This document is Amendment #2 to Request for Quote (RFQ) #140A0126Q0043 for Phase I Environmental Site Assessment (ESA) services for the Great Plains Regional Office (GPRO) of the Bureau of Indian Affairs (BIA). The amendment includes questions and answers addressing offeror inquiries regarding the solicitation.

The RFQ requires Phase I ESA services for eight properties located in North Dakota and South Dakota, with eight Contract Line Item Numbers (CLINs): Charles Fettig (CLIN 00010), Howard Fettig (CLIN 00020), Gladue (CLIN 00030), Bear Butte Tract (CLIN 00040), Leiseth I (CLIN 00050), Leiseth II (CLIN 00060), Johnson (CLIN 00070), and an unnamed eighth property (CLIN 00080). All assessments must follow ASTM E1527-21 standards and be conducted in individual reports for each site, with site visits available immediately upon award and BIA coordination of access. The due date for quotations was extended from September 3, 2026 to September 8, 2026 at 5:00 PM PT. The period of performance is one year, with all deliverables due by September 30, 2027. Contractors may submit invoices per line item upon delivery and acceptance of each individual Phase I ESA report. No TERO (Tribal Employment Rights Office) requirements apply. BIA will provide government escort for site access if needed and will coordinate with associated Tribes as required. The solicitation is a firm-fixed-price contract administered by BIA Pacific, with offerors required to acknowledge receipt of this amendment by completing blocks 8 and 15A-C of the Standard Form 30 and returning the completed page 1 with their quotation.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Jodi Zachary

See continuation page

BIA PACIFIC 00013

2800 COTTAGE WAY ROOM W2820

Contracting Office Sacramento CA 95825

DOI, BIA PACIFIC

Contracting Office

2800 COTTAGE WAY ROOM W2800

Sacramento CA 95825

A13

A13

140A0126Q0043

08/21/2026

08/21/2026

1 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140A0126Q0043/0002

The purpose of the Amendment 0002 is to release all questions asked and the responses provided by BIA

The Due Date for quotes is hereby changed from

9/3/26, 5pm PT, to now read 9/8/26, 5pm PT.

All interested parties submitting a quotation must complete blocks 8 and 15A-C of this

Amendment AND INCLUDE the completed page 1 of this Amendment with their quotation.

All terms and conditions of the solicitation remain unchanged.

Period of Performance: 09/24/2026 to

09/30/2027

RFQ #140A0126Q0043

Phase I Environmental Site Assessment for GPRO

Amendment #2 Questions & Answers

1. The aerials provided for Attachment 2 C Fettig and Attachment 3 H Fettig appear to be the same. No, they are not the same. Please see the revised Attachment 3, map for HFettig.

2. General question across all 8 sites: are there any buildings on these properties? If so, which properties are developed and which are undeveloped land? BIA has no information about what is located on each site.

3. If the properties are developed, are they developed for residential, commercial, or industrial uses? (i.e., any gas stations associated with these properties?) BIA has no information about what is located on each site.

4. On the Bear Butte Tract, the aerial shows areas highlighted in purple and red. Can you confirm that we would be performing the Phase I ESA on the purple parcels? Both parcels are included, as shown by the legal description on the map provided.

5. Would the BIA like our Phase I ESA to include chain of title search and/or environmental lien search? No

6. Are there 3 parcels associated with Leiseth 1? If so, can BIA provide where the parcel on page 2 of Attachment 6 in located in relation to the two on Page 1? We are trying to determine if they are close enough to perform a single Phase I ESA report that covers all three parcels.

The maps have the legal description that identifies the parcel location. Although the parcels are not contiguous, they may be addressed in a single report.

7. Can BIA provide aerial maps for Attachment 4 Gladue and Attachment 8 Johnson? All currently available files have been provided.

8. Item No. 00010 and 00020: The figures for CFettig-Attachment 2 and HFettig-Attachment 3 show the same legal description for Charles Fettig. Please provide an updated figure for HFettig. See revised attachment.

