This document is a Revised Schedule of Items for a construction services contract to rehabilitate Quarters 2 at the Culebra National Wildlife Refuge in Culebra, Puerto Rico. The solicitation number is 140FHR24R0008, and the contracting agency is the Department of the Interior Fish and Wildlife Service.
The Schedule of Items includes a base bid for tasks such as mold detection, exterior wall repair, storm shutter repair, interior wall and door repair, floor tile cleaning, and replacement of a propane tank concrete storage structure. There are also two option tasks for mold mitigation and roof repair. Contractors are required to provide pricing and cost element breakdowns for each item listed. The total for the base bid tasks and option tasks is provided. This document provides the required pricing information for contractors to submit bids in response to the federal contract opportunity.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISED SCHEDULE OF ITEMS
for
Construction Services for Quarters 2 Rehabilitation Project at the Culebra NWR, Culebra, Puerto Rico
BASE BID TASKS (10-60)
OPTION TASKS (70-80)
CLIN Number Description Quantity Unit Amount
70 Mold Mitigation Square Foot $
80 Roof Repair 1 Lump Sum $___________
TOTAL (BASE BID + OPTION
TASKS (10-80)
NOTE:
Provide pricing and cost element break downs for each of the items listed.
CLIN Number Description Quantity Unit Amount
10 Mold Detection 1 Lump Sum $
20 Repair and Repaint Damaged Exterior Walls
1 Lump Sum $
30 Repair Damaged Storm Shutters
1 Lump Sum $
40 Repair Damaged Interior Walls and Doors
1 Lump Sum $
50 Deep Clean Floor Tiles 1 Lump Sum $
60 Replace Propane Tank Concrete Storage Structure
1 Lump Sum $
TOTAL (BASE BID