Atch 2 Specifications Sand Settling Basin.pdf
PDF 2 MB Posted
- Attached to
- REHAB HOTCHKISS NFH SAND SETTLING BASIN
- Solicitation number
- 140F0620R0004
About this file
This document outlines the scope of work for a federal contract opportunity to rehabilitate the sand settling basin at the Hotchkiss National Fish Hatchery. The work includes selective demolition, piping and fencing revisions with the addition of a flow meter, construction of a floor drain and weir, a piped decant system, asphalt paving, installation of a pre-engineered fabric structure and concrete-lined swale to create a complete and operational facility. The point of contact is listed as the Contracting Officer from the Department of the Interior Fish and Wildlife Service.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Modify Sand Settling Basin
Hotchkiss National Fish Hatchery
U.S.
FISH & WD,DLIFE
SERVICE
Technical Specifications
August 19, 2019
THIS PAGE IS INTENTIONALLY BLANK
STANTEC - 2242020172 TABLE OF CONTENTS
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE TOC - 1
TABLE OF CONTENTS
DIVISION 01: GENERAL REQUIREMENTS
011000 SUMMARY ...................................................................................................... 4 PAGES
012500 SUBSTITUTION PROCEDURES ................................................................... 4 PAGES
012600 CONTRACT MODIFICATION PROCEDURES ............................................. 2 PAGES
012900 PAYMENT PROCEDURES ............................................................................ 4 PAGES
013100 PROJECT MANAGEMENT AND COORDINATION ..................................... 8 PAGES
013200 CONSTRUCTION PROGRESS DOCUMENTATION ................................... 4 PAGES
013300 SUBMITTAL PROCEDURES ....................................................................... 10 PAGES
SUBMITTAL LIST ............................................................................................ 4 PAGES
014000 QUALITY REQUIREMENTS ........................................................................ 18 PAGES
015000 TEMPORARY FACILITIES AND CONTROLS .............................................. 4 PAGES
016000 PRODUCT REQUIREMENTS ........................................................................ 6 PAGES
017300 EXECUTION .................................................................................................... 8 PAGES
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL ..................... 4 PAGES
017700 CLOSEOUT PROCEDURES .......................................................................... 6 PAGES
017823 OPERATION AND MAINTENANCE DATA ................................................... 8 PAGES
017839 PROJECT RECORD DOCUMENTS .............................................................. 4 PAGES
DIVISION 02: EXISTING CONDITIONS
024119 DEMOLITION AND RECONSTRUCTION ..................................................... 6 PAGES
DIVISION 03: CONCRETE
033150 CAST-IN-PLACE CONCRETE ..................................................................... 22 PAGES
036000 GROUT .......................................................................................................... 10 PAGES
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE TOC - 2
DIVISION 05: METALS
055000 MISCELLANEOUS METALWORK ...........................................................8 PAGES
DIVISION 13: SPECIAL CONSTRUCTION
131310 PRE-ENGINEERED FABRIC STRUCTURE ............................................6 PAGES
DIVISION 26: ELECTRICAL
260000 ELECTRICAL BASIC REQUIREMENTS ................................................ 10 PAGES
DIVISION 31: EARTHWORK
311000 SITE PREPARATION ..............................................................................2 PAGES
313000 EARTHWORK ........................................................................................... 12 PAGES
DIVISION 32: EXTERIOR IMPROVEMENTS
321113 ASPHALT CONCRETE PAVEMENT AND BASE .................................. 10 PAGES
DIVISION 33: UTILITIES
330516 PRECAST CONCRETE VAULTS ............................................................4 PAGES
339220 DUCTILE IRON PIPING .............................................................................. 6 PAGES
339540 SMALL POLY VINYL CHLORIDE NON-PRESSURE PIPING,
RUBBER JOINTS ....................................................................................... 4 PAGES
339553 POLY VINYL CHLORIDE PRESSURE PIPING,
RUBBER JOINTS ....................................................................................... 6 PAGES
DIVISION 40: PROCESS INTERCONNECTIONS
405000 PIPING GENERAL .................................................................................... 10 PAGES
409102 IN-LINE LIQUID FLOW MEASURING DEVICES ...................................... 4 PAGES
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE TOC - 3
DIVISION 43: MATERIAL HANDLING EQUIPMENT
433014 BUTTERFLY VALVES ................................................................................ 2 PAGES
END OF TABLE OF CONTENTS
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE TOC - 4
THIS PAGE IS INTENTIONALLY BLANK
STANTEC - 2242020172 SUMMARY
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 011000 - 1
SECTION 011000 – SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Use of premises.