9. Item No. 00030: No legal description or figure was provided for Gladue. Please provide a legal description along with a figure outlining the 65 acres. See revised attachment.

10. Item No. 00030 and 00060: For Gladue and Leiseth II, the description under Supplies/Services states, "inspect for hazardous materials." Please confirm whether any structures on these properties require a hazardous materials survey for asbestos, lead paint, and other typical materials inspected for during a Hazardous Materials Survey. It is unknown what structures are on the properties. The requirement to “inspect for hazardous materials” applies to all sites and refers to the standard Phase I Environmental Site Assessment (ESA) reconnaissance, which includes identifying potential environmental concerns.

11. Item No. 00070: No legal description or figure was provided for Johnson. Please provide a legal description along with a figure outlining the 487.68 acres. See revised attachment.

12. Can the Government provide shapefiles or KMZ files for the parcels? Contractor responsible for creating shape or KMZ files.

13. Will BIA coordinate access and escort to the parcels for the site reconnaissance phase of the site assessment? Yes

14. In the SAM listing, the map for Charles Fettig (CLIN 10) is the same as the Howard Fettig (CLIN 20) map and does not align with the legal description of the parcels. Is a map available that shows the Howard Fettig parcels of interest? Please provide relevant locational information (e.g., map, township, range, etc.). See attachments.

15. Maps are not presented for the Gladue (CLIN 30) and Johnson (CLIN 70) parcels. Are maps available for the Gladue and Johnson parcels? See attachments.

https://sam.gov/workspace/contract/opp/18e613e892f44b1fa9ccc664ea83c911/view

Amendment #2 Questions & Answers

16. Site questionnaires are provided for some parcels. Are completed questionnaires available for all eight parcels? If so, please provide. Also, will the Government provide updated “Questionnaire for Interview” responses? The responses provided are over 1 year old. All files currently available have been provided.

17. Have any of these sites had prior Phase ESAs? No

18. If so, will these reports be provided? No

19. Will the Government provide copies of available records noted in the Land Description and

Validation checklists? All files currently available have been provided.

20. Will Activity and Use Limitations (AULs) and Environmental Liens searches back to 1980 be required? All files currently available have been provided.

21. Will the Government provide available chain-of-ownership records for all properties? All files currently available have been provided.

22. The Howard F. Fettig line item is described as an undivided 24.97% mineral interest with no accompanying surface interest. Does the Government intend for the contractor to conduct surface site reconnaissance on this parcel? Yes

23. and if so, can BIA facilitate coordination with the surface estate owner? Contractor responsible for identifying and locating these individuals.

24. Section 1.5 and Amendment 0001 state a single Period of Performance of 09/24/2026 to 09/30/2027, but the SF-1449 schedule shows a Delivery date of 09/30/2027 for line items 00010–00030 and 09/30/2028 for line items 00040–00080. Can BIA clarify the correct delivery schedule for each line item? The period of performance is 1 year. All lines will end 9/30/27 on the final award.

25. Does BIA have current landowner and/or occupant contact information for each of the eight parcels to support the interview component of the assessment? Contractor responsible for identifying and locating these individuals.

26. Are there any access limitations that will need to be considered? None

27. Will all on-site structures be accessible? Yes with Government escort? If needed.

28. Is the Government able to provide TAAMS legal description printouts and any prior environmental investigation records (if they exist) for these parcels as government-furnished information, or is the contractor expected to obtain these independently? All files currently available have been provided.

29. Does BIA require a separate Phase I ESA Report for each of the eight parcels, or may parcels located in the same county be combined into a single report where appropriate? Individual report for each site listed in contract.

30. Does BIA have a preferred report template or format, or should the contractor prepare each report using its own ASTM E1527-21-compliant template? ASTM E1527-21-compliant template.

31. The SOW references "the current applicable ASTM standard" while the SF-1449 schedule specifies ASTM E1527-21. Please confirm E1527-21 is the applicable standard for this requirement. ASTM E1527-21 is the current applicable standard for this requirement.

32. Will a single BIA Technical POC be assigned for coordination across all eight sites, or will points of contact vary by parcel or by state (ND/SD)? Both are correct. There will be a POC at the Regional Office and POC’s at the agencies.

33. Will any direct coordination or consultation with the associated Tribes be required? Yes

Amendment #2 Questions & Answers

34. Will work in any of these project areas be subject to TERO requirements? If so, please identify applicable sites/locations/Tribes and provide the applicable TERO office contact information for each location. This project is not subject to TERO.

35. Given the requirement to price each line item individually, may the contractor submit invoices per line item upon delivery and acceptance of each individual Phase I ESA report, or is a single consolidated invoice required after all eight reports are accepted? The contractor may submit invoices per line item, upon delivery and acceptance of each individual Phase I ESA report.

36. We kindly request an extension to 9/10/26 to allow offerors adequate time to review the Government's responses and incorporate additional information into a complete and accurate quote. The RFQ is hereby extended to 9/8, 5pm PT

37. Issue 1 — SF-1449 pricing block instructions conflict

• Section 6.3 says: “Complete Block 20, on pages (2)-(4) of the SF-1449, for line item

00010-00080, reflecting the Firm-Fixed-Price.”

• But Block 20 is the Schedule of Supplies/Services description column, while the SF-1449 identifies:

• Block/column 23 = Unit Price

• Block/column 24 = Amount

• and the SF-1449 face says the offeror should complete Blocks 12, 17, 23, 24, and 30.

• Question to ask: Should offerors enter the FFP for CLINs 00010–00080 in Columns 23 and 24, rather than “Block 20” as stated in Section 6.3?

Yes, use blocks 23 and 24

38. Issue 2 — “Pages 2–4” do not contain all eight CLINs Section 6.3 says price CLINs 00010–00080 on pages 2–4.

But:

• 00010 begins page 2

• 00020–00030 are page 3

• 00040–00060 begin page 4

• 00060 continues onto page 5

• 00070 and 00080 are on page 5

• 00080 continues onto page 6.

Question to ask: Should the Section 6.3 reference to pages 2–4 read pages 2–6?

Yes, completed and return pages 2-6

39. Issue 3 — Period of performance / delivery dates conflict

• Amendment 0001 says: 09/24/2026–09/30/2027.

• The solicitation also describes the tentative performance period as award through 09/30/2027.

• However, several CLIN entries in the SF-1449 show Delivery: 09/30/2028, including later line items.

• That is a discrepancy.

Please confirm whether the final completion/delivery date for all CLINs 00010– 00080 is September 30, 2027, consistent with Amendment 0001, or whether any CLINs actually extend through September 30, 2028.

The period of performance is 1 year. All lines will end 9/30/27 on the final award.

Amendment #2 Questions & Answers

40. Issue 4 — Legal description or map is missing from Gladue Property

• Only provided information is the Realty Land Description Review Form and the questionnaire.

Question to ask: Where is the Gladue Property located? Is there a map or legal description available?

Map is attached, with legal description

41. Issue 5 — CLINs 00010 and 00020 are for the same property (Fettig); just for different proportions of surface or mineral rights. Yes

42. Are separate Phase 1 ESAs required for the Charles Fettig and Howard Fettig property? Yes

43. Will all sites be available for site visits immediately upon award? Yes Or would site visits need to be staggered over the period of performance? Not necessary

44. Will BIA coordinate site access permissions? Yes

45. Phase I Environmental Site Assessments are valid for 180 days prior to property transaction.

When are the property transactions scheduled? Transactions are scheduled after all Permit to Operate objections are cleared Will property transactions be staggered or all at the same general timeframe? Unknown what is being asked.

End https://sam.gov/workspace/contract/opp/18e613e892f44b1fa9ccc664ea83c911/view

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .