Amendment 0001 to Solicitation 1333ND26RNB190025 – Building 2A Demolition Project

This is Standard Form 30 Amendment to Solicitation issued by the National Institute of Standards and Technology (NIST), effective July 17, 2026. The amendment incorporates 49 offeror Requests for Information (RFIs) with government responses, revises the Statement of Work, and adds supporting documentation. Key clarifications from RFI responses address hazardous materials (no ACM report available; pricing to assume no known ACM with potential later modification), utility disconnection procedures (wet utilities capped at building interior, abandoned-in-place acceptable with documentation), complete removal of concrete foundations, contractor responsibility for furniture and equipment removal remaining in the building, and engineering design requirements limited to specific scopes only (full PE-stamped design package not required). The amendment extends the RFI due date to July 22, 2026 (3:00 PM MT) and shifts the offer due date from July 22, 2026 to August 12, 2026 (3:00 PM MT).

The SOW revisions for Task 1 (Demolish Building 2A) add requirements for removal of remaining interior furnishings, fire alarm programming modifications to be coordinated with Tech Electronics and NIST FPAD, and a Site Layout Concept Plan with specified graphics showing construction perimeter fencing, dumpster and restroom locations, material storage areas, heavy equipment storage, and emergency responder access drives. Two additional documents are added separately to the attachments: "06 Below Grade Condition Requirements.pdf" and "07 B2A DEMO TOPO.pdf." The estimated period of performance is 180 calendar days and is identified as negotiable, with an estimated start date of October 1, 2026 for evaluation purposes only.

View the file

Other files

File Type Posted
06 Below Grade Condition Requirements.pdf PDF
07 B2A DEMO TOPO.pdf PDF
Site Visit Sign-In.pdf PDF
260604 B2A Additional Supporting Documents.zip ZIP file
Attachments.zip ZIP file
1333ND26RNB190025 B2a Demo NIST Boulder CO.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Attachment Page

PAGE 2 OF 21 1333ND26RNB1900250001

The purpose of this amendment (0001) is to incorporate RFI questions with responses, Revise Statement of Work, and add attachments:

A. Incorporate the following Offeror requests for information (RFIs) with government responses:

[KTR RFI 01] “Will the Government provide the as-built drawings for Building 2A, including utility lines and service feeds, i.e., water, gas, compressed air, electrical, etc., going back to Building 2?”

[GOV RESPONSE 01] NIST has a drawing set dated March of 1989 containing drawing information for the building itself (nothing recent), however we do have updated survey drawings for the locations of buried services to B2A. In either case, NIST will make this information available for bidder reference.

[KTR RFI 02] “Will the Government confirm that the (2) ancillary structures which are plan west and plan northwest of Building 2A are to remain?”

[GOV RESPONSE 02] The bike racks, concrete pad and metal canopy structure will remain and should be protected during the demolition construction. The smaller exterior storage cage shall be removed as part of this contract.

[KTR RFI 03] “Will the Government confirm that the request for sidewalk providing access to Building 2A will be routed between Building 2A and the ancillary structure plan west of Building 2A to connect to the path at the north?”

[GOV RESPONSE 03] The sidewalk to be installed should extend from where the existing walks are on the south side of the building, northward toward where the sidewalk to the north of the building is. The new sidewalk flat work should extend the length of the location where new parking spots are to be installed/stripped, such that it is continuous over the entire distance where the new parking spaces will be constructed. Refer to site standards for sidewalk concrete requirements.

[KTR RFI 04] “We are reviewing the Building 2A demolition scope and related demolition specifications. The documents include asbestos-containing material emergency response procedures and also state that hazardous materials may be present in buildings or structures to be demolished. The specifications also reference a hazardous materials report on file for review/use. Could the Government please provide the hazardous materials/asbestos report referenced in the specifications? Please also confirm whether asbestos abatement, lead abatement, PCB removal, universal waste removal, or any other hazardous material remediation is included in the contractor’s demolition scope, or if those items will be handled separately by the Government.”

[GOV RESPONSE 04] Upon further internal coordination at NIST, we do not have an ACM report for Building 2A. As such, please provide pricing as if there is no known ACM in B2A, where ACM can be investigated and a report provided for further coordination with the awarded contractor team as part of a modification to the awarded contract at a later point in time

[KTR RFI 05] “Can wet utilities be capped at the foundation and abandoned in place?”

[GOV RESPONSE 05] Existing wet utilities shall be cut and capped per the SOW (building interior, not at foundation). It is acceptable for existing below grade piping to be abandoned in place, once capped and safed off inside of Building 2 or at source. Fill the abandoned line with self-leveling non-shrink grout or flow fill to 3psi, or approved alternative based on the submitted mix. Survey the capped end to document the location and the depth of the abandoned utility. Survey information to be provided to NIST when completed.

[KTR RFI 06] “Can the caissons be cut off 2 feet below grade?”

[GOV RESPONSE 06] All existing concrete footing walls, caissons and otherwise concrete foundations shall be removed entirely. NIST plans new building construction at the Building 2 and Building 2A locations in the future. Removal of all concrete foundation work is necessary to avoid any confusion and/or conflicts in future building construction.

PAGE 3 OF 21 1333ND26RNB1900250001

[KTR RFI 07] “Will all existing furniture, equipment, fixtures, and other contents within the demolition areas be removed by the Government prior to the start of demolition, or is the Contractor responsible for removing and disposing of these items?”

