Attachment II-Bid Schedule_0001.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
CARPET REPLACEMENT 3 WV-NCTC CAMPUS Federal contract opportunity
Solicitation number
140F0421R0019
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document contains an attachment with a bid schedule for a federal contract opportunity for carpet replacement at three NCTC campuses. The bid schedule provides unit pricing for various carpet installation and demolition line items including general requirements, selective demolition, flooring demolition, wood floor refinishing, carpet tile installation, and office partition removal and reinstallation. It also includes pricing for general contractor markups, general conditions, overhead and profit. The related federal contract opportunity is solicitation number 140F0421R0019 from the Department of the Interior Fish and Wildlife Service for carpet replacement services at three West Virginia NCTC campuses. Pricing is required for various carpet installation and demolition line items to complete the work.

View the file

Other files for this federal contract opportunity

Other files attached to CARPET REPLACEMENT 3 WV-NCTC CAMPUS, newest first.
File Type Posted
Attachment V-REQEUST FOR INFORMATION_0002.pdf PDF
Sol_140F0421R0019_Amd_0002.pdf PDF
Attachment I-B08-Solicitation 140F0421R0019_0001.pdf PDF
Attachment IV-B03-DOL Wage Determination_0001.pdf PDF
Sol_140F0421R0019_Amd_0001.pdf PDF
Attachment III-A06-Drawings Specifications_0001.pdf PDF
Sol_140F0421R0019.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1 Carpet

(Sub-Contracted)
01 General Requirements
013113200180Field personnel, project manager, minimumWeek
013113200240Field personnel, superintendent, minimumWeek
01 General Requirements Subtotal
02 Existing Conditions
024119190840Selective demolition, rubbish handling, dumpster, 40 C.Y., 10 ton capacity, weekly rental, includes one dump per week, cost to beWeek
added to demolition cost
024119192085Selective demolition, rubbish handling, haul and return, add per each extra 100' haul, wheeled, cost to be added to demolition costC.Y.
02 Existing Conditions Subtotal
09 Finishes
090505200400Flooring demolition, carpet, bonded, includes surface scrapingS.F.
090505200400Labor availability, shortage, add, modifications to total project cost summariesProject
096429107600Wood strip flooring, refinish, sand, 2 coats poly, wax, hardwoodS.F.
096805110107Carpet transition strip, clamp down brass divider 12'/each (@vinyl to carpet)Ea.
096813101180Carpet tile, tufted nylon, 35 oz., 18" x 18" or 24" x 24"S.Y.
096813101180Labor availability, shortage, add, modifications to total project cost summariesProject
09 Finishes Subtotal
15

15 Office Partition remove and reinstall, using furniture installation numbers minus materials costs x2

Subtotal
General Contractor's Markup on Subs
Subtotal
General Conditions
Subtotal
General Contractor's Overhead and Profit
Subtotal
Grand Total