B08_Attachment_8_Updated_Statement_of_Work_2_0005.docx

DOCX document 37 KB Posted

Attached to
REPLACE DECK BOARDS W/COMPOSITE DECK BOA Federal contract opportunity
Solicitation number
140G0125Q0077
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This document is a Performance Work Statement (PWS) for the Wetland and Aquatic Research Center (WARC) in Lafayette, Louisiana, detailing a deck replacement project. The project requires removing the existing 2,500 sq ft swamp deck boards, substructure, benches, and rails, and reinstalling new composite or wood deck materials. The contractor must provide two separate pricing options: one for wood materials and another for composite materials, with work to be completed within 30 working days during normal business hours (Monday-Friday, 7:30 am to 4:00 pm).

The solicitation (RFQ 140G0125Q0077) is managed by the US Geological Survey, with an estimated construction magnitude between $100,000 and $250,000. The procurement is open to small businesses, with a site visit scheduled for May 20, 2025, and additional site visit on July 30, 2025. The solicitation has undergone multiple amendments, with the current closing date set for August 5, 2025, at 10:00 am Pacific time. Interested contractors must be registered in SAM.gov, comply with all safety codes, and coordinate closely with USGS staff to minimize disruption to center operations.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE DECK BOARDS W/COMPOSITE DECK BOA, newest first.
File Type Posted
B09_Attachment_9_Questions_and_Answers_Amendment_5_0005.docx DOCX document
Sol_140G0125Q0077_Amd_0005.pdf PDF
Sol_140G0125Q0077_Amd_0004.pdf PDF
Sol_140G0125Q0077_Amd_0003.pdf PDF
B08_Attachment_7_Updated_Statement_of_Work_0003.docx DOCX document
Sol_140G0125Q0077_Amd_0002.pdf PDF
Sol_140G0125Q0077_Amd_0001.pdf PDF
Sol_140G0125Q0077.pdf PDF
B08_Attachment_4_Statement_and_Acknowledgement_of_Subcontractor_SF1413-13e.pdf PDF
B08_Attachment_5_Payroll_WH-347.pdf PDF
B08_Attachment_6_Statement_of_Work.docx DOCX document
B08_Attachment_2_Payment_Bond_SF25A-16d.pdf PDF
B03_Attachment_1_WD_LA20250039.pdf PDF
B08_Attachment_3_Form_DI-137_Release_of_Claims.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wetland and Aquatic Research Center Lafayette, LA

PROJECT TITLE:

Replace Swamp Deck

SECTION C. PERFORMANCE WORK STATEMENT

C.1. INTRODUCTION

The Wetland and Aquatic Research Center (WARC) is located and enclosed within a fenced in area consisting of approximately 19 acres of University of Lafayette Louisiana (ULL) property with a total of 107,361 SQ FT of building space. The WARC requires the replacement of the center’s swamp deck boards with 2,500 sq ft of new composite deck boards.

C.2. BACKGROUND

The Swamp deck boards are original to the building and is aging dramatically and becoming unsafe. The deck area is a center piece of the center, and personnel use it daily for many activities.

C.3. SCOPE

Requirement involves removing the existing swamp deck boards, sub structure, benches & rails and reinstalling new 2,500 sq ft of boards, substructure, rails & benches.

C.4. TECHNICAL REQUIREMENTS AND DELIVERABLES

C.4.1. Remove all current wooden deck sub structure, benches, rails and deck boards.

C.4.2. Labor and materials to replace all sub structure, benches, rails and deck boards.

C.4.3. Install new: all sub structure, benches, rails and deck boards (2,500 sq’).

C.4.4. Provide 2 separate prices: (1) with wood materials (2) with composite materials.

C.4.5. Remove all trash and old deck boards off site.

C.4.6. Changes/Clarifications: All work must be completed as shown in the contract documents. “No cost” change orders shall be submitted in writing to the Contacting Officer (CO) detailing why the work cannot be completed as shown and suggesting corrective action(s) by the contractor. The CO shall provide written consent to the proposed changes before the contractor may proceed with the changed work. The Contacting Officer’s approval must be received before commencing work which will alter the price, scope or terms of the contract.

C.4.7. Special Conditions: The work completed under these specifications shall be on the highest professional quality and craftsmanship. All materials furnished herein shall be complete and in compliance with manufacturer’s recommendations and designs. Contractor shall supply all components of the specified materials utilized as recommended by the manufacturer, whether specifically designated in these specifications or not.

C.4.8. The Contractor is responsible for compliance with all Federal, State, and Local Safety codes that are applicable to hazard material, electrical and fire codes. If there are any conflict between these specifications and codes, the stringent requirement shall apply.

C.4.9. Disposal and Transporting of Debris and Material: All materials and construction debris shall be removed from the work area and placed in an approved dumpster or removed from the site by the contractor on a daily basis.

C.4.10. Materials and Tools: The COR shall designate areas where the contractor can store or place materials and equipment for short-term storage in preparation for installation. There is limited space on site for the storage of contractor equipment. Storage and security of materials and equipment as required for the performance of the contract requirements are the responsibility of the contractor. The contractor shall be responsible for making all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site. Upon completion of the contract, the contractor shall remove all equipment and excess materials, and shall restore the site to its original condition, as approved by the COR, at no additional cost to the Government.

C.4.11. Contractor Smoking Regulations: There shall be no smoking in any buildings at any time; smoking is permitted in designated smoking areas only.

C.4.12. All work must be performed during normal business hours, Monday-Friday 7:30 am to 4:00 pm. No weekend work may be performed unless authorized by COR. No work may be performed on Federal holidays without exception.

C.4.13. All material and equipment are to be provided by the contractor. No tools, equipment or manpower will be provided by the facility. No government employees will assist contractor with unloading, installation or positioning of materials or equipment. Equipment may be stored in gated area surrounding job site during the period of performance, but the facility assumes no liability against loss or theft.

C.4.14. All material and equipment are to be provided by the contractor. No tools, equipment or manpower will be provided by the facility. No government employees will assist contractor with unloading, installation or positioning of materials or equipment. Equipment may be stored in gated area surrounding job site during the period of performance, but the facility assumes no liability against loss or theft.

C.5 SUPPORTING INFORMATON

C.5.1. Place of Performance

Wetland and Aquatic Research Center 700 Cajundome Blvd 70506 Lafayette LA 70506

C.5.2 Period of Performance

30 working days

C.5.3 Government Furnished Property N/A

5.5.4 Special Considerations

The contractor must be able to complete renovations with little disruption to workers. The contractor must coordinate work directly with the USGS staff at the Wetland and Aquatic Research Center. The contractor must comply with all OSHA standards during all phases of the contract. Contractor must have a valid contractor’s licensing.

image1.jpg

File details come from the government source that posted it. Updated .