[GOV RESPONSE 07] Building occupants will have an opportunity to review and remove any of the items in the building prior the start of demolition. Any items remaining in the building at the time of project construction/ demo start will remain in the building and shall be removed and disposed of by this contractor.

[KTR RFI 08] “Please confirm whether demolition plans identifying the items and areas to be removed will be provided as part of the contract documents. Additionally, please clarify whether a grading plan will be issued. If so, please indicate where these documents can be found or when they will be made available.”

[GOV RESPONSE 08] No, NIST will not be providing demolition plans identifying items and areas to be removed and defers to the provided scope of work document. Note that any NIST drawings containing recently surveyed underground utils and original building drawings have been provided and made available by NIST in the 260604 B2A Additional Supporting Documents.zip, posted on SAM.gov.

[KTR RFI 09] “Confirm whether NIST/GC requires asphalt cores for thickness/density, or whether placement observation and supplier certification are sufficient.”

[GOV RESPONSE 09] Refer to NIST site standards for pavement mix design and placement requirements. Based on the small size and scope, cores are not required. (Appendix A, Section 1.2.3 Roads, found in the 260604 B2A Additional Supporting Documents.zip, posted on SAM.gov)

[KTR RFI 10] “Confirm final approximate quantities for foundation backfill, aggregate base, asphalt, curb/gutter, and sidewalk to establish final testing frequency.”

[GOV RESPONSE 10] NIST defers to the contractor to determine quantities for backfill at removed foundations, aggregate base, asphalt, curb/ gutter, and sidewalk. This applies to testing frequency.

[KTR RFI 11] “Confirm whether concrete for luminaire pole bases requires special inspection of reinforcing steel/anchor bolts prior to placement.”

[GOV RESPONSE 11] Special inspection not required. Installation shall follow all testing and inspection required by manufacturer’s requirements. Government must witness placement.

[KTR RFI 12] “Is there an Asbestos Building inspection report with quantities and location of ACM.”

[GOV RESPONSE 12] Please refer to [GOV Response 04]

[KTR RFI 13] “Structure foundation - are there as built drawings available? If not please provide foundation”

[GOV RESPONSE 13] Please refer to [GOV Response 08]

[KTR RFI 14] “Whether the Building 2A utilities must be chased back to their source outside the structure footprint, including into Building 2 where applicable, or if the contractor is only required to disconnect, cap, and make safe the utilities at the Building 2A structure/building limit.”

[GOV RESPONSE 14] Please refer to [GOV Response 05]

[KTR RFI 15] “Is there any hazardous materials that need to be accounted for?”

[GOV RESPONSE 15] Please refer to [GOV Response 04]

[KTR RFI 16] Are there any drawings with dimensions for the footprint of the existing structure?

PAGE 4 OF 21 1333ND26RNB1900250001

[GOV RESPONSE 16] Please refer to [GOV Response 08]

[KTR RFI 17] “Is all FF&E that remains in the building to be disposed of?”

[GOV RESPONSE 17] Please refer to [GOV Response 07]

[KTR RFI 18] “Is there a SUE report that can be shared?”

[GOV RESPONSE 18] NIST drawings containing recently surveyed underground utils and original building drawings have been provided and made available by NIST in the 260604 B2A Additional Supporting Documents .zip, posted on SAM.gov. There is no SUE report or information beyond the aforementioned surveys

[KTR RFI 19] “In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles?”

[GOV RESPONSE 19] Yes, one person can fulfill the supervision, safety, and QAQC roles.

[KTR RFI 20] “Please provide the tax responsibilities of the contractor. Is this project exempt from any of the following: Federal, State, County, City, Use or Gross Receipts taxes?”

[GOV RESPONSE 20] Please refer to solicitation document, page 3, paragraph 9.

[KTR RFI 21] “Please provide all available asbestos, lead-based paint, PCB, mercury, mold, universal waste, and hazardous materials surveys for Building 2A. Confirm whether hazardous material abatement will be performed by the Owner or shall be included in the Contractor's scope.”

[GOV RESPONSE 21] Please refer to [GOV Response 04]

[KTR RFI 22] “Are any of the utilities that are to be disconnected from this building allowed to be abandoned in place?”

[GOV RESPONSE 22] Please refer to [GOV Response 05] for wet utilities. All other utilities shall be cut and capped per the SOW requirements (building interior, not a foundation). It is acceptable for existing below grade piping to be abandoned in place, once capped and safed off inside of Building 2 or at source. Fill the abandoned line with self-leveling non-shrink grout or flow fill to 3psi, or approved alternative based on the submitted mix.

Survey the capped end to document the location and the depth of the abandoned utility.

Survey information to be provided to NIST when completed.

[KTR RFI 23] “Please identify the existing exterior lighting control system and clarify whether the new parking lot lights are to integrate into the existing campus lighting controls.”

[GOV RESPONSE 23] Existing exterior lighting control systems are to be integrated into the existing campus lighting controls. Existing lighting is run through a simple contactor.

There is no exterior lighting control system.

[KTR RFI 24] “Please identify the actual outage windows available during construction and confirm whether all utility outages will be coordinated by NIST.”

[GOV RESPONSE 24] Utility outages shall be coordinated with the COR a minimum of 1 month in advance.

[KTR RFI 25] “Please provide irrigation drawings identifying existing piping and clarify responsibility for repairing unknown damaged irrigation.”

[GOV RESPONSE 25] As with any other damage caused during or as part of the construction process, the contractor team shall be responsible for repairing damage caused by or during construction. Existing damaged irrigation remains the responsibility of NIST to repair.

Refer to the as-built information for irrigation provided in the “2024-02-02 NIST – B2 As- Builts – Civil 100%” pdf document provided in the 260604 B2A Additional Supporting Documents.zip, posted on SAM.gov

PAGE 5 OF 21 1333ND26RNB1900250001

[KTR RFI 26] “Please provide available geotechnical information for: pavement replacement, light pole foundations, demolition backfill

[GOV RESPONSE 26] Refer to the “Below Grade Condition Requirements” pdf document for more information. Refer also to the “B2A DEMO TOPO” pdf document.

[KTR RFI 27] “May suitable excavated material be reused if testing demonstrates compliance with project specifications?”

[GOV RESPONSE 27] Yes. Suitable onsite sourced excavated material may be reused if testing demonstrates compliance with project specifications. Refer also to the “Below Grade Condition Requirements” pdf document for more information.

[KTR RFI 28] “Please identify, oner-furnished equipment, laboratory equipment, furniture, hazardous equipment that will be remaining inside Building 2A at turnover.”

[GOV RESPONSE 28] Please refer to [GOV Response 07] for any existing furniture (etcetera) and please refer to [GOV Response 04] concerning any hazardous materials.

[KTR RFI 29] “Please provide existing topographic survey and utility survey used to prepare the demolition documents”.

[GOV RESPONSE 29] NIST drawings containing recently surveyed underground utils and original building drawings have been provided and made available by NIST in the 260604 B2A Additional Supporting Documents .zip, posted on SAM.gov. Refer also to the “B2A DEMO TOPO” pdf document. NIST defers to the awarded contractor team to match existing topography slopes and etcetera.

[KTR RFI 30] "Please clarify which portions of the OFPM Facility Standards apply to this demolition project.

Specifically confirm whether the Contractor is required to comply with:

Mechanical Standards Plumbing Standards Electrical Standards Laboratory Standards Space Standards or only those sections directly applicable to replacement work."

[GOV RESPONSE 30] Please refer to all NIST OFPM requirements provided in the solicitation and made available by NIST in the 260604 B2A Additional Supporting Documents .zip, posted on SAM.gov

[KTR RFI 31] "Please clarify Contractor engineering responsibilities including:

lighting foundation design demolition engineering temporary shoring utility support traffic control design"

[GOV RESPONSE 31] The contractor team is responsible for any engineering design they feel necessary to execute the demolition and reconstruction scopes identified in the SOW and any other supporting NIST/ OFPM requirements and specifications. This may include all of the scopes identified in this RFI question and at the same time, NIST defers to the contractor teams to determine which engineering responsibilities will be required to meet project requirements. Please refer also to [GOV Response 49] and “Section VI. DELIVERABLES” in the SOW related to architectural and engineering associated with this project.

[KTR RFI 32] “Please confirm that undocumented utilities, foundations, abandoned piping, or unforeseen subsurface conditions encountered during demolition will be treated under the Differing Site Conditions clause.”

[GOV RESPONSE 32] Please refer to solicitation documents, page 104, I.70 52.236-2 Differing Site conditions DEVIATION (JAN 2026) is incorporated into solicitation and future pending award document.

[KTR RFI 33] "Please identify:

PAGE 6 OF 21 1333ND26RNB1900250001

badge processing duration escort requirements laydown areas delivery hours crane restrictions parking restrictions for Contractor personnel."

[GOV RESPONSE 33] Please refer to the requirements identified in the “01A NIST Boulder General Contractor Requirements” pdf document. Any crane activities to be coordinated with NIST as needed, during construction.

[KTR RFI 34] “lease provide complete existing utility drawings showing all underground utilities, abandonment limits, utility ownership, and required demolition extents.”

[GOV RESPONSE 34] Please refer to [GOV Response 08], specifically portions of the response concerning existing drawings, existing utility surveys and demolition extents. NIST owns all onsite utilities connected to Building 2A.

[KTR RFI 35] “Will NIST provide access to the proprietary fire alarm software and programming, or should bidders include a factory-authorized fire alarm contractor?”

[GOV RESPONSE 35] Access to NIST proprietary fire alarm software and programming are limited and controlled by NIST security. Only the NIST security office, NIST FPAD office and Tech Electronics have access to these systems. The awarded contractor team shall coordinate with the aforementioned teams for access and any modifications required to the fire alarm system and electronic diagrams. Coordinate directly with Tech Electronics for fire alarm modifications included in this project.

[KTR RFI 36] “Please identify the required manufacturer, model, software compatibility, licensing requirements, programming responsibilities, and whether NIST IT will commission the system.”

[GOV RESPONSE 36] This project is for the removal of Building 2A. Outside of removal of services to Building 2A, it is unclear what system will need to be commissioned after demolition, since the project does not include installation of any new systems.

[KTR RFI 37] “For the equipment that will remain in the building that the contractor is to remove, is there anything that is hazardous or will require a special means of demolition / removal?”

[GOV RESPONSE 37] Please refer to [GOV Response 04] and [GOV Response 07].

[KTR RFI 38] “Does any of the equipment to remain need a specific or specialty decomissioning contractor?”

