REMOVE/REPLACE DOORS BIE BUS GARAGE TMES
Solicitation number
140A2325R0038
Issued by

About this file

This document is a Statement of Work (SOW) for the Turtle Mountain Elementary School Bus Garage door replacement project in Belcourt, North Dakota. The project requires removing and replacing commercial garage doors, specifically 4 doors measuring 10'2"x12'0" and 12 doors measuring 11'2"x11'9", all with energy-saving, insulated white flush designs featuring R-value of 12 and windows in the third section. The contractor is responsible for complete door and hardware replacement, debris removal, dust protection, weatherstripping replacement, overhead door track modifications, safety compliance, and providing one-year product and workmanship warranties. Additional requirements include submitting a Schedule of Values, materials listing, project safety plan, and compliance with TERO and EPA regulations. The project is solicited under Solicitation Number 140A2325R0038 by the Department of the Interior's Bureau of Indian Affairs Bureau of Indian Education, with the government furnishing necessary utilities for the project's completion.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Turtle Mountain Elementary School – Bus Garage Replace Bus Garage Doors Statement of Work

BACKGROUND: The Turtle Mountain Bus Garage, located in Belcourt, North Dakota, is requesting remove and replace commercial garage doors. The contractor shall furnish all labor, materials and equipment required to remove and replace doors.

SCOPE:

The Contractor shall:

1. Remove damaged garage doors

2. Replace any hardware that may need replacing

3. Replace with Commercial Doors as follows:

a. 4 doors - 10’2X12’0 Energy Saver Flush Low headroom front

White – Insulated with R Value of 12 Windows in 3rd Section

2” Track

Single Trolley

b. 12 doors -11’2X11’9” Energy Saver Flush White – Insulated with R Value of 12

Windows in 3rd Section 2” Track

Single trolley

4. Remove and dispose of all debris and trash from project site to maintain a safe clean work area for staff safety.

5. Contractor is responsible for providing dumpsters to dispose debris.

6. Contractor will be responsible for dust protection and clean up.

7. Contract is responsible to replace the exterior perimeter weatherstripping.

8. Contract is responsible to set up the four overhead doors on the Northwest side of the building converted to have the door track run vertically up the wall to get them up higher and also change the operators to a center mount operator.

9. Provide a Schedule of Values and complete materials listing for ASD approval no less than 14 days prior to commencement of project.

10. Provide a Project Safety Plan and Project Safety POC for compliance with ETR/OJCA/OSHA safety regulations. Furnish and wear all applicable safety and health gear in the performance of this project.

11. Provide a written product warrantee for a One-year period and a workmanship warrantee for a One-year period.

12. Contractor will be responsible for TERO and EPA fees.

13. The Government will furnish all utilities necessary to complete this task.

WORK OUTSIDE REGULAR WORK HOURS

If the contractor desires to perform work under this contract outside regular work hours or on

Saturdays, Sundays or holidays, he shall apply, in writing, to the Contracting Officer no less than 10 calendar days prior to the planned start of such work. Regular work hours are, for the purpose of this clause, those hours the activity or Command where the work is to be performed normally works on a day-by-day basis. Application by the Contractor does not imply consent by the Government. Each application will be considered, and a decision made, on the potential benefit of permitting such work. Approval of a Contractor's application under this clause will be, unless otherwise agreed in writing, at no additional cost to the Government

CONTRACTOR SECURITY REQUIREMENTS

At the Pre-construction Conference [or prior to beginning work on the contract], the Contractor shall provide a list of all on-site personnel, including sub-contractors (including second and third-tier subcontractors) and suppliers, to the Contracting Officer. The contractor shall update this list when changes occur. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the facility. Contractor personnel shall have photo identification at all times while working on BIA facilities. Contractors shall provide the

COR with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, etc...)

and provide the company name, delivery person, and phone number of the firm(s) making deliveries. Otherwise access to the BIA facility may be denied. Employees may be required to submit to a background check and be United States citizens.

NOTE:

It is highly recommended that the contractor makes a site visit before submitting a bid proposal for this contract.