B08_ATTACHMENT__2_BID_SCHEDULE_revised_0001.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
ROAD CONSTRUCTION OTOE MISSOURIA
Solicitation number
140A0321B0005
Issued by

About this file

This document includes a bid schedule and description for a federal contract opportunity to reconstruct various parking lots for the Otoe-Missouria Tribe. The bid schedule lays out pay items, quantities, and space for contractors to provide unit pricing and totals for excavation, topsoil, erosion control, sodding, aggregate base, subgrade modification, separator fabric, asphalt paving, concrete paving, curb and gutter, sidewalks, storm sewer pipe, removal of structures and obstructions, mobilization, construction staking, contractor testing, striping, signs, traffic control, concrete slope walls, and a TERO tax. The related federal contract opportunity is seeking bids for the road construction project, sets the bid opening for August 31, 2021 and anticipated award date of September 24, 2021. The project location is at the Otoe-Missouria Tribal Complex in Oklahoma, and is valued between $1-5 million. The solicitation is set aside exclusively for Indian Economic Enterprises and requires compliance with Kay County, Oklahoma construction wage rates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Original Bid Schedule

Tribe: Otoe - Missouria Tribe
Project: B0721111 Reconstruction of Various Parking Lots - Revised 2021_08_19
PAY QUANTITIES PARKING LOT EXPANSION
ITEMDESCRIPTIONUNITQUANT ITYCONTRACTOR UNIT PRICETOTAL
202(A)UNCLASSIFIED EXCAVATIONL.S.1
205(AlTYPE A SALVAGED TOPSOILL.S.1
221EROSION CONTROLL.S.1
230(A)SOLID SLAB SODDINGS.Y.3,460
303(A)TYPE "A" AGGREGATE BASEC.Y.2,960
310(8)SUBGRADE MODIFICATION METHOD "B"S.Y.17,965*
325SEPARATOR FABRICS.Y.17,965*
411(B)SUPER PAVE, TYPE "S3" (PG64-22 OK) (3.5" THICK)TON2,770*
411(C)SUPER PAVE, TYPE "S4" (PG70-28 OK) (2" THICK)TON1,590*
414(Al6" P.C. CONCRETE PAVEMENTS.Y.2,995*
509(B)CLASS A CONCRETE (CONCRETESWALE)C.Y.95
609(8)6" CONCRETE CURB & GUTTERL.F.1,070
610(A)4" CONCRETE SIDEWALKS.Y.405
613(El18" ADS HP STORM (GRAY PIPE)L.F.140
619(A)REMOVAL OF STRUCTURES AND OBSTRUCTIONSL.S.1
619(8)REMOVAL OF ASPHALT OR CONCRETE PAVEMENTL.S.1
641MOBILIZATIONL.S.1
642(AlCONSTRUCTION STAKING LEVEL 1L.S.1
643CONTRACTOR TESTING AND QUALITY CONTROLL.S.1
SPECSTRIPINGL.S.1
SPECSIGNSL.S.1
SPECTRAFFIC CONTROLL.S.1
SPEC5'x5'x5' DEEP AREA WITH 3" STON EL.S.1
SPECBUMPER BLOCKSEA.83
SPECCONCRETE SLOPEWALL FOR SINGLE 18" PIPEEA.1

BID TOTAL $

SPEC TERO TAX BASED ON TOTAL BID LS 3.00%

BID TOTAL WITH TERO TAX $