[GOV RESPONSE 38] Please refer to [GOV Response 04] and [GOV Response 07]. NIST will decommission/disconnect/etcetera any equipment requiring that effort.

[KTR RFI 39] “Does NIST have a recycle area or special dumpsters that any of the existing equipment needs to be removed to?”

[GOV RESPONSE 39] NIST defers to the awarded contractor team to provide for recycling and/or demolition trash removal as part of this project.

[KTR RFI 40] “Are there approved disposal facilities or hauling restrictions for demolition debris?”

[GOV RESPONSE 40] There are no NIST disposal or hauling restrictions for demolition debris

[KTR RFI 41] “The period of performance for this project is 180 days with a designated start of October 1 for scheduling. This would potentially put the backfill and paving activities during the winter months when paving is not possible. Will there be an extension to the POP allowed or should we account for this in our proposal schedule?”

[GOV RESPONSE 41] The period of performance is identified as an estimated 180 calendar days, and is identified as negotiable (SF1442, block 11, page 1). Additionally, L.12 Instruction

PAGE 7 OF 21 1333ND26RNB1900250001

to Offerors, page 189, b. Factor 2 – Schedule (b) states “…estimated date of October 1, 2026.” As this date is not a “designated” start date, but for evaluation purposes.

[KTR RFI 42] “For the reference projects, should they restricted to demolition and reclimation or is anything that has similar complexities acceptable?”

[GOV RESPONSE 42] For reference projects, any project similar in complexity is acceptable.

[KTR RFI 43] “For the security and Fire Alarm panels that are to be salvaged, where are these to be sent?”

[GOV RESPONSE 43] The awarded contractor team shall coordinate with NIST at time of removal.

[KTR RFI 44] “For the bottle storage location that is to be removed, will NIST be removing any bottles in advance of this project?”

[GOV RESPONSE 44] Confirmed. Any contents within the bottle storage location will be removed prior to demolition.

[KTR RFI 45] “Please provide a site layout plan including new parking lot spaces, new sidewalk, and new light poles.”

[GOV RESPONSE 45] NIST defers to the bidding contractor teams to provide parking space, new lighting and sidewalk layout design as part of this project. Please refer also to [GOV Response 49] and “Section VI. DELIVERABLES” in the SOW related to architectural and engineering associated with this project.

[KTR RFI 46] “We request that the proposal turn in date be extended to allow for proper inclusion of these and other RFI in proposal documentation and pricing. It is requested that a minimum of one week following the return of RFI answers be granted.”

[GOV RESPONSE 46] An extension to proposal due date will be reflected in the amendment.

[KTR RFI 47] “Hazardous Materials Survey & Abatement Scope: Section 024116, 1.8.E states that hazardous materials will be removed by the Owner before the start of the Work, but 1.8.F notes that hazardous materials are present and a report is "on file for review and use." Could the government please provide this hazardous materials report? Additionally, please confirm that the contractor does not need to carry an allowance for abatement in the base bid.”

[GOV RESPONSE 47] Please refer to [GOV Response 04].

[KTR RFI 48] “Limits of Construction (LOC): Task 2 of the Statement of Work notes replacing ‘pavement around Building 2A’ and connecting a sidewalk to the ‘path North of building 2a’.

Could the government provide a site plan with explicit, hardlined Limits of Disturbance/Construction to ensure accurate paving and concrete takeoffs?”

[GOV RESPONSE 48] Please refer to [GOV Response 45]. NIST defers to the awarded contractor team to determine the limits of disturbance/construction such that the NIST campus and areas around Building 2A have as limited disturbance as possible. Refer also to [GOV Response 3] concerning defined limits/areas in which the new sidewalk shall be installed.

[KTR RFI 49] “Engineering Deliverables: Section VI of the SOW states, ‘The Contractor shall provide all architectural and engineering associated with the project, including stamped construction drawings and specifications’. Is this project intended to be a full Design- Build delivery requiring a complete PE-stamped drawing package for the demolition and civil restoration, or are stamped drawings only required for specific items, such as the light pole bases mentioned in Task 2?”

[GOV RESPONSE 49] Contractors should utilize engineers as required to perform the work only on required specific scopes of work. A full design package is not necessary. NIST review of this information will occur during any applicable construction phase submittals.

B. Incorporate revisions to Statement of Work. All revisions are indicated with red text in the attached revised statement of work.

a. Task 1 – Demolish Building 2A (Base Scope – CLIN 0001) revisions:

PAGE 8 OF 21 1333ND26RNB1900250001

i. ADDED, Item #1, “…any remaining existing interior furnishings,…”

ii. ADDED, Item #2, g, “…Access to NIST’s fire alarm programming is limited for security purposes and all fire alarm programming modifications shall be coordinated with Tech Electronics and NIST FPAD as necessary to remove the B2A graphics from NIST’s fire alarm programming.”

iii. ADDED, Item #3, k, “Site Layout Concept Plan – The contractor team shall provide a plan view site layout concept plan, where-in the initial concept draft plan shall be provided at the bid proposal phase for the Government’s review. The plan will there-in be further revised as necessary with the awarded contractor team, after project award. The Site Layout Concept Plan shall graphically show all of, but not limited to the following: a. Construction perimeter fencing., b.

Dumpster location(s)., c. Portable restroom location(s)., d. Material storage locations (for both refuse and any new materials (e.g. – Infill soil) during construction phases)., e. Heavy equipment storage locations., f. Emergency responder (fire/police/ambulance) drive/ access isles through site (including location of perimeter fence access gates at drive isles)”

iv. ADDED, Attachments.zip, NOT INCLUDED INSIDE ZIP FILE BUT SEPERATELY, 06 Below Grade Condition Requirements.pdf, 07 B2A DEMO TOPO.pdf

C. Requests for Information (RFI) due date is extended to July 22, 2026, no later than 3:00 PM

MT.

D. The Offer Due Date, Block 13 of the Standard Form (SF) 1442, is changed from July 22, 2026, to August 12, 2026, no later than 3:00 PM MT.

E. No other changes occur as a result of this amendment.

Table of Contents

SECTION C DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1 Statement of Work

PAGE 9 OF 21 1333ND26RNB1900250001

SECTION C

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1 Statement of Work

PAGE 10 OF 21 1333ND26RNB1900250001

STATEMENT OF WORK

Construction Services for Building 2A Demolition Project (REV 1)

I. BACKGROUND INFORMATION

The Department of Commerce (DOC), National Institute of Standards and Technology (NIST) campus is located in Boulder, Colorado and is a research & development facility. DOC also consists of National Oceanic Atmospheric Administration (NOAA) and National Telecommunications and Information Administration (NTIA) agencies on the NIST campus. The Office of Facilities and Property Management (OFPM) at NIST is responsible for maintaining and renovating spaces which consist of laboratories, office space and facilities maintenance areas, except the David Skaggs Research Center.

II. PURPOSE

The objective of this acquisition is to disconnect Building 2A (B2A) from all utility services supplied to the building, complete demolition/ removal of B2A and remaining contents, return subgrade to elevation of adjacent soils, installation of new concrete sidewalk, new asphalt flatwork at vehicular surfaces, new parking striping on asphalt surfaces and new parking lot luminaires for this section of the parking lot.

III. PLACE OF PERFORMANCE

Work will be performed at the US Department of Commerce (DOC) Boulder Laboratories campus at 325 Broadway, Boulder, CO in and around B2A.

IV. SPECIFIC REQUIREMENTS

1. The Contractor shall coordinate with the Government Contracting Officer’s Representative (COR) all activities required throughout the duration of this task order.

The Contractor shall communicate with the COR and the Contracting Officer (CO) on all matters pertaining to the task order.

2. Contractor will provide and install temporary chain link fencing and safety barriers, as required to secure the site.

Task 1 – Demolish Building 2A (Base Scope – CLIN 0001)

1. The contractor will demolish Building 2A including the superstructure, roof, mechanical and electrical equipment, foundation/footers, building utility feeds, any remaining existing interior furnishings, associated site improvements within the building footprint and the pavement around Building 2A. Dispose of the demolition debris to an off-site facility.

2. Demolish all utilities, abandon piping, and conduits within the demolition footprint. Utility demolition includes removing utilities to:

a. Domestic water – demolish back to the supply from inside of Building 2

b. Sanitary sewer – demolish back to the clean out. Modify as needed to seal and cap ¼” below grade

c. Gas – demolish back to the where gas line tees off from the Building 2 service.

Cut and cap.

d. Compressed Air – demolish back to service in Building 2 service.

PAGE 11 OF 21 1333ND26RNB1900250001

e. Fire Extinguisher’s – turned over to NIST.

f. Electrical – B2A is fed from existing electrical distribution board “PDP, which is located in B2’s mechanical room (B2-0105). Remove conductors in their entirety along with any associated disconnect switches at B2A and in B2-0105. Revise distribution board directory and label circuit break breaker as “SPARE”. Existing underground conduit shall remain and be used for the raceway to serve the new parking lot luminaires. Disconnecting the B2A conductors in “PDP” shall occur during one of the planned site outages in May and September.

g. Fire Alarm – B2A fire alarm devices are fed from the existing fire alarm control panel in B2. The fire alarm cabling entry point and power supply are located in Janitor’s Closet (B2A-115). The power supply shall be handed over to NIST.

Remove all devices in B2A and fire alarm cabling in their entirety back to B2’s fire alarm control panel. If the B2A fire alarm cabling is in a dedicated conduit within B2, the conduit shall be removed as well. Existing underground conduit(s) shall be removed but coordinated with NIST to the extent of their demolition. Provide as-built site plan noting location of abandoned conduit(s). Contractor will also be responsible for updating and removing B2A from NIST’s fire alarm programming.

Access to NIST’s fire alarm programming is limited for security purposes and all fire alarm programming modifications shall be coordinated with Tech Electronics and NIST FPAD as necessary to remove the B2A graphics from NIST’s fire alarm programming.

h. Telecomm – B2A is fed from the existing IT equipment in B2. The existing networking fiber for B2A originates in IT room B2-1062 and passes through IT room B2-1103. The telephone and fiber cabling point is located in Janitor’s Closet (B2A-115). Remove the fiber and telephone cables in their entirety back to B2. Existing underground conduit(s) shall be removed as well but coordinated with NIST to the extent of their demolition. Provide as-built site plan noting location of abandoned conduit(s). NIST-OISM will be responsible for removing networking equipment prior to the building’s demolition.

i. Security – B2A security control panel, located near the west exit, is connected to the existing network IT equipment in B2-0105. All existing security cabling within B2A and back to B2 shall be removed. NIST ESO will remove the keypads, control panel, and all door’s core cylinders prior to the building’s demolition.

Existing security camera shall be removed and returned to NIST. Existing underground conduit that serves the keypad at the gas storage enclosure shall be removed in its entirety.

j. Building Controls - B2A is fed from the existing B2, remove all controls within building and communication trunk back to B2 JCI controls engine.

k. Site Layout Concept Plan – The contractor team shall provide a plan view site layout concept plan, where-in the initial concept draft plan shall be provided at the bid proposal phase for the Government’s review. The plan will there-in be further revised as necessary with the awarded contractor team, after project

PAGE 12 OF 21 1333ND26RNB1900250001

award. The Site Layout Concept Plan shall graphically show all of, but not limited to the following:

a. Construction perimeter fencing.

b. Dumpster location(s).

c. Portable restroom location(s).

d. Material storage locations (for both refuse and any new materials (e.g. –

Infill soil) during construction phases).

e. Heavy equipment storage locations.

f. Emergency responder (fire/police/ambulance) drive/ access isles through site (including location of perimeter fence access gates at drive isles)

Task 2 – Restore Building 2A site (Base Scope – CLIN 0002)

1. Backfill the foundation using approved CDOT Class 1 backfill compacted in 6-inch lifts to 95% maximum dry density on standard proctor test

2. Prior to asphalt operations, fine grade the subgrade to match the surrounding pavement.

Proof roll subgrade with minimum 20 Ton truck to verify that the subgrade is stable. The proof roll must be witnessed by a NIST representative.

3. Install 6” minimum CDOT Class 2 aggregate base compacted to 95% maximum dry density on standard proctor test.

4. Place asphalt, curb and gutter per NIST site standards. Asphalt replacement should extend 12” beyond the new aggregate base. Seal asphalt joints with hot applied single component joint sailing compound.

5. Where sidewalk previously provided access to building 2a connect sidewalk to the path

North of building 2a.

6. Install (2) parking lot luminaires, poles, and concrete bases.

a. New luminaire head shall match site standard fixture and be equipped with an integral photocell.

b. New pole shall match existing type/style, color, and height.

c. New circuit for the parking lot luminaires shall originate from B2 utilizing the underground conduit that served B2A’s electrical service. The conduit goes back to B2 mechanical room (B2-0105). Intercept the conduit in the mechanical room and install a new junction box. Conduit shall then be installed from new junction box to existing panelboard “PNL-0105-08”/”Welder Panel”. Provide new 20A1P circuit breaker in this panelboard to serve the new parking lot luminaires. New circuit breaker shall match existing panelboard manufacturer and AIC rating.

d. Typically, this circuit would be (2#12+#12G)3/4” C. Contractor to perform voltage drop calculations and provide the proper size circuit and conduit.

e. Contractor shall trench and backfill for the new circuit in existing landscaped areas. Repair landscaping to match pre-construction conditions.

f. Rework landscape irrigation as necessary.

PAGE 13 OF 21 1333ND26RNB1900250001

g. Provide pole base detail signed by a licensed Colorado Structural Professional Engineer.

h. Provide photometrics for NIST review/approval.

i. Refer to NIST site standard specifications for additional information and requirements.

7. Install new exterior security camera on the east side of B2 to monitor the new parking spaces. Coordinate exact location with NIST prior to rough-in. New conduit and cabling shall be routed back to existing security networking equipment located in B2-0105. New camera, conduit, cabling, and testing shall meet NIST Site Standards.

8. Stripe new parking lot spaces.

Safety on the NIST Campus NIST is committed to maintaining a work environment that safeguards the public and the environment, as well as personnel and property.

If the award requires construction, demolition, excavation, renovation, or other work for which the contractor directs and oversees contractor personnel (including subcontractors) at NIST-owned and operated sites, the contractor shall:

Provide a detailed, site-specific Safety Plan to the contracting officer within 7 days after award that describes how the contractor will maintain a safe work environment and comply with applicable Occupational Safety and Health Administration (OSHA) standards, as well as with applicable state and local laws, standards, and codes.

The Safety Plan shall specify how the company’s policies and practices will comply with each of the applicable standards, laws, and codes.

The contracting officer will provide written comments regarding the plan to the contractor within seven (7) days of receipt and will require the contractor to submit a revised safety plan within seven (7) days after that to the contracting officer for their review. This cycle may be repeated, if necessary, until the contracting officer determines the safety plan to be acceptable.

Reference:

See NIST’s Contractor Safety Program for required elements of Contractor Safety Plans.

Safety-Related Equipment The Contractor shall:

Provide all safety-related equipment required to perform the work under this award, including personal protective equipment (PPE) and other equipment that is required or appropriate to protect contractor personnel and other personnel on the NIST campus.

PAGE 14 OF 21 1333ND26RNB1900250001

Contractor-provided personal protective equipment shall include, at a minimum, hard hats, safety shoes, safety glasses (prescription or standard), respiratory protection (powered air purifying respirator or full-face mask respirator), high visibility clothing and gloves that meet applicable OSHA standards for PPE.

Training The Contractor shall:

Provide safety-related training required by applicable OSHA, state and local regulations or standards to affected contractor personnel (including subcontractor personnel) that perform work under this award. Such training may include, for example, training for proper use of PPE, respirator use, fall protection, crane operation, forklift operation;

electrical safety, or other safety-related topics.

Maintain records of safety training provided to contractor personnel (including subcontractor personnel) that perform work on this award. The contractor shall make those records available to the contracting officer, contracting officer’s representative for the award, or other authorized personnel within 7 days of receipt of their written request, and annually thereafter or upon request.

