Amendment 0001.docx
DOCX document 190 KB Posted
- Attached to
- POLAR Neutron Detectors Federal contract opportunity
- Solicitation number
- 1333ND26QNB610462
About this file
This is an amendment to a Request for Quote (RFQ) for POLAR Neutron Detectors issued by the Department of Commerce National Institute of Standards and Technology. Amendment 0001, issued on August 14, 2026, extends the lead time requirement from four months after receipt of order to fifty-two weeks after receipt of order. The amendment responds to a contractor question regarding the feasibility of extending the delivery timeline. The RFQ number is 1333ND26QNB610462, and the response deadline is August 17, 2026.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0003.docx | DOCX document | |
| Amendment 0002.docx | DOCX document | |
| CSS.docx | DOCX document | |
| SOW_Final.docx | DOCX document | |
| Provisions_Clauses.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 RFQ Number: 1333ND26QNB610462 Requirement: POLAR Neutron Detectors Response Deadline: 08/17/26 Amendment Date: 08/14/26
The purpose of Amendment 0001 is to provide the Government’s response to a submitted question.
QUESTION 1: Can the lead time be extended to fifty-two (52) weeks?
RESPONSE 1: Yes, the lead time can be extended to fifty-two (52) weeks. The lead time is hereby extended from four (4) months after receipt of order to fifty-two (52) weeks after receipt of order.