This statement of work outlines requirements for the design and installation of a ground-mounted solar photovoltaic system at the Camas National Wildlife Refuge in Idaho. The project includes three options for system sizes of 100kW, 200kW, and 300kW to be approved by the local utility. The selected contractor will complete design, permitting, installation, testing, training, and warranty registration for the turnkey solar system. Key deliverables include preliminary and final design drawings, weekly progress photos and reports, component submittals, as-built drawings, operations and maintenance manuals, estimated maintenance costs, and system training materials. Work must comply with applicable building codes and utility interconnection standards. The period of performance is 365 days from notice to proceed. The federal agency involved is the U.S. Fish and Wildlife Service.

View the file

Other files for this federal contract opportunity

Other files attached to ID-CAMAS NWR GAOA WATER CONTROL PROJECT, newest first.
File Type Posted
Sol_140F0821R0004_Amd_0006.pdf PDF
Updated_Amendment_0005_Bid_Schedule_Solar_0005.pdf PDF
Updated_Amendment_0005_SOLAR_PV_SYSTEM_COMBINED_DRAWINGS_20210614_0005.pdf PDF
140F0821R0004_Amendment_0005_Q_A_ResponsesV3_0005.pdf PDF
Sol_140F0821R0004_Amd_0005.pdf PDF
Sol_140F0821R0004_Amd_0004.pdf PDF
Sol_140F0821R0004_Amd_0003.pdf PDF
Sol_140F0821R0004_Amd_0002.pdf PDF
Sol_140F0821R0004_Amd_0001.pdf PDF
DOL Wage Determinations.pdf PDF
Price Schedule.pdf PDF
Camas NWR PV Array Drawings.pdf PDF
Site Visit Instructions.pdf PDF
Past Performance Work Sheet.pdf PDF
Scope Narrative.pdf PDF
Sol_140F0821R0004.pdf PDF
Camas NWR PV Array SOW.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Camas NWR Water Delivery System Upgrades Solar System Camas NWR, ID

11 June, 2021

1. GENERAL:

1.1 The US Department of the Interior has a request for Construction contract to design and install a ground mounted solar system at Camas NWR, ID. The US Department of the Interior owns and operates the Camas National Wildlife Refuge (Camas NWR), located at 2150 E 2350 N near Hamer, Idaho. The main entrance facility is located west of Veterans Memorial Highway (Interstate 15) off of E 2350 N.

1.2 Work will include, but is not limited to, the design and installation of a ground based solar array that shall connect to the local power grid and offset power utilized by the NWR facilities. Solar system design shall include three system sizes and capacities: a 100kW-DC system, a 200kW-DC system and 300kW-DC system. Design is not required to accommodate future expansion of the PV array. The constructed size and capacity of the system will be 100kW, 200kW or 300kW as approved by the utility through coordination, generation application and review.

1.3 Work shall include the coordination with the utility provider, Rocky Mountain Power (RMP), to install a “PV Meter”; establishment of Electric Grid Interconnection Agreements for a federal facility to allow the solar system to be connected to the RMP grid, and all tasks and communication necessary to secure required systems approvals from RMP and all agencies having jurisdiction . All components selected shall be RMP approved. The contractor shall construct and install the system in accordance with all applicable codes and standards specifically the 2020 NEC and IEEE. NWR has included a preliminary design for reference.

1.4 Cultural resource assessment and review at the project site has been initiated by USFWS but has not been completed. Assessment and review is anticipated to completed in Fall 2021, and will be completed no later than December 31, 2021. Contractor shall not begin site disturbing activities until cultural resource assessment and review has been completed by USFWS.

1.4 Performance Period: 365 days from NTP

2. DEFINITIONS: N/A

3. SCOPE:

Work shall include but not necessarily limited to the design and installation of a ground mounted based solar power generating system. System design shall include three system sizes:

a. a 100kwW-DC system that can connect and provide 140,000kWh annually (as calculated using the NREL.gov tool)

b. a 200kW-DC system that can connect and provide 300,000kWh annually (as calculated using the NREL.gov tool)

c. a 300kW-DC system that can connect and provide 450,000kWh annually (as calculated using the NREL.gov tool)

Solar system is expected to assist in offsetting power utilized by the Refuge throughout the year. Contractor shall use the included preliminary PV design for the basis of the project.

Contractor shall review the proposed system; provide key components as required to ensure all components are compliant and on the approved RMP equipment list for connection to their system.

Contractor shall:

1) Complete the design of ground based solar power systems;

2) Pre-coordinate the proposed design with RMP;

3) Obtain RMP approval of proposed design;

4) Install the system of the size and capacity approved by RMP;

5) Test the system;

6) Coordinate with RMP for the appropriate meter installation;

7) Perform all tasks and communication required to secure approvals from RMP and all agencies having jurisdiction to complete construction of the system, connection of the system to the RMP grid, and activation of the system;

8) Provide all construction, infrastructure, fieldwork, testing, commissioning, coordination, documentation required to complete construction of the system, connection of the system to the RMP grid, and activation of the system.

TASK 1: Site Investigation, Development of System Shop Drawings

1) This task shall include a site visit to collect the necessary information needed to draft a detailed design documents / Shop Drawings that shall further develop the proposed Grid-Interactive solar PV array system.

2) Design shall include component locations, wire connections from the solar array to the inverters, list of all system components (including rapid shut-down controls), detailed summary of the system capabilities, line diagram in latest version of

AutoCAD.

3) Basis of Design components are: LG NEON Series 2 High Efficiency Solar Panels and SMA Core 1 Inverters. Alternates are acceptable provided that they are considered equivalent by the owner (or owner’s designated representative).

4) Proposed system shall utilize “premium grade” UL listed Solar Panels, be balanced to include solar combiners, grounding, disconnects, and related hardware, associated schematics, testing reports, performance analysis and structural engineering analysis as required.

5) System shall be designed with a 25-year life cycle. Panels shall include a 25-year warranty and inverter shall include a 15-year warranty.

6) Size and orient the PV array to provide the expected electrical power and energy.

7) Design shall ensure the installation site is capable of handling the desired system size.

Design shall specify sunlight and weather resistant materials for all outdoor equipment.

8) Design shall locate the array to eliminate shading from nearby elements and itself.

9) Design the system in compliance with all applicable building and electrical codes, see detailed list below.

10) Design the system with a minimum of electrical losses due to wiring, fuses, switches, and inverters.

11) Design shall allow for construction three sizes and capacities of PV array depending on utility approval, 100kW, 200kW and 300kW. Design is not required to accommodate future expansion of the PV array, system size and capacity approved by the utility will be the basis for the constructed system.

12) Contractor shall ensure the design meets local utility interconnection requirements.

Design shall meet Seismic Design Category D and wind load ASCE 7-05 (110 mph for California Building Code) with a snow load based on Hamer, ID.

13) Contractor shall obtain all permits and approvals required to complete construction of the project.

14) Contractor shall prepare and submit required utility interconnection agreement documents. Camas NWR staff will provide signatures for agreement documents if required. Please note, USFWS currently has no agreements in place with RMP for grid-tied solar at Camas NWR.

Task 1 Deliverables:

_1_ electronic Preliminary Shop Drawing set to include system schematic, component summary, cut sheets, and one-line diagram for Owner review. (PDF format)

_1_ electronic Final Shop Drawing set to include system schematic, component summary, cut sheets, one-line diagram, and RMP review and approval of the proposed design. (PDF format)

Meeting and Teleconference Discussion Notes for all communications with USFWS, RMP and agencies having jurisdiction (PDF format)

Any drawings created in AutoCAD file format (NWR CAD standards apply and are attached)

TASK 2: System Installation

1) System shall be installed by Idaho licensed professionals.

2) It is recommended the contractor follow the applicable Jefferson County Planning, Zoning and Building Department design and plan checklists for ground mount PV Solar Systems.

3) Construct and install the ground-mounted systems shall be commercial grade and installed as part of a permanent system.

4) Construct and install the solar panels and associated inverter, wiring, conduit, system components, etc.

5) Angle the system per shop drawings and design calculations for maximum generation.

6) Install required junction boxes, panels, accessories, etc. as needed to support the system.

7) All panels shall be labeled with typed information on weather resistant material.

Label shall be Mylar or equivalent that are durable, fade-resistant UV ink that keeps the labels readable for years. Such as the highest quality polyester and vinyl materials that create a scuff-proof, smudge-resistant product that resists tears and rips.

8) Contractor shall be responsible for all refuse and debris collection and removal associated with the project; contractor shall provide documentation all debris was properly disposed of.

9) Contractor shall provide restrooms for workers.

10) Contractor shall ensure the installation area site is capable of handling the desired system size and loading by provided structural calculations to support the loads.

11) Contractor shall properly seal “any and all” penetrations with industry approved sealing methods.

12) Install equipment according to manufacturer’s specifications, using installation requirements and procedures from the manufacturers' specifications.

13) Properly ground the system parts to reduce the threat of shock hazards and induced surges.

14) Check for proper PV system operation by following the checkout procedures on the PV System Installation Checklist.

14) Ensure the design meets local utility interconnection requirements.

15) Have final inspections completed by the Authority Having Jurisdiction (AHJ) and the utility (if required).

16) Work hours for the facility are 7:30am – 4:30pm, but the contractor may request extended work hours during construction. However, all inspectable items must be completed during normal work hours and the contractor shall notify the government contracting officer’s representative at least 48-hours prior to any inspection requirements.

Task 2 Deliverables:

System Installation and testing Weekly photos of the project progress

Daily reports (completed on days during active construction) Submittals for all system components (PDF format) Meeting minutes/notes from discussions with RMP, USFWS and agencies having jurisdiction

TASK 3: System Connection, As-Built Drawings, O&M Manuals, Detailed Maintenance Costs, System Training:

1) Contractor shall check and make all required connections to the facility and to the RMP grid as required by the interconnection agreement.

2) Provide the NWR with “As-Built” drawings in AutoCAD format.

3) Provide electronic copy and one printed copy of the O&M manuals for all system components.

4) Register all warranties on behalf of the NWR. Contractor shall provide 12-month full labor and material replacement warranty of system after project acceptance by the Owner.

5) Provide estimated annual maintenance costs for the system and detail to the NWR what those tasks require.

6) Provide NWR required closeout documents for federal construction contracts.

Task 3 Deliverables:

_1_ electronic set of design drawings t (PDF format)

_1_ Copy of all permits (PDF format)

_1_ Copy of O&M manuals (PDF format)

_1_ Copy of As-built drawings (PDF format and AutoCAD)

_1_ Copy of letter stating all components were installed IAW applicable codes, standards, and design. (PDF format)

_1_ Copy of all warranties (PDF format)

_1_ Copy of Estimated Maintenance Costs (PDF format)

_1_ Copy of Training materials (PDF format)

_1_ Copy of all photos taken during construction (jpg or pdf)

4. APPLICABLE CODE ENFORCEMENT:

Work shall be performed in accordance with the following applicable codes:

1) Uniform Building Code

2) Current NFPA

3) IEEE Standards

4) 2020 National Electric Code

5) Idaho Building Codes

6) RMP Interconnection Rules and Standards

7) Other applicable standards required by local jurisdictions

8) Federal construction standards as applicable to the system installation

5. ATTACHMENTS:

1) Preliminary Design Documents

2) USFWS CAD Standards

3) USFWS Submittal Form

4) USFWS Safety Checklists

5) USFWS General Requirements

6. INSPECTION AND ACCEPTANCE:

Work shall be performed in accordance with the requirements of this SOW. Work shall be accepted when all the work is completed as described herein.

7. GOVERNMENT FURNISHED EQUIPMENT:

The NWR will provide all available record drawings related to the project location.

8. PROJECT LOCATION AND AVAILABILITY:

The project is located at the Camas National Wildlife Refuge, located at 2150 E 2350 N Hamer, ID 83425.

Normal work hours at the station are 7:30am to 4:30pm, Monday through Friday, excluding Holidays. Coordinate with staff if access to the site is required. Extended work periods, weekend work periods and evening work period maybe requested and shall be approved based on hatchery staff availability.

9. CONTACTS:

USFWS Project Manager

Rob Moriarty Project Execution Branch, Infrastructure Management Division US Fish and Wildlife Service Legacy Regions 1, 7 & 8 911 NE 11th Avenue Portland, OR 97232-4181

Office: 503-736-4440 Cell: 971-347-6812 Email: lynn_moriarty@fws.gov

Camas NWR Refuge Manager

Brian Wehausen Refuge Manager - Camas NWR 2150 E 2350 N Hamer, ID 83425 Office: (208) 662-5423 Cell: (208) 241-5410 Email: brian_wehausen@fws.gov

File details come from the government source that posted it. Updated .