The document is a pricing tabulation spreadsheet for a bid solicitation by Indian River County, Florida, involving the replacement of sodium hypochlorite storage tanks at two water production facilities. The project requires removing and replacing three existing 6,500-gallon tanks at the Hobart Water Production Facility and removing two existing 5,500-gallon tanks, with one being replaced at the Oslo Water Production Facility. The contractor must complete the tank replacements while maintaining full water plant operations.
The pricing tabulation shows two bidders: E&W Mechanical Contracting and Odyssey Manufacturing Co. Odyssey Manufacturing Co. submitted the lower total bid of $245,178.00, compared to E&W Mechanical Contracting's bid of $300,231.00. The breakdown includes $190,153.00 for the Hobart Water Production Facility tank replacements and $55,025.00 for the Oslo Water Production Facility tank replacements. The bid includes a lump sum pricing structure, with the lowest-priced bidder highlighted in green cells on the spreadsheet.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Legend
Pricing Sheet (BT-58WN)
Legend
| The green cells with bolded numbers indicate that this bid was the lowest price. | $ 123 |
| The orange cells indicate that this item from that vendor was selected. | |
| The green cells with orange outline indicate that this item from that vendor was selected, and has the lowest price. |
Sheet 1
| E&W Mechanical Contracting | Odyssey Manufacturing Co. | ||||||||
| Total Cost | $ 300,231.0 | $ 245,178.0 | |||||||
| Selected # | 0 | 0 | |||||||
| Selected ($) | $ 0 | $ 0 | |||||||
| # | Locked | Items | Selected | Lowest | Quantity | ||||
| Required | Lump | ||||||||
| Sum | Unit | ||||||||
| Price | Total | ||||||||
| Cost | Unit | ||||||||
| Price | Total |
Cost
| 0 | No Basket (2) | |||||||||
| #0-1 | FALSE | Remove and replace 3 existing 6,500-gallon tanks at Hobart Water Production Facility | $ 0 | $ 190,153.0 | 1 | LS | $ 240,185.0 | $ 240,185.0 | $ 190,153.0 | $ 190,153.0 |
| #0-2 | FALSE | Remove 2 existing tanks and replace 1 5500-gallon tank at Oslo Water Production Facility | $ 0 | $ 55,025.0 | 1 | LS | $ 60,046.0 | $ 60,046.0 | $ 55,025.0 | $ 55,025.0 |