Sol_140A2325Q0241_Amd_0001.pdf
PDF 93 KB Posted
- Attached to
- LPG Delivery, Albq ERC Federal contract opportunity
- Solicitation number
- 140A2325Q0241
About this file
This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for liquid propane gas (LPG) delivery to Jemez Day School and T'siya Day School in New Mexico. The amendment (Number 0001) modifies two key aspects of the original solicitation: 1) extending the response date from August 19, 2025, to August 22, 2025, at 10:00 AM Mountain Daylight Time, and 2) changing the contract type from Firm Fixed Price to Firm Fixed Price with Economic Price Adjustment.
The contract period of performance is from September 1, 2025, to August 31, 2026. The amendment includes FAR clause 52.216-2 for Economic Price Adjustment, which allows for potential price increases up to 10 percent of the original contract unit price, subject to specific conditions and verification by the Contracting Officer. Acknowledgement of this amendment is required for a responsive offer to the solicitation, and it was issued by the Indian Education Acquisition Office located in Albuquerque, New Mexico.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage_Determination_2015-5443.pdf | ||
| B08_IA_-_IEE_Representation_Form.pdf | ||
| Sol_140A2325Q0241.pdf | ||
| D01__Scope_of_Work-Propane.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140A2325Q0241 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
A23
Albuquerque NM 87104 Suite 352A 1011 Indian School Rd.
Indian Education Acquisition Office
08/20/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/12/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amend 001: Update Contract Type and Response Date
The purpose of this amendment is to update contract type and extend response date to provide liquid propane gas (LPG) delivery for Jemez Day School and T'siya Day School, located in New Mexico.
1. Response date changed FROM: August 19, 2025, at 10:00 AM Mountain Daylight Time (MD) TO:
August 22, 2025, at 10:00 AM Mountain Daylight Time (MD).
2. Update Contract type FROM: Firm Fixed Price TO: Firm Fixed Price with Economic Price
Adjustment.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140A2325Q0241/0001
Add: 52.216-2 Economic Price Adjustment-Standard
Supplies (Nov 2021)
(a) The Contractor warrants that the unit price stated in the Schedule for ____________ [offeror insert Schedule line item number] is not in excess of the Contractor¿s applicable established price in effect on the contract date for like quantities of the same item. The term "unit price" excludes any part of the price directly resulting from requirements for preservation, packaging, or packing beyond standard commercial practice. The term "established price" means a price that-
(1) Is an established catalog or market price for a commercial product sold in substantial quantities to the general public; and
(2) Is the net price after applying any standard trade discounts offered by the Contractor.
(b) The Contractor shall promptly notify the
Contracting Officer of the amount and effective date of each decrease in any applicable established price. Each corresponding contract unit price shall be decreased by the same percentage that the established price is decreased. The decrease shall apply to those items delivered on and after the effective date of the decrease in the Contractor¿s established price, and this contract shall be modified accordingly.
(c) If the Contractor¿s applicable established price is increased after the contract date, the corresponding contract unit price shall be increased, upon the Contractor¿s written request to the Contracting Officer, by the same percentage that the established price is increased, and the contract shall be modified accordingly, subject to the following limitations:
(1) The aggregate of the increases in any contract unit price under this clause shall not exceed 10 percent of the original contract unit price.
(2) The increased contract unit price shall be
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140A2325Q0241/0001 effective-
(i) On the effective date of the increase in the applicable established price if the Contracting
Officer receives the Contractor¿s written request within 10 days thereafter; or
(ii) If the written request is received later, on the date the Contracting Officer receives the request.
(3) The increased contract unit price shall not apply to quantities scheduled under the contract for delivery before the effective date of the increased contract unit price, unless failure to deliver before that date results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the Default clause.
(4) No modification increasing a contract unit price shall be executed under this paragraph (c) until the Contracting Officer verifies the increase in the applicable established price.
(5) Within 30 days after receipt of the
Contractor¿s written request, the Contracting
Officer may cancel, without liability to either party, any undelivered portion of the contract items affected by the requested increase.
(d) During the time allowed for the cancellation provided for in paragraph (c)(5) of this clause, and thereafter if there is no cancellation, the
Contractor shall continue deliveries according to the contract delivery schedule, and the
Government shall pay for such deliveries at the contract unit price, increased to the extent provided by paragraph (c) of this clause.
(End of clause)
**Acknowledgement of this amendment is required for a responsive offer to the Solicitation.
Period of Performance: 09/01/2025 to 08/31/2026
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .