Additional_Q_A_04082025_0005.pdf
PDF 85 KB Posted
- Attached to
- Fort Cavazos Range Repair Construction Services
- Solicitation number
- 140D0425R0055
About this file
This document is an Additional Q&A addendum for Solicitation 140D0425R0055 for the Fort Cavazos Range Repair project, dated 04/08/2025. The document provides specific technical clarifications in response to two questions: First, the amperage on RLM lights along heating blankets for MATs 2 and 8 is confirmed to be 5.10 amps for both thermals and lights. Second, it confirms that all RLM work on Jack Mountain must be performed during mandatory shutdown, indicating strict operational constraints for the project's execution.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation: 140D0425R0055 Project Name: Fort Cavazos Range Repair
Date: 04/08/2025
Additional Q&A
What is the amperage on the RLM lights along the heating blankets for MATs 2 and 8?
ANS: The amp load is 5.10 amps for the thermals and the lights.
Does all the RLM work on Jack Mountain need to be performed during mandatory shut down?
ANS: Yes.