Sol_140D0426R0010_Amd_0008.pdf
PDF 353 KB Posted
- Attached to
- Army Design-Build & Design-Bid-Build Construction Federal contract opportunity
- Solicitation number
- 140D0426R0010
About this file
This document is Amendment 0008 to a federal Indefinite Delivery/Indefinite Quantity (IDIQ) contract solicitation for construction services issued by the Department of Defense, specifically DEVCOM (Army Combat Capabilities Development Command) at Picatinny Arsenal, New Jersey. The amendment provides responses to industry questions regarding two SEED (Simplified Energy Efficiency Deployment) projects and updates to project documentation.
The two primary construction projects are: B717 Bathroom Renovation and B21 HVAC and Drainage System. The B717 project involves renovation of men's and women's restrooms and locker rooms, including replacement of ceiling grids, wall-mounted sinks with countertops, lighting fixtures, occupancy sensors, hand dryers, paper towel holders, toilet paper dispensers, paint, ceramic tile flooring with cove base, and bathroom partitions. Sealed engineering drawings are not required; sketches and submittals are acceptable. The B21 project encompasses removal and replacement of HVAC equipment (including a boiler-in-a-box and installation of a rooftop unit), installation of unit heaters, new electrical panels, gas line connections, perimeter drainage system installation, and control system integration with the base-wide BMS (Building Management System) using BACnet connectivity. Neither project requires formal PE-stamped design work; contractors must provide design submittals only. Key clarifications address site conditions including the absence of electrical as-built drawings, asbestos testing to be performed by government prior to Notice to Proceed, UXO (Unexploded Ordnance) sweep requirements for B21 excavation at government expense, and coordination with utility providers (Sussex Rural Electric Company for electrical service disconnection and New Jersey Natural Gas for gas service modifications). The solicitation establishes that the proposal submission deadline remains June 22, 2026, at 2:00 PM EDT. The document lists companies that attended pre-proposal site visits on April 7, 2026. All changes made in this amendment have been highlighted throughout the revised Statement of Work sections and supporting enclosures.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140D0426R0010_Amd_0007.pdf | ||
| Sol_140D0426R0010_Amd_0006.pdf | ||
| Sol_140D0426R0010_Amd_0005.pdf | ||
| Sol_140D0426R0010_Amd_0004.pdf | ||
| Sol_140D0426R0010_Amd_0003.pdf | ||
| Sol_140D0426R0010_Amd_0002.pdf | ||
| Sol_140D0426R0010_Amd_0001.pdf | ||
| Attachment_10_PPQ_0001.docx | DOCX document | |
| B08_SOL_Attachment_5_DOI_Release_of_Claims.pdf | ||
| B08_SOL_Attachment_2_-IDIQ_Key_Labor_Categories___Rates.xlsx | XLSX spreadsheet | |
| Sol_140D0426R0010.pdf | ||
| B08_SOL_Attachment_3_DBA_WD_NJ20240038_6_6_2025_(Dover__NJ).pdf | ||
| B08_SOL_Attachment_4_DBA_WD_NY20250002_7_25_2025_(Watervliet__NY).pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Angelina Clements
See continuation page
Interior Business Center, AQD Acquisition Services Directorate 381 Elden Street Suite 2000A Herndon VA 20170
D27
140D0426R0010
06/10/2026
03/25/2026
1 35
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140D0426R0010/0008
The purpose of this amendment is to provide responses to additional questions from industry received in response to Amendment 0007. The due date for the receipt of proposals is unchanged and is still June 22, 2026, at 2:00PM ED.
All changes have been highlighted below.
Revised SEED Project Attachments will not be provided.
DEVCOM Solicitation Questions
SEED Project - B717 Bathroom Renovation
Question # Question Response Reference 1 Ceiling Grid is in worse shape than expected. Original SOW specified ceiling tiles be replaced but ceiling grid reused.
SOW revised to reflect replacement of ceiling grid in rooms covered by the project.
See revised SOW sections 3.1.7, 3.1.10, 3.2.6, 3.2.7, 3.3.3, 3.3.4.
2 #2 - Original SOW specified singular, wall mounted sinks.
Functionality of sink area could be improved by a countertop instead of separate sinks.
SOW revised to reflect wall mounted, solid surface counter specified for both bathrooms.
See revised SOW sections 3.1.24, 3.2.22.
3 Please provide UFC spec/criteria 3-501-01, 3-250- 01 and 3-530-01
WBDG Home | WBDG - Whole Building Design Guide
4 Please project spec for LED light fixture
SOW revised to include basis of design light fixture.
See revised SOW sections 3.1.11, 3.2.10.
5 Please provide spec for ceiling mount occupancy sensor.
SOW revised to include basis of design light fixture.
See revised SOW sections 3.1.11, 3.2.10.
6 Who is providing elec. Hand dryer ?
Hand dryer to be contractor purchased, contractor installed.
7 Need equipment cut sheet of hand dryer.
Manufacturer or equal specified in SOW 3.1.14.
8 Need equipment cut of exhaust fan.
Propose exhaust fan for bathroom during submittal phase.
9 Any building controls required for the exhaust fan ?
No, this fan will be controlled by lighting circuit.
Light on, Fan on.
10 Are electrical as-built drawings available for this area indicating location of nearest electrical panels.
There are no electrical plans for B717 available.
The nearest electrical panel, which was 150 ft away, requiring surface mount conduit.
11 3.1. Men’s Restroom: 3.1.28.
Preparation of subfloor to receive, and installation of, a new Armstrong vinyl tiled floor and vinyl cove base or approved equal in storage area.
Colors to be selected by
Names of rooms clarified in updated SOW. Rooms shown in sketch are the construction limits for this project.
See revised SOW sections 3.3 and Enclosure 1.
https://www.wbdg.org/ https://www.wbdg.org/ https://www.wbdg.org/ customer. Question – Please confirm this is for the Break Room Area as shown in Enclosure 1 Men’s Restroom Layout attached above is in fact the Storage Room. If not please provide the size and location of the Storage Room. Also, provide a scope of work to occur in the Break Room, if required.
12 3.2. Women’s Restroom:
3.2.26. Preparation of subfloor
to receive, and installation of, a new Armstrong vinyl tiled floor and vinyl cove base or approved equal in storage area.
Colors to be selected by customer. Question – Please confirm the Storage Room is the Women’s Break Room area as shown in Enclosure 2 Women’s Restroom Layout attached above. If not please provide the size and location of the Storage area. Also, provide a scope of work to occur in the Break Room, if required.
Names of rooms clarified in updated SOW. Rooms shown in sketch are the construction limits for this project.
See revised SOW sections 3.3 and Enclosure 2.
13 3.3. Locker Room: Question - Where is the locker room? Is the Locker Room the Break Room as shown in Enclosure 2 Women’s Restroom Layout attached above? If not please provide the size and location of the Locker Room. Also, provide a scope of work to occur in the Break Room, if required.
Names of rooms clarified in updated SOW. Rooms shown in sketch are the construction limits for this project.
See revised SOW sections 3.3 and Enclosures 1 & 2.
14 Confirm that extent of job is to replace fixtures in existing locations in kind.
Yes, follow SOW.
15 Confirm floor drains are existing to remain.
Yes.
16 Confirm that layout of bathroom fixtures does not need to be modified to meet any codes/standards.
That is correct, layout remains.
17 Clarify the design/build requirements (i.e. are signed stamped drawings required).
Sealed drawings are not required for this project.
Sketches and submittals are acceptable.
18 Confirm there is no work in janitor’s closet.
There is no work in the janitor’s closet.
19 Section 8.4 references testing and commissioning. Please clarify extent of any testing and commissioning. Maybe none is required?
Functions, check and QA inspection. No testing or commissioning for B717 Bathroom project.
20 Can the Quality Control Manager (QCM) also serve as SSHO and/or Site Superintendent?
These positions can vary by complexity of project. For this project, it is acceptable to have all roles filled by Site Superintendent.
21 Please confirm the required number of key personnel for this scope.
Please see response to Question #20.
22 Can the Site Superintendent also serve as SSHO?
Please see response to Question #20.
23 Please confirm whether this is a design project. If so, identify the required design deliverables to support preparation of the project schedule.
This effort is not a design project.
24 Reference 3.1.13 hand dryer finish.
Stainless Steel
25 Reference 3.1.17 paint manufacturer.
Sherwin Williams
26 Reference 3.1.18 ceiling tile manufacturer and type. Also confirm if ceiling grid is to be included, if so please specify.
SOW revised to reflect replacement of ceiling grid in rooms covered by the project.
See revised SOW sections 3.1.7, 3.1.10, 3.2.6, 3.2.7, 3.3.3, 3.3.4.
27 Reference 3.1.20 bathroom partition height – specs.
SOW revised to include partition height.
See revised SOW sections 3.1.21 and 3.2.20.
28 Reference 3.1.26 paper towel, soap dispenser manufacturer and color.
SOW revised to include basis of design manufacturer and models.
See revised SOW sections 3.1.27, 3.2.25.
29 Confirm what toilet paper dispensers are to be supplied and installed.
Please see response to Question #28.
See revised SOW sections 3.1.27, 3.2.25.
30 Demolition of (2) wall hung sinks at Men’s Restroom and
(3) at Women’s Restroom are mentioned and to supply and install new wall mounted sinks. It was mentioned at walk
SOW revised. See revised SOW sections 3.1.24, 3.2.22.
through that there was to be a continuous counter at each sink area. Please confirm this and if so, what material (ie. Corian) is to be used.
31 Is it possible to have another site visit for either of these projects if requested? Due to each contractor being limited to (3) personnel on the original site visit, but there being (2) projects with multiple trades involved, it would be beneficial to be able to see the projects one more time with our subcontractors. Please advise.
No additional site visits are planned.
32 Attachment 2 - IDIQ Key Labor Categories: Would it be acceptable if the Site Superintendent can also serve as QC Mgr. & Safety Mgr. for these Seed Projects?
Please see response to Question #20.
33 Pg 7 - C.3.4.1: Seed Projects a Type 1 or Type 2? (Clarify As- Builts required only)
This project has no requirements for As-Built drawings to be submitted.
This project requires existing building sketches to be marked up by awardee to detail as-built conditions
34 Scope of Work for Building 717 Paragraph 3.3: lists "Locker Room" instead of Break Room. Please clarify that this is the accurate scope for this project.
Please see response to Question #13.
See revised SOW sections 3.3 and Enclosures 1 & 2.
35 Scope of Work for Building 717 Enclosure 2: lists Women's Restroom and Connected Break Room.
Enclosure 1 lists only Men's Restroom. However, both plans show a Break Room connected to each restroom.
Please confirm if the listed scope of work is for both or only the break room attached to the Women's Restroom.
SOW revised accordingly. See revised SOW sections 3.3 and Enclosures 1 & 2.
36 Scope of Work for Bldg. 717 -
3.1.21 & 3.1.23 & 3.1.14 - Men's Restroom: Provide Model #'s/Specs of sinks, toilets & exhaust fans.
SOW revised to include basis of design sink and counter manufacturer.
Exhaust fans to be sized and provided by contractor to meet requirements of section 3.1.15.
See revised SOW sections:
Sinks – 3.1.24 Toilets – 3.1.22 Exhaust fans – 3.1.15
37 Scope of Work for Bldg. 717 -
3.2.13 - Women's Restroom:
Provide Model #/Specs for exhaust fans.
Exhaust fans to be sized and provided by contractor to meet requirements of section 3.2.14.
38 Reference Section L.2.3, Volume IV – Past Performance, regarding submission of Past Performance Questionnaires (Attachment 10): For several of our most relevant contracts, the designated CORs and project points of contact have separated from federal service through the Deferred Resignation Program and other early retirement offerings, rendering these individuals inaccessible to complete Attachment 10. This effectively eliminates otherwise highly relevant and verifiable past performance examples through no fault of the offeror.
Understood, please provide the information you have with Attachment 10.
39 We respectfully request the Government allow offerors to submit CPARS evaluations and/or previously completed PPQs as acceptable alternatives or supplements to newly completed Attachment 10 questionnaires. This accommodation would preserve the integrity of the evaluation through official, government-generated performance records, reduce the administrative burden on current government personnel who may not have direct knowledge of the referenced work, and ensure the
The Government will pull CPARS, Offerors are not required to submit CPARS.
Vendors should only submit Attachment 10.
Government receives the most complete and competitive proposal pool for a best-value determination.
40 Will the Government accept CPARS evaluations and/or previously completed PPQs in lieu of, or in addition to, newly completed Attachment 10 questionnaires?
Please see response to Question #39.
41 Will the Government provide engineered plumbing riser diagrams, electrical panel schedules, and reflected ceiling plans? If not, is this considered a Design-Build task order requiring a licensed PE per Section C.3.2?
This project is not considered a Design-Build project and therefore, does not require PE stamped drawings. This project does not include work being done to the plumbing riser.
Please see response to Question #10.
42 If Design-Build, should the PE stamp requirement and design costs be included in the seed project bid price?
Please see response to Question #41.
43 Can the Government share the copies of the sign in sheets for both of the Site Visit.
Vendors that participated in the site visits are listed below.
44 Will the government consider expanding page limit for Volume 3 Management plan to 50 pages, since there are a lot of deliverables requested under this division and will be hard to condense it to 10 pages.
The Page count will remain 10 Pages. A detailed summary of the plan is acceptable for the parent contract.
RFP revised to allow for detailed summaries for both the Management Plan and Quality Control Plan.
See revised RFP section L.2.2.3.
45 The layout for the locker room is currently missing. Could you please provide this along with the necessary dimensions?
Please see response to Question #13.
See revised SOW sections 3.3 and Enclosures 1 & 2.
46 Are there existing site photos available for review?
There are no existing site photos available for B717.
47 Could you please confirm if ceramic tiles are required for the restrooms and VCT for the break rooms?
Yes, ceramic tiles are required for the restrooms.
Yes, VCT for the locker rooms.
*Please see response to Question #13.
48 Are the seed projects intended to be design-build or design-bid-build?
There are no design requirements for either the B717 Bathroom Refresh or B21 HVAC and Drainage seed projects as they are both Build only projects.
49 If the SEED projects are design-bid-build, can offerors expect additional drawings, specifications, or design documents to be issued prior to the proposal due date?
Please see response to Question #48.
50 If the SEED projects are design-build, should offerors include design services as part of their proposed scope and pricing for the seed projects?
Please see response to Question #48.
51 Typically, a quality control plan is a post-award submittal that is over 100 pages long.
The RFP only allots 10 pages for the management plan and the quality control plan. Please confirm that all items under
“CONSTRUCTION
QUALITY CONTROL PLAN:
DELIVERABLES
CHECKLIST” on page 81 are required in the VOLUME III Management Plan or if a summary of the plan is acceptable. If all items are required, will the quality control plan be included in the page limit? Alternatively, if the full plan is required, would the government consider allowing the quality control plan to be attached as an appendix?
Please see response to Question #44.
See revised RFP section L.2.2.3.
52 Is there a specific CLIN breakdown for each SEED project? Attachments 7 and 9 include tabs for 4 CLINs, but it is not clear what each CLIN entails. Please clarify how contractor should break out pricing.
Bid Forms revised. See revised Bid Forms.
53 Are contractors required to attend both site visits?
No, both the morning and afternoon sessions included the same information.
54 On page 82, Section L.2.3 states the past performance survey submissions should include “at least one example of managing multiple construction projects concurrently.” Please clarify how this requirement should be met. Would another IDIQ parent contract suffice for meeting this requirement?
Would submitting multiple separate contracts that were performed concurrently (and clearly noting this in our response) suffice?
If the parent contract cited is an example of managing multiple construction projects concurrently, then it is acceptable. Offerors are encouraged to read the instructions to offerors and submit in accordance with those.
55 On the SF 1442, item 13d indicates a bid hold of 10 days.
Please confirm that this is correct.
Confirmed.
56 Is this IDIQ a new contract or a follow-on to an existing contract? If this is a follow-on, please provide the contract numbers and incumbents for the prior contract.
This is a new requirement for
DEVCOM AC.
57 Page 78, paragraph L.1.4 says, "Offerors will have three (3) business days after the site visit to ask any additional questions." Farther down on page 78, paragraph L.1.7 says, "All questions are to be submitted electronically by April 10, 2026 by 2:00 PM EDT". Please confirm that offerors will have until April 10th to submit questions on the site visit, as well as any questions related to any of the solicitation documents.
All questions were due by April 10, 2026 in accordance with the RFP, Section L1.7 Questions Concerning Solicitation.
58 On page 82, Section L.2.3 says, regarding projects submitted for past performance, that the “Project magnitude for the construction projects should be between
Removed.