Require contractor personnel (including subcontractors) to attend required NIST-specific health or safety training that is required by the award.

Health Hazard Assessments and Medical Evaluations The Contractor shall:

Provide required health hazard exposure assessments, medical evaluations and screenings, and exposure monitoring required by applicable OSHA requirements.

Ensure PII information is protected.

Homeland Security Presidential Directive (HSPD)-12 The Contractor (and/or any subcontractor) and its employees who require physical access to NIST facilities or logical access to NIST IT networks or systems must comply with Homeland Security Presidential Directive (HSPD)-12, Policy for a Common Identification Standard for Federal Employees and Contractors; OMB M-05-24; OMB M- 19-17; FIPS 201, Personal Identity Verification (PIV) of Federal Employees and Contractors; NIST HSPD-12 policy; and Executive Order 13467, Part 1 §1.2.

5. Roster

The Contractor (and/or any subcontractor) must submit a roster by name, position, e-mail address, phone number and responsibility, of all staff working under this acquisition where the Contractor will develop, have the ability to access, or host and/or maintain a government information system(s).

PAGE 15 OF 21 1333ND26RNB1900250001

The roster must be submitted to the COR and/or CO within 14 days of the effective date of this contract. Any revisions to the roster as a result of staffing changes must be submitted within 14 days of the change. The COR will notify the Contractor of the appropriate level of investigation required for each staff member. If the employee is filling a new position, the Contractor must provide a position description, and the Government will determine the appropriate suitability level.

Position Sensitivity Designations Requirement All Contractor (and/or any subcontractor) employees must obtain a background investigation commensurate with their position sensitivity designation that complies with Parts 1400 and 731 of Title 5, Code of Federal Regulations (CFR).

V. GENERAL REQUIREMENTS

Include all requirements that are not specific tasks but are applicable to the overall contract and the work that will be performed. For example, IT Security, Government Property, Public Affairs Clearance, OMB clearance, printing, data rights, etc.

REQUIREMENTS FOR CONTRACTOR PERSONNEL

Identify all qualifications that the Contractor and/or their personnel working on this contract must possess.

Safety: The Contractor employee must be responsible for knowing and complying with all installation safety prevention regulations. Such regulations include, but are not limited to, general safety, fire prevention, and waste disposal.

Security: NIST is a restricted campus. An identification badge is required for access for entry into buildings and is shown to the armed Security Police when entering the campus.

Identification Badges: Contractor employees must comply with NIST identification and access requirements. Each Contractor employee must wear a visible identification badge provided by the NIST Security Office.

VI. DELIVERABLES

1. Quality Control Plans and Site-Specific Safety Plans shall be submitted no later than 30 days after award.

2. Notice to Proceed will not be issued until the contractor’s Site-Specific Safety Plan has been accepted.

3. If not included in the proposal, a schedule of values shall be submitted no later than 30 days after award.

Standards of Acceptance: The NIST POC or COR shall review all the above deliverables and respond with an acceptance or an email with request for revision to the Contractor Point of Contact (POC) within 15 business days of receipt of a deliverable.

• The Contractor shall provide a submittal log and submittals in formats approved by the

COR.

• Contractor is not to include any contact information in the specifications or drawings.

PAGE 16 OF 21 1333ND26RNB1900250001

• The Contractor shall provide all architectural and engineering associated with the project, including stamped construction drawings and specifications.

• Detailed as-builts in PDF format shall be provided.

• The Contractor shall review, and field verify all existing facility documentation provided by NIST.

VII. PAYMENT SCHEDULE

The Contractor will be paid, in accordance with the payments clause in the contract and as otherwise noted in this document, upon receipt of a proper invoice. Refer to FAR Clause 52.232-5 Payments under Fixed-Price Construction Contracts.

VIII. SITE MOBILIZATION

1. NIST shall provide the Contractor with the area for construction and staging activities shown in the attached staging drawing. Additional storage areas on the NIST campus may be available to the Contractor if approved by NIST. Refer to NIST Boulder General Contractor Requirements. Fire department access into and through the B81 parking lot, including access to the B81 FDC must be maintained during the project. Provide the described site plan, with FD access drives highlighted, for review by FPAD.

IX. SUBMITTALS

Contractor shall provide the following submittals to the COR for approval. NIST shall have up to 14 calendar days to review and return the submittal to the contractor.

Submittals as required in the contract documents from the following divisions:

Division 00 - Procurement and Contracting Requirements

Project CPM Schedule Testing agency certifications Construction daily reports Project as-builts in .pdf format.

