140G0122Q0051 Amendment 002 Questions and Answers

1) What does CERC plan to do during the installation period of the AHU?

a. We will maintain the space if necessary during installation with our own portable AC units.

2) Will the lab area (that this unit serves) be in operation, or will it be vacated?

a. It will be operational however if we need to have the space unoccupied for a couple of days we can.

3) If occupied, you will need an alternate HVAC source to condition the air?

a. No.

4) If the space is planned to be vacated, do you require the air to be temporarily conditioned with an auxiliary HVAC unit provided by contractor?

a. No.