FWS – Dirt Moving and Levee Construction – RFQ Questions (140F1B23Q0004)
Solicitation (RFQ) Questions and Responses:
1. I'm writing to confirm the project magnitude, is this magnitude accurate?
Yes, the magnitude indicated in the solicitation is correct.
2. I was wondering that per Line item #2, number 3 states that the levee is to be built utilizing dirt pans. Would we be able to use off road haul trucks in lieu of pans for this project? If there is any issue with obtaining proper compaction, would using a sheeps foot roller be an option?
Off road haul trucks should not be used in lieu of pans. A dirtpan is preferable due to the levee compaction that they provide and the precision of pans with regards to topsoil placement on top of the levee upon completion.