2025, with specific requirements for a single-person film crew.
Critical specifications include filming aboard the RV Atlantis with access to power and Wi-Fi, underwater and submersible filming capabilities, and safety-related access restrictions. The contractor will be responsible for their own travel, lodging is provided on the vessel, and deliverables include a short X<10 minute overview video and rough cut at the cruise's conclusion. The period of performance is 06/12/2025 to 06/11/2026, with payment contingent upon full project completion. The documentary-style project requires the contractor to work flexibly in shared spaces, use battery-powered equipment, and prioritize deep sea exploration visual content.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFq_Questions_cruise_0001.pdf | ||
| Sol_140G0325Q0122.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140G0325Q0122 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
GSB
SACRAMENTO CA 95819-6027
3020 STATE UNIVERSITY DRIVE EAST
MODOC HALL, CSUS
USGS OAG SACRAMENTO ACQUISITION BR.
05/29/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/21/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to extend the hours and date for receipt of offers and provide questions and answers to potential vendors. Please see attached for Q&A. The amendment is hereby extended to 06/03/2025 0700 PD.
Email quote and documents to: Anthony Berry at aberry@usgs.gov
Q&A
1. Question: Is the film crew to stay onboard RV Atlantis the entirety of the research trip?
Answer: Yes
2. Question: Is there a need to be prepped for underwater filming not in a watercraft
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Gerald Lewandowski
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140G0325Q0122/0001
(submersible camera)?
Answer: Yes
3. For filming in a submarine or other underwater vehicle are they pressure regulated?
Answer: Yes
4. Question: Is there a size restriction for cameras used in submarine?
Answer: Yes the sub crew will provide contractor with size restrictions.
5. Question: Is there access to power supply for charging equipment and data management?
Answer: Yes
6. Question: is there access to Wi-Fi or satellite communication on board?
Answer: Yes
7. Question: Are there windows for research work and filming or is it continuous 24 hours per day
Answer: Dependent upon operations and schedule.
8. Question: Are there opportunities to film boat to boat?
Answer: no
9. Question: Is 16MM film required?
Answer: No
10. Question: Will payment be for work on completion or as parts of the project are completed?
Answer: When the entire project is completed.
11. Question: Is there a designated area aboard the RV Atlantis for scientific sample and content photography, or should we plan to work flexibly in shared spaces? If a designated space is available, approximately how much room should we expect for deploying a mobile studio setup?
Should we anticipate access to standard 120V power during photography sessions, or plan to operate fully on battery power?
Answer: Plan to work flexibly in shared spaces, its best to plan to work on battery with ability to charge.
12. Question: Are measurement scales or other additions required in scientific images? Will materials such as shooting surfaces and scales be available on board, or should we supply these scientific set materials?
Answer: Scales are required for scientific images, scales and surfaces will be provided.
13. Question: Is there an estimated footprint for available equipment storage space
Answer: No not at this time.
14. Question: Would you prefer to see sample Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140G0325Q0122/0001 imagery and video embedded directly within the quote document, linked externally (e.g., portfolio site), or is such media not required or preferred for this solicitation?
Answer: Not required
15. Question: Given the remoteness of the location and limited commercial flight availability to Dutch Harbor in early June, we are evaluating commercial standby options as well as charter flights. Are any travel coordination resources available through the agency, or is travel to and from Dutch Harbor solely the responsibility of the contractor?
Answer: Responsibility of the Contractor
16. Question: Will USGS be providing a shot list or specific creative direction, or is content development expected from the contractor?
Answer: USGS will work with contractor but defer to contractor¿s expertise and experience
17. Question: Are there any restrictions on the use of drone footage, or FAA compliance requirements specific to the location?
Answer: Dependent on ship operation
18. Can you elaborate on the scientific samples or activities that should be prioritized in the visuals?
Answer: Contractor should be familiar with deep sea exploration priorities
19. Will USGS coordinate the on-camera interviews, or is that expected to be managed by the contractor?
Answer: By contractor
20. Are there branding guidelines or previous content we should align with in terms of tone and style?
Answer: Documentary style
21. What level of access will be granted aboard RV Atlantis for filming, will crew have access to labs or restricted areas?
Answer: there will be some restrictions related to safety.
22. Is any off-ship filming required or expected (e.g., local events, land-based locations)?
Answer: there is the possibility of post cruise interviews.
23. Are there required milestones for post-production deliverables (e.g., draft review deadlines)?
Answer: Short X<10 minute overview video and rough cut of video at conclusion of the cruise
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140G0325Q0122/0001
24. Are there specific waivers, permits, or insurance endorsements required due to the marine or federal nature of the work?
Answer: Work will be conducted under USGS environmental compliance. Contractor will need personal liability insurance outlined in the statement of work.
25. How many full days of filming are expected during the cruise from June 13¿July 4, 2025?
Answer: The duration of the cruise
26. What is the anticipated daily filming schedule or working hours for the production crew?
Answer: The ship operates 24 hours so contractor will need to determine schedule to optimize filiming
27. Is there a recommended or typical crew size based on previous projects of this nature?
Answer: One person permitted.
28. Will adequate space and power access be available on board for equipment storage and charging
Answer: Yes
29. Is lodging provided aboard the RV Atlantis, or is the expectation that the crew will return to shore each night?
Answer: Lodging will be aboard the vessel
30. Is there a preference or incentive for including local Alaskan crew or adopting environmentally sustainable production practices
Answer: No.
Period of Performance: 06/12/2025 to 06/11/2026
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
File details come from the government source that posted it. Updated .