FORM IA-C713 is a Contract Progress Report template used by the Department of the Interior, Indian Affairs to track contractor performance and completion status throughout a contract period.
The form captures essential contract administration data including contractor name and address, report number, period covered, project number, contract number, and contract completion date. It features a work element tracking table where contractors list individual line items, specify the percentage of total contract value for each element, document the percentage completed during the current reporting period, and provide cumulative completion percentages. A remarks section allows for additional narrative information. The form includes a Progress or Completion Certificate section requiring certification by the contractor that work has been satisfactorily completed per contract specifications, with signature lines for both the submitting party and the Contracting Officer's representative. The form also includes a yes/no checkbox confirming whether payrolls were submitted for the reporting period. The form notes that information provided may be used for computing progress payments at the Contracting Officer's discretion according to the contract's payment clause.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A4_-_IA_-_IEE_Representation_Form.pdf | ||
| A8_SF1413_Statement_and_Acknowledgement.pdf | ||
| A6_-__RFQ_Questions_and_Answers_Log.xlsx | XLSX spreadsheet | |
| A1_-_SOW_Tohaali_Sidewalk_Replacement_AB856959__090226.docx | DOCX document | |
| A9_IA_Form_C113_Progress_Schedule.pdf | ||
| A02_-_Wage_Rates.pdf | ||
| Sol_140A2327Q0318.pdf | ||
| A3_-__-_DIAR_1452_280-2_Supplement.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Interior, Indian Affairs
CONTRACT PROGRESS REPORT
CONTRACTOR ADDRESS
REPORT NO. PERIOD COVERED
FROM: TO:
PROJECT NO. CONTRACT NO. COMPLETION DATE
LINE
NO.
WORK ELEMENT % OF
TOTAL
% COMPLETED
THIS PERIOD
% COMPLETED
CUMULATIVE
TOTAL
REMARKS
At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY: _________________________
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
REVIEWED BY OR FOR CONTRACTING OFFICER
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
FORM IA-C713
Have payrolls been submitted for this time period? YES / NO