- CSP - Grease Waste Infrastructure Replacement at Ben Taub for Harris Health (Estimated Budget $948, 500)
- Solicitation number
- 26/0039
- Issued by
- Harris County, Texas
About this file
This is a Competitive Sealed Proposal (CSP) document issued by Harris Health, a Harris County entity, for Grease Waste Infrastructure Replacement at Ben Taub Hospital located at 1504 Taub Loop, Houston, Texas. The project involves furnishing all personnel, labor, materials, equipment, and incidentals necessary to replace grease waste infrastructure at the facility. Harris Health released the CSP on February 6, 2026, with a mandatory pre-proposal conference and site visit scheduled for February 23, 2026, at 10:00 a.m. CST. Attendance at the pre-proposal conference and site visit is mandatory for all vendors intending to submit a proposal, and vendors must sign in to be eligible. Written questions must be submitted by February 27, 2026, with responses posted by March 6, 2026. Proposals are due no later than 2:00 p.m. CDT on Monday, March 16, 2026, with anticipated Board of Trustees approval on May 13, 2026. The contract does not specify an explicit term or renewal options.
The estimated project budget is $948,500, and Harris Health anticipates awarding to a single vendor, though it reserves the right to award to multiple vendors if in its best interest. Pricing constitutes 50% of the evaluation criteria, with qualifications, safety, and past performance weighted at 30% and technical approach and methodology at 20%. All-inclusive rates quoted on the BidTable must incorporate all charges for labor, materials, equipment, and other costs with no separate line-item rates accepted. Each proposer must submit a bid bond or cashier's check for 5% of the total bid amount. The vendor selected must provide a 100% performance and/or payment bond for the entire construction budget. Payment terms are Net 30 from the date Harris Health approves the invoice. The project is subject to Texas Government Code Section 2258 prevailing wage requirements and Section 2253.021 performance and payment bond requirements. Harris Health has established a 30% Minority/Woman-owned Business Entity utilization goal, and vendors must complete and submit an MWBE Utilization Plan. All vendors must complete Form 1295 (Certificate of Interested Parties) prior to proposal submission.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMPETITIVE SEALED PROPOSAL FOR
Grease Waste Infrastructure Replacement at Ben Taub for Harris Health
JOB NO. 26/0039
4800 FOURNACE PLACE
BELLAIRE, TEXAS 77401
PROPOSALS ARE DUE NO LATER THAN:
Monday, March 16, 2026 AT 2:00 P.M. CDT
TABLE OF CONTENTS
SECTION PAGE
1.0 Procurement Schedule 3
2.0 Scope of Work 3
2.1 Overview and Purpose
2.2 Mandatory Pre-Proposal Conference
2.3 Questions
2.4 Specifications
2.5 Certificate of Interested Parties (Form 1295)
3.0 Evaluation 4
3.1 Evaluation Criteria
3.2 Award
3.3 Submittals
4.0 Special Requirements For Proposers 8
4.1 No Confidentiality of Competitive Sealed Proposal
4.2 Evaluation Process
4.3 Onsite Staff Policies
4.4 Toll/Parking
4.5 Drawings/Additional Specifications
4.6 Additional Requirements
4.7 Prevailing Wages
4.8 Contract Transition
1.0 PROCUREMENT SCHEDULE
1.1 The Procurement Schedule is as follows, understanding it is a tentative schedule and may be modified as necessary by the Sourcing Manager.
DATE ITEM
02/06/2026 Release of CSP document and posted in Euna fka Bonfire
02/23/2026 Mandatory Pre-Proposal Conference (See Section 2.2) 02/27/2026 Questions Due (See Section 2.3) 03/06/2026 Reponses to Questions posted in Euna
03/16/2026 Proposals are due no later than 2:00 PM local time in Houston, Texas
5/13/2026 Anticipated Approval from Board of Trustees
2.0 SCOPE OF WORK
2.1 OVERVIEW AND PURPOSE
The intention of this Harris County Competitive Sealed Proposal (CSP) is to solicit offers for Grease Waste Infrastructure Replacement at Ben Taub for Harris Health.
2.2 MANDATORY PRE-PROPOSAL CONFERENCE AND SITE VISIT
There will be a MANDATORY PRE-PROPOSAL CONFERENCES AND SITE VISIT on February 23, 2026 starting at 10:00 a.m. CST. The site visit will be conducted at Ben Taub Hospital, 1504 Taub Loop, Houston, TX 77030. All required solicitation information will be presented exclusively during the Pre-Proposal Conference at Ben Taub Hospital prior to the site visit. Vendors shall assemble in the garden area of Ben Taub. A MANDATORY SITE VISIT will be conducted to allow vendors to inspect the work locations. Attendance is mandatory and all vendors intending to submit a proposal must attend to discuss the requirements of this CSP and hear the answer to questions. A vendor sign-in sheet will be provided and Vendors must sign in to be eligible to submit a proposal. The site visit will not be conducted until the representative of Harris County Purchasing Office is present and vendors have signed in. The pre-proposal conference and site-visit will not be rescheduled due to tardiness or any other issues that may arise; no exceptions. Persons with disabilities requiring special accommodations should contact the Purchasing Office at (713) 274-4400 at least two (2) days prior to the pre-proposal conference.
2.3 QUESTIONS
It is the responsibility of each vendor to examine the entire Competitive Sealed Proposal (CSP) package, seek clarification in writing, and review their response for accuracy before submitting. Questions relating to this CSP must be submitted in writing in Euna at https://harriscountytx.bonfirehub.com no later than the date listed in Section 1.0 Procurement Schedule and the Events Schedule within Euna. However, questions received after the Question Deadline are not guaranteed responses. All questions submitted in writing prior to the deadline will be compiled and responded to via an https://harriscountytx.bonfirehub.com/
Addendum, and vendors will be notified of the Addendum by public notice in Euna. Harris Health will not be bound by any information conveyed verbally.
2.4 SPECIFICATIONS
This project consists of the vendor furnishing all personnel, labor, materials, equipment and incidentals necessary for the Grease Waste Infrastructure Replacement at Ben Taub for Harris Health To get a better understanding of this project, please refer to the Project Manual, and Drawing available in Euna.
The rates quoted on the BidTable must be all-inclusive. “All-inclusive" shall be construed as costs incorporating all charges for labor, material, equipment and any other cost incurred. No separate line-item rates or charges will be accepted.
2.5 CERTIFICATE OF INTERESTED PARTIES (FORM 1295)
Texas law requires all parties who enter into any contract with the Harris County Hospital District which must be approved by its Board of Trustees to disclose all interested parties.
Form 1295 must be completed in its entirety at the following website:
https://www.ethics.state.tx.us/whatsnew/elf_info_form1295.htm prior to submitting your response. Failure to do so may result in disqualification of your response.
3.0 EVALUATION
3.1 EVALUATION CRITERIA
Award shall be made to the responsible vendor whose proposal is determined to be the best evaluated offer resulting from negotiations and taking into consideration all aspects of proposal impact items and the following:
a. Qualifications, Safety, & Past Performance ……………………………………….30%
(Vendor demonstrates their ability to meet the required qualifications listed herein.
Identify the team who will be assigned construction management responsibility and the construction superintendent. Provide experience with similar projects and experience in healthcare environment no fewer than five (5) projects similar in size, scope, and type to the one described in this CSP. Provide the name and location of each project, the client, contact person and number. Describe the firm’s safety experience working on construction projects of similar scope. Vendor’s ability to fully bond the project.)
