B12_MISC_RFP_RFI_Log_Answered_11_16_26-REV_0002.pdf
PDF 119 KB Posted
- Attached to
- FAIR Route 3 - 96-inch CMP Replacement Project
- Solicitation number
- 140A1627Q0105
About this file
This is a Questions and Answers Log for federal contract solicitation 140A1627Q0105, FAIR Route 3 - 96-inch Corrugated Metal Pipe (CMP) Replacement Project. The document addresses 41 questions submitted by potential contractors between November 10-11, 2026, with responses provided on November 16, 2026.
The project involves replacing a 96-inch galvanized-coated CMP culvert at a washout on FAIR Route 3 in Cibecue, Arizona, with 20 feet of cover above the pipe crown (28 feet to invert). The work is classified as Road Maintenance on a firm fixed-price basis with progress payments made upon completion of work performed. The contract period of performance is 90 days. The solicitation is set aside exclusively for Indian Small Business Economic Enterprises (ISBEEs). Contractors must conform to FP-14 Section 707 and Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects. The route is currently closed and will remain closed until the CMP is replaced with the same structure. Quotes were due November 18, 2026, by 5:00 PM Eastern Time, submitted by email. Site visit attendance was highly recommended but not mandatory. Davis-Bacon wage determination applies. The contractor must provide surveying to install the structure and restore the roadway to original condition, perform sewer line repairs, provide quality control through an independent testing company when material testing is required, and handle excavated material reuse and disposal within BIA right-of-way. The contractor cannot add elements beyond the existing structure specifications under Road Maintenance funding constraints. No geotechnical data is available, and temporary water diversion is not feasible due to limited space.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Number Date Received Question Answer Date Answered
1 11/10/2026
Please provide the referenced structural concrete headwall details, existing culvert drawings, and any available roadway cross sections.
See attached Drawings.
11/16/2026
2 11/10/2026 Does the stated 20-foot burial depth refer to cover above the pipe crown or the depth to the pipe invert?
Above the pipe crown. The depth would be 28 feet to the invert of the corrugated metal pipe (CMP). 11/16/2026
3 11/10/2026 Are geotechnical reports, boring logs, or information regarding rock and groundwater conditions available?
No geotechnical data is available, since this was designed and constructed in 1969. No design required for Road Maintenance. 11/16/2026
4 11/10/2026 Will complete closure of FAIR Route 3 be authorized during construction, or must traffic be maintained?
Yes, it is closed now and will remain closed until the CMP is replaced with the same structure. 11/16/2026
5 11/10/2026 Are temporary water diversion or dewatering measures required, and are design criteria available?
No, there is no room to have a diversion of the drainage. It is only running during storm events. 11/16/2026
6 11/10/2026
Please identify the required CMP gauge, corrugation profile, coating, and structural design requirements.
Conform to the FP-14, Section 707, and "galvanized coated" will be required for a 96" CMP. It is the Standard Specifications For Construction of Roads and Bridges on Federal Highway Projects.
11/16/2026
7 11/10/2026
Is excavated material permitted to be reused as structural backfill if testing demonstrates compliance?
Yes, existing material can be reused as structural backfill. Since material has been washed out since July, borrow material will be required to complete the backfill. 11/16/2026
8 11/10/2026
Are there designated disposal areas, approved borrow sources, or other material restrictions?
The COR will contact the agency superintendent for borrow sources.
This item was not needed when the original assesssment was completed in July 2026. The COR will notify you of the locations when they are determined. 11/16/2026
9 11/10/2026 Please confirm whether the project is firm-fixed-price, as the Statement of Work references reimbursement of allowable costs.
Firm fixed price. Progress payments will be made based on the work completed (performed). 11/16/2026
10 11/10/2026
Please clarify whether attendance at the November 10 site visit is mandatory for quotation eligibility and whether a site visit report or photographs will be provided.
Site Visit attendance is HIGHLY RECOMMENDED not required.
11/16/2026
11 11/10/2026 Will the Government provide an engineer's quantity estimate, construction drawings, or any additional technical attachments?
See attached Drawings.
11/16/2026
12 11/11/2026 The solicitation lists the location as Show Low, but the SOW says Cibecue. Can you confirm the work is at the washout on Route 3 in Cibecue?
The CMP and work site is Cibecue, Arizona. The closest hotel and restaurants are in Show Low, Arizona. 11/16/2026
13 11/11/2026 The SOW mentions a headwall detail, but it was not included. Can you send it? If there is no detail, are we expected to design the headwalls?
See Headwall Drawing. Replacing "as is " since it is a Road Maintenance contract we cannot add anything. 11/16/2026
14 11/11/2026 Is the 20 feet of cover measured to the top of the pipe or to the bottom? Answered above. 11/16/2026 15 11/11/2026 Is there a required gauge, corrugation, or coating for the new pipe? Answered above. 11/16/2026
16 11/11/2026 Can the road be fully closed with a detour during construction, or does traffic need to stay open?
Answered above.
11/16/2026
17 11/11/2026 Can you provide the Davis-Bacon wage determination for this project? Contracting Officer to provide those wages. See attached Wage
Determination. 11/16/2026
18 11/11/2026 The solicitation says firm fixed price, but the SOW talks about cost reimbursement.
Which one applies, and how will progress payments be handled?
Answered above.
11/16/2026
19 11/11/2026 Both the small business set-aside and the Buy Indian set-aside clauses are listed. Can you confirm this is Buy Indian (ISBEE) only?
This solicitation is set aside for ISBEEs only.
11/16/2026
Questions and Answers Log 140A1627Q0105, FAIR Route 3 - 96-in CMP Replacement Project
20 11/11/2026 Should quotes be submitted by email? Also, what time zone is the 5:00 PM deadline?
Yes, e-mail. Quotes are now due by by 5:00 PM Eastern Time on November 18, 2026 (Wednesday). 11/16/2026
21 11/11/2026 Has BIA already obtained the 404, cultural/THPO, and stormwater clearances? If not, who is responsible for them? Will a tribal monitor be required?
All work will be completed in the BIA R/W, 50' left and right of centerline and was cleared environmentally and archeologically. 11/16/2026
22 11/11/2026
Are the following included in our scope: removal and disposal of the old pipe, riprap at the inlet and outlet, striping, guardrail, and seeding?
Nothing can be added to the Road Maintenance contract or it does not qualify for Road Maintenance. It would be considered construction.
The agency will remove the old CMP pipes. 11/16/2026
23 11/11/2026 Is construction surveying our responsibility? Will BIA provide control points or any existing survey? Is an as-built survey required at the end?
The Contractor will provide the survey to install the structure and roadway back to the original condition. 11/16/2026
24 11/11/2026 If local asphalt plants are closed for the winter, can we put down a temporary surface and pave in the spring? How would that be paid?
This is allowed.
11/16/2026
25 11/11/2026 Will time extensions be allowed for weather delays? Are there any liquidated damages?
Extensions will be granted for unsual weather conditions.
11/16/2026
26 11/11/2026 Does BIA have any survey, drone photos, or engineering report on the damage or pipe condition that you can share?
The Agency has photos of the damage.
11/16/2026
27 11/11/2026 Can excess or unsuitable excavated material stay on site? For example, can it be spread or placed in an approved area within the project limits?
Yes, the COR can direct this activity.
11/16/2026
28 11/11/2026 If it cannot stay on site, is there an approved disposal area on the reservation, or will it need to be hauled off the reservation?
Yes, there is a certified landfill near White River, Arizona. This will not be required. 11/16/2026
29 11/11/2026 Is there an approved area on site where we can stockpile excavated material during construction?
Yes, in the BIA R/W by the project.
11/16/2026
30 11/11/2026 Will cultural or environmental clearance be needed for any stockpile or disposal area?
No.
11/16/2026
31 11/11/2026 Is repair or replacement of the sewer line part of this contract? Yes. 11/16/2026
32 11/11/2026
If it is, please provide:
- Who owns and maintains the sewer line
- Pipe size, material, depth, and location in relation to the culvert
- Required repair method and specifications
- Whether sewage bypass pumping will be required, and who coordinates any shutdowns
- Any permits or approvals needed
COR will find out from the Tribe/Agency. Yes, the COR will determine the owner of the sewer line and let you know. Since this will be a bid item, all potential Contractors will have the utility companies number for a cost to replace.
11/16/2026
33 11/11/2026
If it is not part of this contract, who will repair it, and will the repair be completed before our work begins? The leak affects worker safety in the excavation and the water we will be discharging to the creek.
Part of the contract.
11/16/2026
34 11/11/2026
Are there any other utilities within the work area, such as water, power, or communication lines? If so, please provide owners and locations.
Not that we know of.
11/16/2026
35 11/11/2026
A bid schedule and DOT wingwall drawing were distrubuted on site walk by BIA personnel. This is assumed to be basis of bid for the project. Please see attached and confirm this is acceptable.
Yes, the COR distrubuted these documents and they are acceptable for bidding. They include the headwall detail and bid items for bidding.
11/16/2026
36 11/11/2026
56 day period of performance does not seem feasible to procure pipe, install pipe, install headwalls, backfill, pave and install pavement markings. In 56-days the pipe can be installed and road opened, minus paving and concrete headwall install. Please review PoP and advise.
The period of performanc will be ninety (90) days to complete the project.
11/16/2026
37 11/11/2026
It is assumed earthwork/utility crew foreman and a full time superintendent will be onsite at all times during construction. All QC will be handled by onsite staff during construction. Please advise if this is acceptable.
Yes, Contractor will be onsite throughout the replacement of the CMP.
Quality control will be required by the an Independent Testing Company when testing of material is required. 11/16/2026
38 11/11/2026 What level of revegitation, if any, is required for this solicitation. Please advise on what bid should include.
None.
11/16/2026
39 11/11/2026 Is the broken sanitary sewer line to be fix as a part of this solicitation. Please advise on what bid should include.
Yes, this should be included.
11/16/2026
40 11/11/2026
Will there be any testing or remediation effort necessary as a result of the broken sanitary sewer line? Please advise on what bid should include.
This was not known until the storm washed out a lot of the material a few weeks ago. 11/16/2026
41 11/11/2026
96" CMP flared end sections are available and would accelarate install. Please advise if this solution is desired.
Unfortunately, we can only replace what is existing, since it is a Road Maintenance project using Road Maintenance funds, we are held to the existing structure. 11/16/2026
Sheet1