This is no longer applicable under RFO Part 36.
$2,000K and $11M.” Will projects with a magnitude above $11 million be evaluated as favorably as projects within the $2,000 to $11M range?
59 Can the government provide an estimated magnitude range for each of the SEED projects?
Please see response to Question #58.
60 On page 79, in Section L.2.1, it says “two columns per page are acceptable.” Please confirm that single-column pages are also acceptable.
Removed.
61 On page 80, the SEED bid schedules are listed as part of Volume I. Should the bid schedules be submitted in the excel file templates or converted to PDF files to include with the rest of Volume I?
Please submit the Excel file templates (Attachments 7 & 9).
RFP revised.
See revised RFP section L.2.2.
62 Page 79 shows that Volume II
– Technical Capability has a 10-page limit. Are the two SEED project schedules included in the 10-page limit?
The Offeror should submit the information required in accordance with the Instructions to Offerors Section L.2.2.2.
63 On page 92, Attachment 10 Past Performance Questionnaire says to return only page 1 of the survey. Page 1 appears to be clipped short, only including item 1, “contractor information” from the first section. Please clarify if only the first page (page 92) needs to be submitted or if the entire first section (items 1-4), spanning pages 92-93, should be submitted with the proposal.
RFP Section L.2.3 revised.
Offerors should read the instructions for completion of the Past Performance Questionnaire.
See revised RFP section L.2.3.
64 Can the government provide the PPQ as a separate Word document attachment?
A Word version was included in Amendment 001.
65 Do projects need to be 100% complete in order to include them as past performance?
RFP revised to reflect projects referenced must be at least 90% completed at the time of submission.
See revised RFP section L.2.3.
66 Is it acceptable to submit previously completed past performance questionnaires? If so, can the page limit in
The Offeror should submit the information required in accordance with the
Volume IV Past Performance be extended to allow this?
Instructions to Offerors Section L.2.2.2.
67 Do key personnel in Section L.2.2.3 Volume III – Management Plan need to be identified by name or position only?
Please provide the position and experience.
See revised RFP section L.2.2.3.
68 Please clarify if any dual-hatting will be allowed or if the contractor will be required to have a full-time QC, a full-time SSHO, and a full-time Superintendent.
Please see response to Question #20.
69 Please provide CADD as-built drawings of both the men’s and the women’s restrooms and the adjoining breakrooms.
Please ensure that as-built drawings are complete with mechanical, electrical, and plumbing drawings.
Not available. Please see response to Question #33.
70 Please confirm the age of the existing building (Building
717) and if any hazardous materials are to be encountered.
1952, the Government can provide test results on insulation and existing floor tile / mastic before NTP.
71 Will the government require the contractor to test for any existing hazardous materials for either/both SEED projects?
No, the Government will not require the contractor to test for any existing hazardous materials for either SEED projects under this RFP.
72 Please confirm that the header of pages 2-11 of Attachment 8 are incorrect and should read “B717 – Renovate Restrooms."
SOW revised to reflect B717
– Renovate Restrooms.
See revised SOW header.
73 Do the men’s and women’s restrooms currently have or require the installation of a handicap accessible stall? If there is not a handicap accessible stall but the government requires one, will the government provide the new layout?
B717 is exempt from ADA requirements. No handicap stall is required.
74 Regarding the bathroom renovation SEED project, please confirm that the work is a one-for-one replacement of existing plumbing fixtures and
This project is a one-for-one replacement and therefore, no additional fixtures are required.
that no new fixtures are required.
75 In Attachment 8, paragraph 2.2 states, “Renovation of the B717 break room." However, paragraph 3.3 refers to a “Locker Room." Additionally, Enclosures 1 and 2 show areas labeled "Break Room." Please clarify if B717 SEED project includes the renovation of a break room or locker room.
Please see response to Question #13.
See revised SOW sections 3.3 and Enclosures 1 & 2.
76 Are there any existing trouble codes or alarms on the existing fire alarm panel in B717?
No trouble codes present.
77 Please confirm the work listed in the Attachment 8 SOW regarding finishes and other accessories in the renovated area are required.
SOW revised to include basis of design manufacturer and models.
See revised SOW sections 3.1.27, 3.2.25.
78 In Attachment 8, paragraphs
3.1.12 and 3.2.12, please provide approximate distance to nearest electrical panel that has the capacity for the installation of 2 automatic hand dryers. This information is critical in allowing offerors the opportunity to provide accurate and competitive pricing.
Please see response to Question #10.
79 In Attachment 8, paragraph 3.1.13, what is the location of the existing hand dryer? Please provide the location of the of the new hand dryer.
There are no existing hand dryers. New hand dryer will be located between sinks and the entrance to the bathroom.
80 Regarding Attachment 8,
3.1.13 & 3.1.26 and 3.2.12 & 3.2.24, please confirm the government requires the installation of both a hand dryer and a paper towel holder.
Yes, the Government requires the installation of both a hand dryer and a paper towel holder.
81 Should Attachment 8, Paragraph 3.1.17 say, “two coats of mildew resistant commercial grade paint” instead of "two coats of milder resistant commercial grade paint"?
Yes, SOW should read as “two coats of mildew resistant commercial grade paint.”
See revised SOW section 3.1.18.
82 Do the new sag resistant ceiling tiles referenced in Attachment 8, Paragraphs 3.1.18, 3.2.17, and 3.3.6 also need to include moisture and mildew resistance?
SOW updated to include basis of design manufacturer and model of ceiling tile and grid.
See revised SOW sections 3.1.10, 3.2.7, 3.3.4.
83 What is the occupancy and usage of the bathrooms?
Attachment 8, Paragraphs
3.1.27 and 3.2.25 indicate PEI 3 ceramic tile. Ceramic tile with PEI of 3 or 4 are typically used in residential restrooms, while commercial/high traffic restrooms typically receive tile with a PEI of 4 or 5. Please confirm the new ceramic tile category desired.
SOW updated to include basis of design manufacturer and model of floor tile and cove base.
See revised SOW sections 3.1.28, 3.2.26.
84 What is the location and approximate square footage of the storage area(s) for the installation of the vinyl tiled floor, referenced in Attachment 8, Paragraphs 3.1.28, 3.2.26, and 3.3.11?
SOW revised to remove any language pertaining to the “storage areas” for this project.
See revised SOW.
85 Please confirm that the toilet paper holder in the B717 restrooms will be GFE and installed by the contractor.
This is not GFE.
86 Please provide clarification on the required on-site field staff and the limitations on their roles.
Please see response to Question #20.
87 If dual-hatting is allowed, will the QCM also be able to serve as the SSHO?
Please see response to Question #20.
88 Can a staging area be identified for dumpster, materials, equipment and port-a-potty?
Yes, a staging area will be identified before NTP.
89 Are we using the existing ceiling grid or should we price installing new ?
Please see response to Question #1.
See revised SOW sections 3.1.7, 3.1.10, 3.2.6, 3.2.7, 3.3.3, 3.3.4
90 For the restrooms are we using ceramic tile cove base or vinyl?
Tile cove base for restrooms. See revised SOW sections 3.1.28, 3.2.26.
91 What type of material is to be used for the bathroom thresholds?
SOW revised to reflect marble thresholds in restrooms.
sections 3.1.28, 3.2.26.
92 What type of material is to be used for vinyl tile thresholds?
Armstrong vinyl trim. See SOW section 3.3.12.
93 Is there a preferred make and model number for the soap dispenser and paper towel holder so as to match what is currently stocked for refills?
Please see response to Question #28.
See revised SOW sections 3.1.27, 3.2.25.
94 If there are a preferred models to question above, can model numbers be provided?
Please see response to Question #28.
See revised SOW sections 3.1.27, 3.2.25.
95 The supply lines for the toilets are not large enough to supply flush valves can power flush tank toilets be provided?
SOW revised to reflect replacement toilets being floor mounted power flush.
See revised SOW sections 3.1.22, 3.2.21.
96 For the urinal partition is wall hung 18" X 48" or a 18" X 58" with a post mounted to the floor preferred?
Wall-hung panel preferred.
SEED Project - B21 HVAC and Drainage
Question # Question Response Reference 97 Who is the HVAC controls integrator for the base?
Ainsworth Controls
Ainsworth POC: Harris Littman, 609.860.6600 Harris.littman@ainsworth.co m
Ainsworth Inc. Building Automation Solutions 10 Centre Drive Monroe, NJ 08831
98 Possibility of Asbestos pipe insulation on condensate pipes or steam pipes.
The Government will get asbestos testing done on condensate lines (underground) and above ground steam lines prior to NTP being issued Proposals shall assume no asbestos present.
If the testing shows the presence of asbestos, that will be considered unforeseen site conditions, and its remediation will be negotiated.
mailto:Harris.littman@ainsworth.com mailto:Harris.littman@ainsworth.com
99 Where is demolition on steam pipes going to stop in mechanical room?
SOW updated to reflect Above ground steam lines shall be removed from mechanical room completely and capped /plugged at interior dividing wall of mech. room and office space.
See revised SOW section 3.1.7.
100 What is happening with condensate pit outside of B21? Not mentioned in
PWS.
SOW updated to reflect construction contractor removing condensate pump unit from the pit when they remove condensate piping outside the building. This pump unit will be transported by construction contractor to the same holding area as Boiler in a box.
Approximately 1.5 miles away on base. This equipment is approximately 300lbs.
See revised SOW section 3.1.5.
101 Where is soil being disposed of during excavation around B21?
Please see SOW section 8.6.
102 What is happening with bollards near split condenser, Boiler in a box, and mini-split condenser?
SOW updated to reflect removal of two bollards next to AC condenser being removed on the corner of B21. And two new bollards being installed around new RTU and driveway. Bollards in front of mini-split condenser on the side of B21 shall be removed during excavation and new bollards installed. Pad for Mini-split will be removed in one piece and re-installed.
See revised SOW sections 3.1.9, 3.1.4, and 3.1.13.
103 Piers under the Boiler in a box and future concrete pad for RTU.
Clarification: Piers shall be modified to allow concrete pad for RTU to be installed at top of slab 6" above grade.
Piers shall be tied into new concrete pad.
104 Return Trunk being added to B21.
After reviewing this at site visits, SOW updated to reflect fully ducted returns into ceiling grid of space. Return plenum will be deleted.
Plenum grills will be section 3.1.17.
removed. Construction Contractor will propose return and supply locations on shop drawings to provide airflow to occupied space by submittal after Notice to Proceed. Flex Duct will be allowed to transition through historic ceiling and into ceiling grid at 6ft max length.
105 Are Duct detectors required for B21 RTU being installed?
Yes, smoke detectors for the ducts are required and need to be tied into Fire alarm panel.
Suggested Fire alarm vendors are: SYSTEM ONE ALARM
SERVICES, INC
795 FRANKLIN AVENUE
PO BOX 487
FRANKLIN LAKES, NJ
07417 Phone # 201-891-2666 United Fire 1Mark Rd, Kenilworth, NJ 07033 Phone: (908) 688-0300
106 What is the bottom of duct height required outside of B21 for new trunks entering the building from RTU on pad.
At least 6" above the existing mech. Rm doors. Maintain clearance in front of doors for access to mech. room. If necessary trace building roof line so duct does not protrude above sloping roof line.