Division 01 - General Requirements Refer to Attachment 01 for General Requirements Submittals

Division 02 - Existing Conditions Pre-construction photographs showing the existing conditions of the area around the site Submit proposed protection measures, including drawings, that indicates the measures proposed for protecting individuals and property. Indicate proposed locations and construction of barriers

Division 03 – Concrete Concrete demolition procedures Product data Mill certs

Division 04 - Masonry (NOT USED) Division 05 - Metals (NOT USED) Division 06 - Wood, Plastics, Composites (NOT USED) Division 07 - Thermal and Moisture Protection (NOT USED) Division 08 - Openings (NOT USED) Division 09 - Finishes (NOT USED) Division 10 - Specialties (NOT USED) Division 11 - Equipment (NOT USED)

PAGE 17 OF 21 1333ND26RNB1900250001

Division 12 - Furnishings (NOT USED) Division 13 - Special Construction (NOT USED) Division 14 - Conveying Equipment (NOT USED) Division 21 - Fire Suppression (NOT USED) Division 22 - Plumbing ( NOT USED) Division 23 - Heating, Ventilating, and Air Conditioning (HVAC) (NOT USED) Division 25 - Integrated Automation (NOT USED) Division 26 - Electrical Division 27 – Communications (NOT USED) Division 28 - Electronic Safety and Security Division 31 - Earthwork

Pre-excavation conference meeting minutes. Meeting at project site to include, at minimum, general contractor, excavation contractor, COR and NIST OFPM safety representative. The excavation permit will be issued after the meeting. Refer to Attachment 01 General Requirements for excavation permit requirements.

Material test reports for all imported fills including:

• Classification according to ASTM D2487 for each on-site or borrow soil material proposed for fill and backfill.

• Laboratory compaction curve according to ASTM D698 for each on-site or borrow soil proposed for backfill.

Water sample data, if dewatering is required

Division 32 - Exterior Improvements Certificate of grass seed compliant with NIST standard seed mix requirements Certification of each seed mixture for turfgrass sod compliant with NIST standard seed mix requirements Product certificates Asphalt mix and material certifications

Division 33 – Utilities Test reports: Submit all field quality control test reports

• Contractor shall provide submittals through a NIST approved, secure electronic site accessible by NIST.

X. SECURITY REQUIREMENTS

1. No Government-furnished tools, equipment, or devices shall be removed from the NIST site.

2. The contractor (including subcontractors) shall be responsible for properly protecting all information used, gathered, or developed as a result of work under this contract.

3. The data shall not be used for any other purpose other than that specified in the contract. Any information made available to the contractor by the Government shall be used only for the purpose of carrying out the requirements of this contract.

4. If the contractor (including subcontractors) anticipates using external information system services provided by third-party entities, the contractor shall ensure that external information system meets the security standards as described in NIST Special Publication 800-53 and shall be maintained throughout the duration of the contract.

5. At the completion of the contract, all Government data shall be returned to NIST, or if return is not feasible, destroy and do not retain any copies of Government data such as backup copies created at the contractor (including subcontractors) site (and certify in writing to NIST that such return or destruction has been completed).

PAGE 18 OF 21 1333ND26RNB1900250001

XI. Product and Execution Requirements

Refer to NIST site standards attachment.

Quality Assurance

1. Comply with all applicable requirements from federal, local, and state regulations and ordinances concerning shoring, bracing, or sloping of excavations and safety of workers.

2. All inspections and testing, including special inspections, required to complete the scope of work will be performed by an independent testing and inspection agency employed by the contractor and approved by the contracting officer as having the competence necessary to perform the work.

PAGE 19 OF 21 1333ND26RNB1900250001

Attachments: (All attachments contained within Attachments.zip, and 260604 B2A Additional Supporting Documents.zip) If you do not have the attachment files please contact the points of contact on documents.

Attachments.zip

• 01 General Contractor Requirements Boulder.pdf (inline in solicitation and in zip file)

• 02 Safety Plan Checklist.xlxs

• 03 NIST Laboratories Physical Access Control Standards.pdf

• 04 Building 2A Map.pdf

• 05 PPQ Performance.pdf

NOT INCLUDED INSIDE ZIP FILE BUT SEPERATELY

• 06 Below Grade Condition Requirements.pdf

• 07 B2A DEMO TOPO.pdf

260604 B2A Additional Supporting Documents.zip

• OFPM Site Standards o 1- OFPM Lab and Office Material Standards 8-30-2024.pdf o 2- Appendix A Boulder 8-30-2024.pdf o 7- Appendix C Abbr 8-30-2024.pdf o 8- Appendix D Perf Tables 8-30-2024.pdf o 9- Appendix E OFPM Mech Site Standards 8-30-2024.pdf o 10- APP E1 Boulder Plumbing Fixtures 6-21-2024.pdf

• 000103-COVER PG & TOC (REV 1).pdf

• 2024-02-02 NIST - B2 As-Builts - Civil 100%.pdf

• 2024-02-02 NIST - B2 As-Builts - MEP 100%.pdf

• 013233-Photographic Documentation.pdf

• 015000-Temporary Facilities and Controls.pdf

• 011000.01.pdf

• 011000.pdf

• 011300.pdf

• 013100.pdf

• 013200.pdf

• 013300.pdf

• 013400.pdf

• 014000.pdf

• 014200.pdf

• 015100.pdf

• 017300.pdf

• 017400.pdf

• 017700.pdf

• 024119.pdf

• 024116-Structure Demolition.pdf

• 311000-Site Clearing.pdf

PAGE 20 OF 21 1333ND26RNB1900250001

• 312000-Earth Moving.pdf

• B2 2E2419 One-Line.pdf

• B2A Demo Elec Specs.pdf

• B2A Existing Utility Plan and Testholes.pdf

• NIST Elec Site Standards.pdf

• RAB Exterior Fixture.pdf

PAGE 21 OF 21 1333ND26RNB1900250001

1.2

C:\PERFORM\FORMS\S30.FRP

Forms Management

C:PERFORMFORMSS30.FRP

Acrobat PDFWriter 2.01 for Windows D:19971010095222 D:19990614133004 Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.