A1_-_SOW_Tohaali_Sidewalk_Replacement_AB856959__090226.docx
DOCX document 26 KB Posted
- Attached to
- TO'HAALI' SCHOOL REPLACE FRONT ENTRANCE SIDEWALK
- Solicitation number
- 140A2327Q0318
About this file
This is a Statement of Work (SOW) for concrete sidewalk demolition and replacement at Tohaali Community School located on the Navajo Indian Reservation in Newcomb, New Mexico (Work Order AB856959). The project addresses deteriorated and damaged concrete sidewalk sections that are not ADA-compliant and pose trip hazards to students, faculty, staff, and visitors. The contractor must demolish approximately 797 square feet of existing concrete sidewalk (estimated 100 feet long by 6 feet wide, 4-6 inches thick) and replace it with new ADA-compliant concrete sidewalks that provide safe, level, and durable pedestrian surfaces. Work includes site mobilization, pre-construction inspection, utility and structure protection, concrete demolition and removal, subgrade preparation with compacted aggregate base installation, new concrete placement with proper reinforcement and joints, surface finishing, curing and protection, site restoration, and final cleanup. All work must be completed Monday through Friday between 8:00 a.m. and 4:30 p.m., with weekend work requiring written approval from the Contracting Officer's Representative.
The contractor bears full responsibility for labor, supervision, equipment, tools, materials, transportation, testing, disposal, permits, insurance, and temporary facilities necessary to complete the work. Field verification of existing conditions, dimensions, quantities, elevations, and drainage requirements is mandatory prior to construction, with actual final quantities based on field conditions. A one-year warranty covering workmanship and installation defects applies from the date of Government acceptance. Primary project contacts include David Allison (New Mexico Navajo South Facility Manager), Stanley L. Henderson (Acting Supervisory Facility Operations Specialist), Delores Patch-Bitsilly (Principal), and Tommy Thacker (Maintenance Supervisor). Deliverables include final field-verified quantities, warranty documentation, final inspection documentation, site restoration certification, and invoices submitted through the Invoice Processing Platform. The related solicitation (140A2327Q0318) is a fixed-price contract set aside for Indian Small Business Economic Enterprises (ISBEE) with a site visit scheduled for November 19, 2026, questions due December 2, 2026, and technical and price quotes due December 14, 2026; the estimated project magnitude ranges from $25,000 to $100,000 with performance expected within 30 days, and bid bonding requirements apply for quotes exceeding $35,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A4_-_IA_-_IEE_Representation_Form.pdf | ||
| A8_SF1413_Statement_and_Acknowledgement.pdf | ||
| A6_-__RFQ_Questions_and_Answers_Log.xlsx | XLSX spreadsheet | |
| A9_IA_Form_C113_Progress_Schedule.pdf | ||
| A02_-_Wage_Rates.pdf | ||
| A10_IA_Form_C713_Progress_Report.pdf | ||
| Sol_140A2327Q0318.pdf | ||
| A3_-__-_DIAR_1452_280-2_Supplement.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
New Mexico Navajo South Agency Tohaali Community School – WO# AB856959 Highway 491, Route 19 Newcomb, New Mexico 87455 Statement of Work (SOW) 09/02/2026 Concrete Sidewalk Demolition and Replacement
Overview Tohaali Community School is in need of demolition and replacement of deteriorated and damaged concrete sidewalk sections located on the school campus. The existing concrete sidewalk is not ADA-compliant, has areas of cracking, spalling, settlement, deterioration, and/or other deficiencies that create uneven walking surfaces and may present trip hazards to students, faculty, staff, visitors, and school maintenance personnel.
The purpose of this project is to remove the identified defective concrete sidewalk sections and replace them with new concrete sidewalks that provide a safe, ADA accessible, durable, level, and accessible pedestrian walking surface.
The Contractor shall provide all labor, supervision, equipment, tools, materials, transportation, demolition, disposal, site preparation, concrete placement, finishing, curing, cleanup, and incidentals necessary to complete the project in accordance with this Statement of Work.
The Contractor shall field-verify the existing sidewalk conditions, dimensions, quantities, elevations, drainage requirements, adjacent structures, utilities, and other site conditions prior to beginning work.
The completed sidewalk shall provide a durable pedestrian surface and shall be properly integrated with existing sidewalks, curbs, entrances, drainage areas, and surrounding grades.
Scope of Work Requested New Mexico Navajo South Facility Management intends to obtain the services of a qualified concrete contractor to demolish and replace designated deteriorated concrete sidewalk sections at Tohaali Community School.
The Contractor shall furnish all labor, supervision, equipment, tools, materials, transportation, testing, quality control, disposal, and incidentals necessary to complete the work.
The Contractor shall verify all existing field conditions and sidewalk dimensions prior to construction. Final quantities shall be based upon actual field conditions and the requirements identified by the Government.
The work shall include, but not necessarily be limited to, the following:
· Mobilize to Tohaali Community School and coordinate the project with BIE Facility Management and school administration.