b. Technical Approach & Methodology……………………………………………....20%
(Vendor shall provide a detailed and comprehensive explanation of the proposed approach and methodology required for this project. The submission should demonstrate a thorough understanding of the project scope, site conditions, schedule requirements, and quality expectations. Vendor must outline their proposed construction management responsibility, including project execution strategies, coordination methods, schedule development, and quality assurance/quality control processes. Vendor shall also provide examples of similar projects—preferably involving medical, governmental, or other complex facility https://www.ethics.state.tx.us/whatsnew/elf_info_form1295.htm environments—that demonstrate their experience and capacity to perform work of comparable size and scope. Provide the project name, location, client, contact information, and a brief description highlighting relevance to this CSP.)
c. Pricing (Please refer to Section III) ………….………………………….……………50%
Submission of a proposal implies the vendor's acceptance of the evaluation criteria and vendor’s recognition that subjective judgments must be made by the Evaluation Committee.
3.2 AWARD
Harris Health anticipates awarding to a single vendor. However, Harris Health reserves the right to award to more than one (1) vendor if in the best interest of Harris Health.
The award cannot be finalized until Harris Health’s Contract Diversity Department has thoroughly evaluated and approved the vendor’s MWBE Utilization Plan and until approved by Harris Health Board of Trustees. This CSP does not obligate Harris Health to the eventual purchase of any product/service described, implied or which may be proposed. Progress toward this end is solely at the discretion of Harris Health and may be terminated at any time prior to execution of a contract.
3.3 SUBMITTALS
Sections I-VI below must be uploaded under Euna’s Requested Information section.
A. Section I: Transmittal Letter:
The transmittal letter should not exceed three (3) pages and should include:
i. Company name and address; name, title, email, telephone and fax number of person(s) to be contacted for clarifications or additional information regarding proposal,
ii. Name, title, email, telephone and fax number of person authorized to contractually obligate vendor’s company with proposal,
iii. A brief statement summarizing the vendor’s understanding of the project and relevant experience.
B. Section II: Scope of Service/Narrative of Proposed Services
i. Describe your firm’s philosophy, approach(es) and preferred methods for meeting requirements and/or deliverables in the Specifications sheets of this
CSP.
ii. Provide the greatest amount of meaningful detail possible to describe the proposed products/services. Indicate if vendor can meet the specifications, or if the specifications can be met only under certain conditions or circumstances. If vendor is not able to meet the specification, briefly explain why, noting any concerns or issues Harris County should be aware of.
iii. Provide a timeline indicating deliverables/estimated completion date from the time a Purchase Order is issued (calendar days), vendor responsibilities and resources needed from Harris County.
iv. Define reporting capabilities including monthly management reports, comprehensive invoicing, notification, and electronic capabilities. Include samples of reporting procedures, any standard reporting forms provided to the customer, and additional programs available to customers.
v. Provide safety record for each of the past three (3) calendar years, and describe firm safety experience working on construction projects of similar scope. The safety record should be supported by accurate and verifiable date.
vi. List identifying any potential subcontractors, professionals, suppliers, and vendors that you may work with on this project.
vii. Describe any professional liability limits.
viii. Describe any other consultant relationships.
ix. Describe and/or include information concerning warranty.
x. Provide current workload and projects.
Mere reiterations of specifications are strongly discouraged, as they do not provide insight into the vendor’s ability to meet the specifications.
C. Section III: Pricing Information – See the BidTable within Euna for instructions. Each proposer must submit a bid bond or cashier’s check for five percent (5%) of the total amount bid as required in attachment Bid Guaranty & Performance Bond
Information & Requirements and in attachment Bid Check Return Authorization Form
(if applicable). When submitting through Euna and electing to provide a cashier’s check in lieu of a bid bond, the cashier’s check must be physically dropped off in a sealed envelope referencing the Ref. # (Job No.) from Euna before the due date at
1111 Fannin, 12th Floor, Houston, TX 77002.
D. Section IV: Organizational Information/Qualifications
a) Vendor’s history, background and principal officers.
b) Company organization chart.
c) Provide documentation of experience and training in applying Interim Life
Safety Measures (ILSM) and the use of Infection Control Risk Assessment (ICRA) techniques. Consideration will be made for infection control procedures.
d) Detailed project execution plan, or methodology, that discusses principles, practices, and procedures to be used by the vendor in implementing associated work for this project. The information should include, but not be limited to, a discussion of design services, project mobilization, use of subcontractors (if applicable), a project organization chart, project manager identification, quality assurance program, safety record, and reporting capabilities. Briefly:
a. Project mobilization means the time required to have a team in place at the job site once the Purchase Order has been issued, and identification of which skills would be performed by the vendor and by any required subcontractors.
b. Subcontractor discussions should include information regarding the program that is used to pre-qualify a subcontractor as satisfactory due to their financial stability and technical qualifications. Vendor shall provide detailed information regarding pre-approved subcontractors, such as name of firm, address, phone number, contact, area of specialty(ies), size of work force, and years as a pre-approved subcontractor.
c. A project organization chart should detail the team to be assigned to Harris County. The organizational chart shall show the chain of command, and the role and responsibility of each member. (The vendor shall keep Harris Health up to date with a revised organization chart each time there is a significant change).
d. Vendor must provide Harris Health with a quality assurance program that ensures, at a minimum, the following:
i. Utilization of proper materials
ii. Utilization of satisfactory workmanship
iii. Correction plan if unsatisfactory materials or workmanship is utilized
iv. That all necessary paper work, drawings, and documentation follow the job from start to finish and ensure compliance with construction documents approved submittals, request for information (RFI) and change in contracts (CIC)
v. That entire job is complete on time as mutually agreed, and to satisfaction of Harris Health
e) Vendor must provide Harris Health with, at a minimum, monthly computer-generated reports that will provide an overview of the project, showing originally estimated completion date, actual start date, and revised completion date, if any. Revised completion dates must include detailed explanations.
f) Summary of credentials, licenses and accreditations.
g) Identify vendor’s contracts of similar size and scope.
h) Fiscal and Bonding Capacity:
a. List your total annual billings for each of the past five (5) calendar years,
b. Supply financial references,
c. After proposal(s) are opened but prior to award, the vendors may be required to submit upon request financial statements that include a balance sheet, audited annual statement & income statement.
d. The vendor selected for this project must provide a 100% performance and/or payment bond for the entire amount of the construction budget. Provide a letter from a bonding company demonstrating your ability to satisfy this requirement.
E. Section V: Miscellaneous:
State exceptions to any of the requirements in this CSP, if any.
F. MWBE Utilization Plan Review the MWBE Utilization Plan for information on Harris Health’s 30% Minority/Woman-owned Business Entity goal for the purchase of the requested goods or services. The packet will also have instructions on how to complete the Utilization Plan and the Letter of Intent, which is required to be uploaded into Euna as part of your proposal submission.
This CSP is governed by the procedures as contained in §2269 et seq., Subchapter D of the Texas Government Code. Therefore, award of contract(s) shall be made to the provider of the required services that is evaluated to be the best value based on selection criteria, and, after negotiations, if needed, whose pricing is considered to be fair and reasonable. Harris Health does not accept any financial responsibility incurred in order to respond to this CSP. In addition, Harris Health reserves the right to accept or reject any or all CSPs, or waive any and all formalities not considered advantageous to
Harris Health.
Harris Health will not be liable for any costs incurred by the vendor in preparing a response to this CSP. Vendors submit proposal(s) at their own risk and expense. Harris
Health makes no guarantee that any products or services will be purchased as a result of this CSP and reserves the right to reject any and all proposals. All proposals and accompanying documentation will become the property of Harris Health. All proposals are open to negotiation.
The vendor is expected to examine all documents, forms, specifications, and all instructions. Failure to do so will be at vendor’s risk.
4.0 SPECIAL REQUIREMENTS FOR PROPOSERS
4.1 NO CONFIDENTIALITY OF COMPETITIVE SEALED PROPOSALS
Once opened, proposals are public records. There are no exceptions. When submitting a proposal, vendor must be sure to redact confidential information if the information is needed to address requirements of the bid. If there are any questions concerning confidentiality of information to be submitted, contact the Buyer listed within Euna.
4.2 EVALUATION PROCESS
All proposals will be examined by an evaluation committee consisting of various Harris Health and Harris County Purchasing personnel and ranked according to the selection criteria set out above. Harris Health will select the vendor that, in the opinion of Harris Health, submits the proposal that offers the best value for Harris Health based on the selection criteria and the weighted value for each selection criteria and the weighted value for each selection criteria and on Harris Health’s ranking evaluation. The vendor that offers the best value may or may not be the vendor that submits the lowest proposal for the cost of construction.
Proposals that do not conform to the instructions or which do not address all the services as specified may be eliminated from consideration. However, Harris Health, reserves the right to accept such a proposal if it is determined to be in the best interest of Harris Health.
While Harris Health appreciates a brief, straightforward, concise reply, the proposer must fully understand that the evaluation is based on the information provided. Accuracy and completeness are essential. Omissions, ambiguous and equivocal statements may be construed against the proposer. The proposal response may be incorporated into any contract which results from this CSP, and vendors are cautioned not to make claims or statements it is not prepared to commit to contractually. Failure of the vendor to meet such claims will result in a requirement that the vendor provide resources necessary to meet submitted claims.
Harris County Purchasing may initiate discussions with selected vendors; however, discussions may not be initiated by vendors. Harris County Purchasing expects to conduct discussions with vendor’s representatives authorized to contractually obligate the vendor with an offer. Vendors shall not contact any Harris Health personnel during the CSP process without the express permission from the Office of the Harris County Purchasing Agent.
Harris County Purchasing may disqualify any vendor who has made site visits, contacted Harris Health personnel or distributed any literature without authorization from Harris County Purchasing.
All correspondence relating to this CSP, from advertisement to award shall be sent to the Harris County Purchasing. All presentations and/or meetings, if applicable, between Harris Health and the vendor relating to this CSP shall be coordinated by the Harris County Purchasing.
Harris Health may conduct negotiations with vendor’s representatives authorized to contractually obligate the vendor with an offer. If vendor is unable to agree to contract terms and conditions, Harris Health reserves the right to terminate contract negotiations with that vendor and initiate negotiations with another vendor.
4.3 ONSITE STAFF POLICIES
Policies for onsite staff can be found here: https://www.harrishealth.org/Pages/vendor-relations.aspx. At a minimum, please review policy 3.55.00. Additional policies and procedures in Euna.
4.4 TOLL/PARKING FEES
All toll/parking FEES incurred by the vendor during the term of this contract will be the responsibility of the vendor.
4.5 DRAWINGS/ADDITIONAL SPECIFICATIONS
Vendors may download drawings, additional specifications, plans, and/or maps for this project from Euna at harriscountytx.bonfirehub.com portal as referenced in the attachments titled Project Manual and Drawing. Do NOT include the drawings from this CSP package with the vendor’s submittal.
https://www.harrishealth.org/Pages/vendor-relations.aspx https://www.harrishealth.org/Pages/vendor-relations.aspx
4.6 ADDITIONAL REQUIREMENTS
Where these special requirements and information as detailed in attachment General Conditions for Building Construction and Related Work, differ from the General Requirements for Proposals, the specific requirements within the General Conditions for Building Construction and Related Work, supersede where applicable.
Brand names and model numbers that may appear in the documents of this CSP are for reference only. It is not the intent of Harris Health to restrict these bids in such cases, but to establish a desired quality of level of merchandise or to meet a pre-established standard due to like existing items. Offerors may offer items of equal stature and the burden of proof of such stature rests with offerors. Harris Health shall act as sole judge in determining equality and acceptability of products offered. After opening of proposals, but prior to award recommendation, Harris Health may require documentation demonstrating equal or superior products as compared to products required.