3. Government occupancy requirements.
4. Specification formats and conventions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Modify Sand Settling Basin, Hotchkiss NFH.
1. Project location: The project is located at the Hotchkiss National Fish Hatchery.
The Hotchkiss NFH is located about 20 miles east of Delta, CO near the town of Hotchkiss. From Delta follow Colorado Highway 92 east for approximately 17 miles to 3100 Road. Turn right onto 3100 Road and travel south for one and a half miles to the town of Lazear. Turn left into Lazear Road for half of a mile and then turn right onto Hatchery Road. Remain on Hatchery Road for less than a mile to the Hatchery Entrance.
2. Mailing Address: Hotchkiss NFH, 8077 Hatchery Road, Hotchkiss, CO 81419
3. Geographic Address: Hotchkiss NFH, 8077 Hatchery Road, Hotchkiss, CO 81419
B. Technical Coordinators:
1. FWS Point of Contact:
US Fish and Wildlife Service Division of Engineering, R-6 143 Union Boulevard Lakewood, CO 80228 Phone: 303-236-4470 Email: peggy_mott@fws.gov
2. Hatchery Point of Contact:
Craig Eaton Hotchkiss NFH 8077 Hatchery Road Hotchkiss, CO 81419 Phone: 970-872-3170 Email: craig_eaton@fws.gov mailto:peggy_mott@fws.gov mailto:craig_eaton@fws.gov
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 011000 - 2
C. The Work includes modification to an existing sand settling basin including:
1. Selective demolition of concrete, piping, and fencing,
2. Inlet and outlet piping revisions including addition of a flow meter,
3. Construction of a floor drain in the settling basin,
4. Installation of a weir in the outlet chamber,
5. Construction of a piped decant system,
6. Asphalt paving of the basin’s access road,
7. Installation of a pre-engineered fabric structure over the basin,
8. Construction of a concrete lined swale,
9. Other work for a complete and operational facility.
D. Project will be constructed under a single prime contract.
1.3 USE OF PREMISES
A. Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits.
B. Schedule operations so that Work is conducted during regular office hours which are
7:00 am to 7:00 pm, Monday through Friday. No work on Saturday, Sunday or federal holidays is allowed without the specific, written permission of the Hatchery Manager.
C. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
D. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Government Occupancy: Allow for Government occupancy of Project site and use by the public. Government personnel will be continuously occupying areas of the buildings immediately adjacent to the work area. Conduct work in a manner that will minimize needs for disruption of normal Government operations. Provide minimum 72 hours advance notice to Contracting Officer of activities that will impact normal Government operations. Secure Contracting Officer's written approval of activities that will impact normal Government operations to avoid delays in overall construction and permit proper installation or work.
2. Deliveries and material storage locations are subject to approval of the Hatchery Manager.
3. Driveways and Entrances: Keep driveways, parking areas, loading areas, and entrances serving premises clear and available to Government, public, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 011000 - 3
E. Utilities:
1. Service interruptions of electric power and potable water utilities will be allowed for short periods of time per schedule approved by Contracting Officer.
Interruptions to the fish rearing water supply are not allowed at any time. All diversions or changes to the water supply system for the hatchery shall be performed by hatchery personnel only.
2. The Contractor shall provide and have available at the project site pipeline repair materials and equipment including repair sleeves, couplings, and pipe to provide immediate repair to any damage inflicted by the contractor or any subcontractor to the water supply and distribution system.
1.4 GOVERNMENT OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy site and existing adjacent buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government and public usage. Perform the Work so as not to interfere with Government day-to-day operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
1.5 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 43-division format and CSI/CSC's "MasterFormat" numbering system.
1. Division 01: Sections in Division 01 govern the execution of the Work of all
Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract
Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 011000 - 4
fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context are implied where a colon (:) is used within a sentence or phrase.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
STANTEC - 2242020172 SUBSTITUTION PROCEDURES
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 012500 - 1
SECTION 012500 – SUBSTITUTION PROCEDURES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Government that are not required in order to meet other Project requirements but may offer advantage to Contractor or Government.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Government and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes such as
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 012500 - 2
performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects with project names and addresses and names and addresses of Contracting Officers and Governments.
h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project.
j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
2. Contracting Officer's Action: If necessary, Contracting Officer will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Contracting Officer will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or
Contracting Officer's Supplemental Instructions for minor changes in the Work.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 012500 - 3
approved substitutions.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Contracting Officer will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the
Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Contracting Officer will consider requests for substitution if received within 60 days after commencement of the Work. Requests received after that time may be considered or rejected at discretion of Contracting Officer.
1. Conditions: Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Contracting Officer will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Government must assume. Government's additional responsibilities may include compensation to Contracting Officer for redesign and evaluation services, increased cost of other construction by Government, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 012500 - 4
will produce indicated results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the
Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
END OF SECTION 012500
STANTEC - 2242020172 CONTRACT MODIFICATION PROCEDURES
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Contracting Officer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.4 PROPOSAL REQUESTS
A. Government-Initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Contracting Officer are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or 30 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use forms acceptable to Contracting Officer.
STANTEC - 2242020172 CONTRACT MODIFICATION PROCEDURES
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 012600 - 2
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Contracting Officer.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to Contracting Officer.
1.5 CHANGE ORDER PROCEDURES
A. On Government's approval of a Work Changes Proposal Request, Contracting Officer will issue a Contract Modification for signatures of Government and Contractor.
END OF SECTION 012600
STANTEC - 2242020172 PAYMENT PROCEDURES
HOTCHKISS NFH-REPLACE SAND SETTLING BASIN PAGE 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
2. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:
a. Application for Payment forms with continuation sheets.
b. Submittal schedule.
c. Items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Contracting Officer at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification
1. Identification: Include the following Project identification on the schedule of
HOTCHKISS NFH-REPLACE SAND SETTLING BASIN PAGE 012900 - 2
values:
a. Project name and location.
b. Name of Contracting Officer.
c. Contracting Officer's project number.
d. Contractor's name and address.
e. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703.
3. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value of the following, as a percentage of the Contract Sum to nearest one- hundredth percent, adjusted to total 100 percent.
1) Labor.
2) Materials.
3) Equipment.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.
a. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.
5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
6. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.
7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
8. Each item in the schedule of values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of
HOTCHKISS NFH-REPLACE SAND SETTLING BASIN PAGE 012900 - 3
actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.
1.5 APPLICATIONS FOR PAYMENT
A. Refer to FAR Clause 52.232-70 for electronic invoicing and payment requirements.
END OF SECTION 012900
HOTCHKISS NFH-REPLACE SAND SETTLING BASIN PAGE 012900 - 4
THIS PAGE INTENTIONALLY LEFT BLANK
STANTEC - 2242020172 PROJECT MANAGEMENT AND COORDINATION
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Requests for Information (RFIs).
3. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.
2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
A. RFI: Request from Government, Contracting Officer, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Contractor needs to submit each proposed subcontractor on a SF 1413 (Statement and Acknowledgment) in accordance with Paragraph (d)(1) of FAR Clause 52.222-11. SF 1413s need to be submitted with 14 days after award of the contract.
B. Key Personnel Names: Within 14 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 2
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
Coordinate use of temporary utilities to minimize waste.
1.6 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Contracting Officer will return RFIs submitted to Contracting Officer by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in
Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Contracting Officer.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the
RFI.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 3
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Form with substantially the same content as indicated above, acceptable to Contracting Officer.
1. Attachments shall be electronic files in Adobe Acrobat PDF format.
D. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and respond. Allow seven working days for Contracting Officer's response for each RFI. RFIs received by Contracting Officer after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Contracting Officer actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information, in which case Contracting Officer's time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract
Time or the Contract Sum, notify Contracting Officer in writing within 10 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Contracting Officer.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 4
6. Date the RFI was submitted.
7. Date Contracting Officer's response was received.
F. On receipt of Contracting Officer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven days if Contractor disagrees with response.
1. Identification of related Minor Change in the Work, Construction Change
Directive, and Proposal Request, as appropriate.
1.7 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Government and Contracting Officer of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Government and Contracting Officer, within three days of the meeting.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Government and Contracting Officer, but no later than 15 days after execution of the Agreement.
1. Conduct the conference to review responsibilities and personnel assignments.
2. Attendees: Authorized representatives of Government, Contracting Officer, and their consultants; Contractor and its superintendent; major subcontractors;
suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Lines of communications.
f. Procedures for processing field decisions and Change Orders.
g. Procedures for RFIs.
h. Procedures for testing and inspecting.
i. Procedures for processing Applications for Payment.
j. Distribution of the Contract Documents.
k. Submittal procedures.
l. Preparation of record documents.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 5
m. Use of the premises.
n. Work restrictions.
o. Working hours.
p. Responsibility for temporary facilities and controls.
q. Procedures for disruptions and shutdowns.
r. Parking availability.
s. Office, work, and storage areas.
t. Equipment deliveries and priorities.
u. Safety requirements.
v. First aid.
w. Security.
x. Labor laws.
4. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Government and Contracting Officer, but no later than 90 days prior to the scheduled date of Substantial Completion.
1. Conduct the conference to review requirements and responsibilities related to
Project closeout.
2. Attendees: Authorized representatives of Government, Government's
Commissioning Authority, Contracting Officer, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of record documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for completing sustainable design documentation.
e. Requirements for preparing operations and maintenance data.
f. Requirements for delivery of material samples, attic stock, and spare parts.
g. Requirements for demonstration and training.
h. Preparation of Contractor's punch list.
i. Procedures for processing Applications for Payment at Substantial
Completion and for final payment.
j. Submittal procedures.
k. Coordination of separate contracts.
l. Government's partial occupancy requirements.
m. Installation of Government's furniture, fixtures, and equipment.
n. Responsibility for removing temporary facilities and controls.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 6
D. Progress Meetings: Conduct progress meetings at biweekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Government and Contracting Officer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule.
Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of proposal requests.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
18) Documentation of information for payment requests.
4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 7
progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
PART 3 – EXECUTION (Not Used)
END OF SECTION 013100
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013100 - 8
STANTEC - 2242020172 CONSTRUCTION PROGRESS DOCUMENTATION
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 033200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Startup construction schedule.
2. Contractor's construction schedule.
3. Construction schedule updating reports.
4. Daily construction reports.
5. Material location reports.
6. Site condition reports.
7. Special reports.
1. Section 013300 "Submittal Procedures" for submitting schedules and reports.
2. Section 014000 "Quality Requirements" for submitting a schedule of tests and inspections.
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. Working electronic copy of schedule file, where indicated.
2. PDF electronic file.
B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 033200 - 2
C. Construction Schedule Updating Reports: Submit with Applications for Payment.
D. Daily Construction Reports: Submit at monthly intervals.
E. Site Condition Reports: Submit at time of discovery of differing conditions.
F. Special Reports: Submit at time of unusual event.
G. Qualification Data: For scheduling consultant.
1.5 COORDINATION
A. Coordinate Contractor's construction schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for commencement of the Work to date of final completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
B. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:
1. Startup and Testing Time: Include no fewer than 15 days for startup and testing.
2. Substantial Completion: Indicate completion in advance of date established for
Substantial Completion and allow time for Contracting Officer's administrative procedures necessary for certification of Substantial Completion.
3. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.
4. Indicate long-lead items that can disrupt major portions of work if not ordered in time.
C. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.
D. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 033200 - 3
2.2 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. List of subcontractors at Project site.
2. List of separate contractors at Project site.
3. Approximate count of personnel at Project site.
4. Equipment at Project site.
5. Material deliveries.
6. High and low temperatures and general weather conditions, including presence of rain or snow.
7. Accidents.
8. Meetings and significant decisions.
9. Unusual events (see special reports).
10. Stoppages, delays, shortages, and losses.
11. Meter readings and similar recordings.
12. Emergency procedures.
13. Orders and requests of authorities having jurisdiction.
14. Change Orders received and implemented.
15. Construction Change Directives received and implemented.
16. Services connected and disconnected.
17. Equipment or system tests and startups.
18. Partial completions and occupancies.
19. Substantial Completions authorized.
B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
2.3 SPECIAL REPORTS
A. General: Submit special reports directly to Government within one day of an occurrence. Distribute copies of report to parties affected by the occurrence.
B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Government in advance when these events are known or predictable.
PART 3 - EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 033200 - 4
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate final completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Contracting Officer, Government, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
END OF SECTION 013200
STANTEC - 2242020172 SUBMITTAL PROCEDURES
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1. Section 012900 "Payment Procedures" for submitting Applications for Payment and the schedule of values.
2. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.
3. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.
4. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.
5. Section 017900 "Demonstration and Training" for submitting video recordings of demonstration of equipment and training of Government's personnel.
A. Action Submittals: Written and graphic information and physical samples that require Contracting Officer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Contracting Officer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
D. Portable Document Format (PDF): An open standard file format licensed by Adobe
Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
HOTCHKISS NFH-MODIFY SAND SETTLING BASIN PAGE 013300 - 2
1.4 ACTION SUBMITTALS
A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Contracting Officer and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the…