· Conduct a pre-construction site inspection and verify the location and extent of sidewalk replacement.
· Identify and protect existing utilities, structures, landscaping, irrigation systems, drainage features, curbs, ramps, doorways, and other adjacent facilities.
· Establish appropriate construction limits and protect areas not included in the work.
· Saw-cut existing concrete at designated removal limits to provide clean and straight demolition joints.
· Demolish and remove existing damaged and deteriorated concrete sidewalk sections.
· Remove concrete debris, unsuitable base material, vegetation, and other materials as necessary to prepare the work area.
· Properly load, transport, and dispose of demolished concrete and construction debris at an approved disposal facility.
· Excavate and prepare the sidewalk subgrade as necessary to provide a stable and properly graded base.
· Remove and replace unsuitable or unstable subgrade material as required.
· Furnish and install compacted aggregate base material where required.
· Compact the prepared subgrade and aggregate base to provide a firm and stable foundation for the new concrete.
· Establish proper elevations and grades to maintain positive drainage and prevent ponding of water.
· Furnish and install new ADA compliant concrete sidewalk at the locations designated by the Government.
· Match existing sidewalk elevations and transitions where practical and appropriate.
· Provide appropriate reinforcement, control joints, expansion joints, and isolation joints as required by the project conditions and applicable standards.
· Finish new concrete to provide a uniform, durable, slip-resistant pedestrian surface.
· Tool or saw-cut control joints at appropriate intervals to minimize uncontrolled cracking.
· Provide concrete curing and protection measures necessary to achieve proper strength and durability.
· Protect newly placed concrete from pedestrian traffic, vehicles, weather, and other potential damage until adequately cured.
· Maintain safe pedestrian access around the construction area and coordinate temporary closures with school administration.
· Restore disturbed adjacent areas, including soil, landscaping, gravel, pavement, or other surfaces affected by construction.
· Remove all excess construction materials, debris, forms, equipment, and temporary facilities from the site.
· Perform final cleanup and inspection with Government representatives.
· Correct deficiencies identified during the final inspection at no additional cost to the Government.
Contractor's Responsibilities/Conditions The Contractor shall:
· Provide all labor, supervision, equipment, tools, materials, supplies, transportation, disposal, permits, insurance, taxes, temporary facilities, staging, storage, safety equipment, and other resources necessary to complete the work.
· Conduct a field verification of existing site conditions, dimensions, elevations, utilities, drainage, and access conditions prior to beginning work.
· Verify all dimensions and quantities prior to ordering materials or beginning demolition.
· Coordinate construction activities with BIE Facility Management and Tohaali Community School administration.
· Protect existing buildings, utilities, sidewalks, curbs, fencing, landscaping, drainage systems, pavement, equipment, and Government property.
· Provide appropriate barricades, warning signs, cones, fencing, and other safety measures around active construction areas.
· Maintain safe access for students, faculty, staff, visitors, maintenance personnel, and emergency responders.
· Control dust, debris, noise, vibration, and other construction activities that may interfere with normal school operations.
· Properly dispose of all demolished concrete and construction debris in accordance with applicable Federal, State, Tribal, and local requirements.
· Provide suitable concrete materials and installation methods appropriate for exterior pedestrian sidewalk applications.
· Ensure concrete is placed, finished, and cured in accordance with manufacturer's recommendations and applicable industry standards.
· Maintain proper grades and drainage throughout the project.
· Notify the Government immediately of unforeseen conditions, underground utilities, unstable soils, drainage issues, hazardous materials, or other conditions that may affect the work.
· Be responsible for damage caused by Contractor operations and restore damaged property to its original or better condition at no additional cost to the Government.
· Maintain a clean and orderly construction site throughout the project.
· Comply with all applicable Federal, State, Tribal, and local laws, regulations, OSHA requirements, BIE policies, and applicable construction standards.
Considerations and Factors Proposing Contractors shall consider the following during proposal preparation and project execution:
· Contractors are encouraged to perform a site visit prior to submitting proposals to verify existing conditions, sidewalk dimensions, access, drainage, and the extent of required demolition and replacement.
· The Contractor shall verify actual field quantities prior to construction.
· The contents of this Statement of Work shall become an integral part of the resulting contract.
· Coordinate all construction activities with Tohaali Community School administration and BIE Facility Management to minimize disruption to school operations.
· Maintain safe access for school personnel, students, visitors, maintenance staff, and emergency responders.
· Construction areas shall be clearly barricaded and protected from unauthorized pedestrian access.
· The Contractor shall take appropriate measures to prevent concrete dust, debris, and construction materials from entering occupied school areas or adjacent facilities.
· Contractor shall consider weather conditions, including temperature, precipitation, freezing conditions, and high winds, when scheduling concrete placement and curing activities.
· New concrete shall not be placed during conditions that would adversely affect the quality, strength, finish, or curing of the concrete.
· Contractor shall coordinate concrete delivery and construction activities to prevent interference with school traffic and daily operations.
· All work shall be performed Monday through Friday between 8:00 a.m. and 4:30 p.m.
· Weekend or holiday work shall require prior written approval from the Contracting Officer through the Contracting Officer's Representative (COR).
Close Out Requirements Upon completion of the project, the Contractor shall:
· Complete a final inspection of all sidewalk replacement areas with designated Government personnel.
· Correct any defective, damaged, uneven, improperly graded, or otherwise unacceptable work identified during final inspection.
· Remove all construction equipment, temporary facilities, barricades, forms, debris, waste materials, and excess materials from the site.
· Restore all disturbed areas surrounding the sidewalk to an acceptable condition.
· Clean the completed sidewalk and adjacent areas.
· Provide concrete material documentation, if requested by the Government.
· Provide documentation of completed work and final quantities, if requested.
· Notify designated BIE Facility Management personnel upon completion of the work.
· Submit all required invoices through the Invoice Processing Platform (IPP).
· Certify that the project site has been cleaned, restored, and left in a safe and acceptable condition.
Warranty Requirements The Contractor shall provide a minimum one (1) year warranty covering workmanship and installation beginning on the date of Government acceptance.
The warranty shall include:
· Correction of defective workmanship.
· Repair or replacement of defective concrete work resulting from improper installation.
· Correction of improperly finished or improperly graded sidewalk surfaces.
· Repair of unacceptable joints or transitions resulting from Contractor workmanship.
· Correction of deficiencies caused by failure to properly prepare the subgrade or base.
· Re-performance of work that does not comply with the requirements of this Statement of Work.
The warranty shall not apply to failures resulting from:
· Owner misuse.
· Unauthorized modifications.
· Third-party damage.
· Acts of God or other conditions beyond the Contractor's control.
Warranty repairs shall be completed promptly at no additional cost to the Government.
Performance Specification/Requirements Proposing Contractors shall prepare and submit their bids using the following Owner performance requirements as the minimum standard.
The completed work shall:
· Provide a safe, durable, and serviceable pedestrian sidewalk.
· Be constructed on a properly prepared and compacted subgrade/base.
· Maintain appropriate drainage and positive surface runoff.
· Provide smooth transitions between new and existing sidewalk surfaces.
· Be free of trip hazards, significant surface defects, excessive cracking, spalling, honeycombing, or other construction deficiencies.
· Have a uniform and durable pedestrian finish.
· Include properly located and constructed control and expansion/isolation joints as appropriate.
· Be properly cured and protected following concrete placement.
· Match existing grades and elevations where required.
· Protect adjacent buildings, utilities, pavement, landscaping, and other Government property.
· Meet or exceed applicable manufacturer's recommendations and recognized concrete construction standards.
· Comply with applicable OSHA, BIE, Federal, State, Tribal, and local requirements.
· Include final cleanup and restoration of all areas disturbed by construction.
· Be accepted by designated Government representatives upon satisfactory completion.
Project Location The project is located on the Navajo Indian Reservation.
Tohaali Community School, Toadlena, New Mexico Project: Concrete Sidewalk Demolition and Replacement 36°14'22.36"N 108°53'23.79"W & 36°14'21.70"N 108°53'22.70"W Sidewalk Locations: Tohaali Community School, Bldg.102, South Main entrance and West sidewalk of Main Gym.
Estimated Quantities:
· Existing concrete sidewalk demolition: 100’x 6’ & 797 sq. ft.- Field verify
· New concrete sidewalk replacement: 100’x 6’ & 797 sq. ft.- Field verify
· Existing sidewalk width: 100’x 6’ & 797 sq. ft.- Field verify
· Existing sidewalk thickness: 4”-6”- Field verify
· Aggregate base requirements: Base course compacted- Field verify
· Reinforcement requirements: Mesh wire- Field verify
· Number of sidewalk sections: Field verify
· Curb and handicap ramps: Field verify The Contractor shall perform a site visit and verify all dimensions, quantities, elevations, access requirements, and existing conditions prior to submitting a final proposal.
Consultation and Coordination The primary technical point of contact for the duration of this project shall be the designated Tohaali Community School Maintenance Supervisor Tommy Thacker or assigned BIE Facility representative.
Government Contacts
| Name |
| Title |
| Phone |
| David Allison |
| New Mexico Navajo South Facility Manager |
| (505) 619-9029 |
| Stanley L. Henderson |
| Acting Supervisory Facility Operations Specialist |
| (505) 619-9130 |
| Delores Patch-Bitsilly |
| Tohaali Community School Principal |
| (505) 789-3201 |
| Tommy Thacker |
| Maintenance Supervisor |
| (505) 635-1055 |
Deliverables At project completion, the Contractor shall provide:
· Written project completion report, if requested.
· Final field-verified quantities of concrete demolished and replaced.
· Concrete material documentation, if requested.
· Warranty documentation for materials and workmanship.
· Final inspection documentation.
· Site restoration and cleanup certification.
· Documentation of any approved changes from the original scope.
· Photographs of completed sidewalk replacement areas, if requested by the Government.
· Invoice submitted through the Invoice Processing Platform (IPP).
End of Statement of Work