Coordination of the project will be through Harris Health and all invoices must be routed through their department. All invoices shall include submission requirements stated in the specifications including completed certified payroll records and lien waivers. Payment terms are “Net 30” from date the invoice is approved by Harris Health; therefore, payment to the vendor may be up to one (1) month from the date the invoice is approved by Harris Health.
In addition, the vendor must comply with Texas Government Code (GC) 2258, Prevailing Wage Rates, and GC 2253.021, Performance and Payment Bonds. Accordingly, GC 2258 requires the vendor to submit a certified payroll record as detailed in the attachments titled Prevailing Wage Rates, Worker Classification Definitions and Payroll Submittal Instructions.(https://oce.harriscountytx.gov/Services/Consultants-Resources-and- Specifications/Construction/Prevailing-Wage-Rates),and compensate any worker employed on a public works project not less than as applicable. As well, GC 2253.021, Performance and Payment Bonds, requires the vendor to provide a payment bond on all public works jobs that exceed $25,000, and a performance bond on all public works jobs that exceed $100,000.
4.7 PREVAILING WAGES
In accordance with Section 2258 of the Texas Government Code, contractor and any subcontractor hired by contractor for the construction of any project, shall not pay less than the rates set forth in the Schedule of Prevailing Wages attached and incorporated by reference in each Project Manual. Contractor warrants that it and its subcontractors shall comply with all requirements and worker ratios per the applicable Schedule of Prevailing Wages and Texas state law.
Contractor shall submit certified payroll of contractor and all subcontractors on a weekly basis. At Harris Health’s request, contractor shall make available and shall require its https://oce.harriscountytx.gov/Services/Consultants-Resources-and-Specifications/Construction/Prevailing-Wage-Rates) https://oce.harriscountytx.gov/Services/Consultants-Resources-and-Specifications/Construction/Prevailing-Wage-Rates) subcontractors to make available, copies of cancelled checks and check stubs for comparisons by the Harris Health or its agents.
Harris Health reserves the right for its agents to visit the project site and to interview contractor, its subcontractors and employees of each on any date or time, as often as desired during the construction period, without prior notification.
Harris Health will ascertain if proper wage rates are being paid to the employees as required by the Project Manual. In the event of a discrepancy between the work performed and the wages paid, Harris Health will document same and notify contractor.
All initial determinations of the classification of workers or the appropriate prevailing wage shall be made by the Harris Health Contract Compliance Officer. Her determinations shall be binding.
If, for any length of time and as determined by the Harris Health Contract Compliance Officer, discrepancies appear between the certified payrolls and the actual wage paid, County shall require check stubs to be attached to each weekly certified payroll.
Pursuant to TEX. GOV’T CODE ANN. §2258.051, the County reserves the right to withhold any monies due contractor until such discrepancy is resolved and the necessary adjustment made. Contractor shall also pay a penalty in accordance with TEX. GOV’T CODE ANN. § 2258.023(b), of Sixty and No/Dollars ($60.00) per day per person per incident that such person is underpaid. Contractor shall impose these same obligations upon its Subcontractors. Contractor understands that with monthly certified payrolls, contractor is responsible for any and all penalties that shall accrue during the month, regardless of the fact that any error could not be discovered by the Contract Compliance Officer until the following certified payroll.
4.8 CONTRACT TRANSITION
In the event services end by either contract expiration or termination, it shall be incumbent upon the vendor to continue services, if requested by Harris County Purchasing, until new services can be completely operational. The vendor acknowledges its responsibility to cooperate fully with the replacement vendor and Harris Health to ensure a smooth and timely transition to the replacement vendor. Such transitional period shall not extend more than ninety (90) days beyond the expiration/termination date of the contract, or any extension thereof. The vendor shall be reimbursed for services during the transitional period at the rate in effect when the transitional period clause is invoked by Harris Health. During any transition period, all other terms and conditions of the agreement shall remain in full force and effect as originally written.
File details come from the government source that posted it. Updated .