107 Decommissioning of Boiler in a box, what are the tasks between construction contractor and Base operations HVAC (Energy Systems Group)?
Construction contractor shall notify ESG two weeks ahead of decommissioning. ESG will need two days to drain and prep BIB for removal and remove parts that can be reused. Once that is complete, utilities and BMS wiring will disconnect through appropriate process (explained in other responses) and construction contractor will load, transport and unload BIB at B314 holding area approximately 1.5 miles away on base. ESG POC info will be supplied before NTP issued.
108 Electrical service to Boiler in a box. What tasks are construction contractors doing and what tasks are utility company doing?
Sussex Rural Electric Company (SREC) will cut utility feed at weather head and remove overhead wiring back to appropriate utility pole. This is not a cost to the construction contractor.
SREC will need two weeks’ notice to complete this task.
SREC POC info will be supplied before NTP.
109 Natural Gas Utility for BIB and future RTU
NJNG is the gas utility for base. Mark out can be requested for all utilities using 1-800-DIG. No cost to construction contractor.
Construction contractor will request disconnect of gas and reconnection of gas at least two weeks ahead of time to NJNG. Construction contractor is responsible to ensure proper amount of NG is available for Proposed RTU. If regulators or piping needs to be changed this is responsibility of construction contractor.
110 What is the list of equipment being removed from B21 and transported to B314 holding area?
Existing AHU in Mech Rm, Existing split AC condenser on the corner of B21, existing condensate pump equipment in condensate pit at B21, Boiler in a Box. All other refuse, dunnage, scrap metal is to be removed by construction contractor at their cost. update upon pit inspection.
111 Unexploded ordinances sweep for excavation at B21.
Is it required? Who provides or pays for support?
UXO sweep is required at B21. US Army will sweep the areas around the building with ground penetrating radar before excavation begins and a representative must be present from US Army at all times during digging. This support cost is born by US
Army. If trenches are deeper than 2 ft then another sweep is required in those areas.
Construction contractor must propose excavation schedule for review and coordinate with UXO resources for coverage.
112 Clarify the design/build requirements (i.e. are signed stamped drawings required)
Seed Projects do not include design, they are build-only projects.
113 Is there a Picatinny HVAC/mechanical set of design standards that can be shared? If not, please clarify the following – 1. Insulation requirements (thicknesses, materials for each type of system), 2. Will duct cleaning, DALT, TAB, BMS integration be required?, 3.
What are the ATFP requirements?
Mechanical standards per UFC sections called out.
www.wbdg.org
114 How is the new packaged unit to be controlled (i.e.
discharge air temperature, return air temperature, averaging stats)
Supply Air reset based off Zone temp control with averaging.
115 Confirm that all radiators and hydronic piping inside the building will be abandoned in place and not demoed.
Confirmed, all radiators and hydronic piping inside the building will be abandoned in place and not demo-ed.
116 Confirm that existing gas flow meter can be re-used.
Contractor is required to check size of gas requirements of proposed RTU and work with NJNG to ensure meter can be reused or new meter needs to be provided by NJNG. No charge to contractor for meter.
117 Who is the customer of record for the gas meter at this location? Will NJNG coordinate with contractor for new/modified service or will they only deal with owner?
Customer of record is Picatinny Garrison DPW.
Their utility manager will interface with NJNG and construction contractor to coordinate service disconnect and new service.
118 Kindly confirm whether temporary heating/cooling will be required?
No temporary heating or cooling will be required.
http://www.wbdg.org/
119 Should the contractor price a Dedicated Outdoor Air System (DOAS) per UFC 3- 410-01 §2-3.2, or a conventional forced-air system?
No, please follow UFC requirements for OA ventilation of office space.
120 If DOAS is required, please advise whether energy recovery ventilation (ERV) should be included in the design.
Please see response to Question #119.
121 What is the approximate square footage and ceiling height of the conditioned space to support equipment sizing?
B21 is 105ft. x 37ft. -approximately 4,000 sq ft.
122 Is it possible to have another site visit for either of these projects if requested? Due to each contractor being limited to (3) personnel on the original site visit, but there being (2) projects with multiple trades involved, it would be beneficial to be able to see the projects one more time with our subcontractors.
Please advise.
Please see response to Question #31.
123 With regard to the installation of the gas line for the new RTU being supplied and installed - the SOW states "installation of a new gas line and meter to service the ground mounted RTU", but the HVAC drawing provided states "reuse gas utility service line for RTU". Which of these statements is the correct direction to follow?
NJNG will provide primary gas line and meter.
Construction contractor is responsible for secondary side of piping from meter to RTU.
See additional information in response to Question #109
124 It is stated within the SOW that all metal generated by the removal of the boiler and condensate lines should be transported to the Garrison recycling yard. Is the contractor required to dispose of any non-metal items being demolished on their own, or will these materials be
Refuse, other than metal, shall be removed by construction contractor at their expense.
Space will be provided for dumpsters before NTP.
brought to the Garrison recycling yard as well?
125 It was mentioned on the site visit that the contractor could use the existing panels on-site to connect the new electrical lines to for the RTU and unit heaters being installed if possible. The SOW states "a new panel" for the RTU and "new electrical sub-panel" for the new unit heaters. If it is indeed possible to use the existing panels, will the contractor be advised to do so, or should new panels be installed regardless per the
SOW?
SOW revised to reflect use of existing panels.
See revised SOW section 3.1.21.
126 Automatic Temperature Controls Scope: Please clarify the required automatic temperature controls scope for Building 21. Should offerors include: (a) tie-in to an existing controls/BAS/BMS system,
(b) modification of an existing controls system, or
(c) furnishing and installing a new standalone controls system for the new RTU and unit heaters? If integration with an existing system is required, please identify the existing controls manufacturer/platform and confirm whether the system is BMS/BAS, DDC, analog, or other.
Reference: Attachment 6, Building 21 HVAC & Drainage SOW
The provided unit shall be provided with BACnet connectivity and is to be integrated into the base-wide BMS. The local controls will be programmed by the contractor and integration into the base system will be paid for and coordinated by the contractor with the installation's BMS contractor.
Ainsworth Inc Building Automation Solutions 10 Centre Drive Monroe, NJ 08831 T: 609.860.6600 | 888.222.2078 www.ainsworth.com
127 Design Responsibility: Please confirm whether Building 21 should be priced as a fully designed construction project, or whether contractor design, design-assist, or PE-certified extension-of-design is required for mechanical, B21 and B717 are Build-only projects and do not require PE design. Contractor design submittals are required.
electrical, gas, and drainage elements.
Reference: Attachment 6, Building 21 HVAC & Drainage SOW and Solicitation Section C
128 Additional Drawings / As- Builts: Are any additional full-size scaled drawings, CAD files, or as-built drawings available beyond the enclosure sketches included in the SEED package?
Reference: Attachment 6, Enclosures
There are no As-Built or additional drawings for this project.
129 Electrical Distribution Scope:
The SOW references a new panel for the RTU and a new electrical subpanel for the unit heaters. Please confirm whether offerors must include those new panels as written, or whether reuse of existing available capacity is acceptable if field conditions support it.
SOW revised to reflect use of existing panels.
Reference: Attachment 6, Building 21 HVAC & Drainage SOW
Please see response to Question #125.
See revised SOW section 3.1.21.
130 Gas Utility Responsibility:
Please clarify the division of responsibility with NJNG for the resized gas service, gas line, and meter. Should offerors carry all utility coordination and final service modifications required for a complete installation?
Reference: Attachment 6, Building 21 HVAC & Drainage SOW
Please see response to Question #123.
131 Drainage Pricing Basis:
Please confirm the required discharge point, invert elevations, and basis of trench depth for the perimeter drain system so offerors can use a consistent pricing assumption.
Reference: Attachment 6, Building 21 HVAC & Drainage SOW and Enclosure 3 / Enclosure 4
SOW revised to include drainage layout and elevations in Enclosure 7.
See revised SOW, Enclosure 7.
132 Can the Government provide existing site photos?
SOW Attach A-D incorporated to provide pictures for B21 panels and breakers.
See SOW Attach A-D.
133 Are there any existing As-built drawings available? If not, could you please provide the building dimensions?
Please see response to Question #128.
134 Are there any known utilities in the area where excavation is required?
Gas line for B21 is between boiler in a box and building.
Utility mark-out will be done prior to construction.
SOW Enclosure 7 revised to display approximate location of other utilities near B21.
See revised SOW, Enclosure 7.
135 Where does the other end of the 6" drain lead? Please provide the relevant connection details.
Please see response to Question #131.
See revised SOW, Enclosure 7.
136 What is the required excavation depth?
Please see response to Question #131.
See revised SOW, Enclosure 7.
137 Would you please provide a more detailed drawing?
A more detailed drawing is not available.
138 Is there an existing controls system in the building?
No, HVAC needs to be BACNET capable to integrate with Base BMS.
139 Are the ductworks existing? On the sketch, it is hard to differentiate old ducts from new.
Supply trunk is being reused.
Return trunk need to be furnished and installed by construction contractor.
Plenum return is being deleted.
140 Please provide pictures around the outside of the
Please see response to Question #132.
See SOW Attach A-J.
building showing the area where the new drainage system is going to be installed. See the red arrows around the perimeter of the building in attached above Enclosure 3 – Drainage System
141 Please provide equipment cuts for new RTU and (5) unit heaters..
Please refer to the SOW for this project and Manufacturer and Models are described.
Offeror will provide submittals on equipment for approval after award.
See SOW Enclosure 2
– New Equipment.
142 Need specifications for panels and breakers , etc.
assuming the information is in the above listed UFC spec/criteria.
SOW Attach A-D incorporated to provide pictures for B21 panels and breakers.
See SOW Attach A-D.
143 Are electrical as-built drawings available for this area indicating location of nearest electrical panels.
Please see response to Question #128.
144 A site survey of existing conditions is requested.
That was scheduled and completed on the date described in the announcement.
RFP L.1.4 Pre- Proposal Site Visit:
Two sessions were held on April 7, 2026, at 9:00 AM and 1:00 PM. Both sessions provided the same information to attendees.
145 Scope of Work for Bldg. 21 - HVAC: Are we reusing supply lay ins or supplying new ones?
They can be reused but we ask the offeror to locate supply and new ducted returns in a layout that will provide adequate airflow to each room. So supplies may need to be relocated.
146 Scope of Work for Bldg. 21 - HVAC - 3.1.13: Is Silver weatherproof wrap fine or a different color - White?
Either is fine. Weather resistance is more important than color. Color selections to be submitted for approval in accordance with SOW section 5.3.
SOW revised.
See revised SOW section 3.1.16.
147 Please confirm whether the 6" discharge pipe is required to be daylighted into the
Confirming a duckbill check valve should be used as the protective screening device.
section 3.2.2.
stream with a rodent/critter guard or other protective screening device.
SOW revised to include a duckbill check valve should be used.
148 Is a flared end section, endwall, or other termination detail required at the outlet of the discharge pipe?
No, Some riprap would be appropriate.
149 For the 4" perforated line on the short side of the building, should the pipe be installed between the building and the existing concrete vault, or outside the vault?
Outside the vault
150 Please confirm the minimum required burial depth/cover for the 4" perforated drain line at its starting points.
4” minimum burial depth at starting point.
SOW Enclosure 7 revised to include drainage layout and elevations.
See revised SOW, Enclosure 7.
151 Is #57 stone acceptable for bedding and cover of the 4" and 6" drain lines, or is 1B (pea gravel, 3/8") specifically required?
3/4" clean for bedding on lines.
152 Should asphalt removed during trenching be restored to match existing pavement thickness and layer structure, or is a different pavement section required?
Match existing pavement thickness. If 3/4" is used mechanically compact in lifts and Asphalt can be installed.
153 Will the asphalt restoration require third‑party testing?
(density testing, compaction verification, or mix testing)
Yes, the asphalt restoration will require third-party testing.
154 Does the HVAC equipment pad require third‑party inspection or testing?
(subgrade compaction, concrete testing, etc.)
Yes, submittal on concrete mixture. Testing to verify.
155 Is the contractor responsible for coordinating with the utility company to provide temporary support or bracing for the telephone pole adjacent to the drainage trench.
Construction contractor is responsible for temporarily bracing / supporting the utility pole while they dig around it.
156 Can section C.3.7.4. be clarified, breaking down some components to under
Removed.
RFP revised.
$1000 dollar increments may not be feasible?
157 Will a Tax Exempt number for purchasing materials be provided for each awarded task order?
Refer to FAR/RFO 52.229-3, Federal, State, and Local Taxes.
158 Where is the staging area for dumpster, materials, equipment, contractor parking, and port-a-potty?
Please see response to Question #88.
159 Is temporary heat or cooling required for building?
Please see response to Question #118.
160 Is temporary cooling required for IT closet?
No. Please see response to Question #118.
161 Is asbestos insulation present on the piping to be removed?
The current assumption is no, however, the Government will test and provide results.
162 Identify pipes below excavation depths to be removed?
Condensate lines only. No other known pipes in the path.
163 Will the existing overhead service line need to be temporarily disconnected to install ductwork?
BIB service will be removed during that event. Other building service will remain during ductwork install.
Utility provider can install insulators on active lines.
164 Is a service light and outlet required by HVAC unit?
Yes, a service light and outlet are required by HVAC unit.
165 Is the "Boiler in a box" container to be brought to recycling in one piece with components left in place?
Yes, the “Boiler in a box” container should be taken to recycling in one piece with components in place.
166 At site the visit, the use of a plenum between the original building ceiling and drop ceiling was discussed, should the returns be brought down to the drop ceiling and registers placed in the ceiling grid?
Yes, SOW revised to reflect this change.
See revised SOW section 3.1.17.
167 If return registers are brought down to ceiling grid should they be supplied with dampers?
Balance dampers should be at trunk takeoffs for supply and return, not registers.
168 Identify dampers on existing supply duct
The supply branches will need dampers to accomplish commissioning of the new system. There are no mechanical as-built drawings;
therefore, an investigation will have to be done on this during demolition.
169 Existing supply registers did not appear to have dampers, should they be changed to damper style to allow for proper balancing?
Dampers should be added to supply runs. Damper style registers is one way. Dampers could also be added to the trunk takeoffs.
170 If the plenum is to be used can locations of eggshell grates for drop ceiling be provided?
The plenum is not being used.
Please see response to Question #166.
See revised SOW section 3.1.17.
171 Should the existing ductwork be cleaned?
Yes, the existing ductwork should be cleaned.
172 What size subpanel should be provided?
SOW revised to reflect use of existing panels.
See revised SOW section 3.1.21.
173 Enclosure 3 detail specifies for 4” and 6" drainage pipe, what material is required (SDR, PVC or HDPE)?
SOW revised to include required material.
See revised SOW section 3.2.1.
174 Are clean-outs required at the start of each run and at changes of direction?
SOW revised. See revised SOW section 3.2.1.
175 Is the 6" pipe crossing the parking lot to be solid or perforated?
The pipe should be solid.
176 What is the invert starting elevation of the 4" pipe on the left front corner of the building?
Please see response to Question #131.
See revised SOW Enclosure 7.
177 6" drain ends in the rear grass area, can an ending invert elevation be provided?
Please see response to Question #131.
See revised SOW, Enclosure 7.
178 In lawn areas, is the grass to be removed in its entirety and replaced with 4” layer of river rock to match trench Detail?
Yes, all grass areas shall be removed and replaced with river stone.
See revised SOW, Enclosure 7.
179 Can drain line portions below excavation depths be abandoned in place?
No.
180 Where does the drain line currently end?
Condensate lines end in condensate pit.
181 What is the final depth of the drain lines?
Less than 3ft deep.
182 If drain lines end in the vault right rear corner does the vault need to be removed and area repaired?
Vault stays, condensate pump is to be removed.
183 Can a spec for the geotextile be provided?
Mirafi 140N or approved equal
184 What is the thickness of the existing asphalt?
Not available, assume 3-4 inches thick.
185 Can a spec for asphalt replacement be provided?
Please refer to: NJ DOT Spec Pavement Restoration Specifications (NJDOT CD- 601-3)
186 What depths are the water line and gas lines?
This will be identified during utility mark-out. Assumed to be between 3ft and 6ft deep.
187 Enclosure 1 says to reuse existing gas line, SOW red note directs contractor to install a new gas line, generally the utility company supplies gas to building and meter set up, does this apply on base?
That does apply on base.
See additional information in response to Question #109 and #123.
188 Will the new gas line from road to…
This is the start of the file's text. The full file is on GovTribe.