About this file

This document provides an amendment to a solicitation for fire protection systems inspection, testing, maintenance, repair and impairment coordinator services at multiple facilities of the National Institute of Standards and Technology. The amendment includes supplemental questions and answers and revises an appendix detailing the automatic sprinkler systems and common components at each covered building. Appendix B summarizes the sprinkler riser locations, areas protected, and system types for various NIST buildings, along with notes on fire pumps, standpipes, backflow preventers and device counts. It also provides an underground water supply map showing hydrant locations.

View the file

Other files

File Type Posted
Amendment 0002.pdf PDF
Amendment 0002 Revised Appendices.pdf PDF
Amendment 0001 SITE MAP.pdf PDF
Amendment 0001_.pdf PDF
1333ND20QNB150185.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

1333ND20QNB1501850003

000014

The purpose of this amendment is to incorporate Supplemental Questions and Answers and revise Appendix B.

Please see the attached responses to questions that were submitted.

NATIONAL INST OF STDS AND TECHNOLOGY

325 BROADWAY

BOULDER CO 80305

See Block 6

NB153000-20-01119

1333ND20QNB150185

1 4

06/01/2020

04/17/2020

Q13. Page 13; Section III.A.2.f. – Common Components and Valves

• Will NIST provide a device count for each Water-Based Fire Protection Systems, i.e. sectionals;

including waterflow alarm device counts, supervisory valve device counts, hose cabinet counts, fire pump counts, etc.?

• Will NIST also provide a count of hydrants and location of hydrants?

A13. Appendix B, Water-Based Fire Protection Systems, has been modified to summarize information regarding Common Components and Valves of the automatic sprinkler systems for each building that is provided with automatic sprinkler protection. All new information is shown in Red. New information is formatted by fire alarm panel Node. Please reference the water flow and valve tamper counts provided by fire alarm Node in Appendix A (fire alarm).

A site map of underground water supply is provided that identifies hydrant count and locations along with a hydrant list.

NIST Boulder Automatic Sprinkler Systems Water-Based Fire Protection Systems Appendix B

Building # Automatic Sprinkler System Riser

Location Area Protected System Type Fire Pump

(Y/N) Standpipe

System (Y/N)

Backflow Preventer

(Y/N)

Building 1 Room 1049 - Mechanical Room Fitness Center, Connector to B81, and Spine Standpipe - All Levels Wet N Y Y

Building 1 Wing 1 Wing 1 Room 2142 Wing 1 (Interconnected to Room 1049 System) Wet N N Y Building 1 Wing 1 Wing 1 Janitor Closet 2100 Room 2106 and 2108 Single Interlock Pre-Action N N N Building 1 Wing 2 Wing 2 West Entrance Vestibule Room 2226 Single Interlock Pre-Action N N N Building 1 Wing 3 Wing 3 Service Corridor North Wing 3 - Main Entry Wet N N Y Building 1 Wing 3 Wing 3 Service Corridor North Wing 3 - Level 3 Wet N N N Building 1 Wing 3 Wing 3 Service Corridor North Wing 3 - Clerestory Wet N N N Building 1 Wing 3 Wing 3 Service Corridor North Wing 3 - Dock Canopy Dry N N N Building 1 Wing 6 Wing 6 - Mechanical Room 3671 Wing 6 - Main Entry Wet N N Y Building 1 Wing 6 Wing 6 - Mechanical Room 3671 Wing 6 - Level 3 Wet N N N Building 1 Wing 6 Wing 6 - Mechanical Room 3671 Wing 6 - Level 4 Wet N N N Building 1 Wing 6 Wing 6 - Mechanical Room 4605 Wing 6 - Level 4 Anechoic Chamber 4607 Single Interlock Pre-Action N N N Building 1 Wing 6 Wing 6 - Mechanical Room 3671 Wing 6 - Clerestory Level - Dock Canopy Dry N N N Building 1 Wing 6 Wing 6 - Mechanical Room 3671 Wing 6 - Clerestory Level Wet N N N Building 1 Annex D Annex D North Closet Near Entry Annex D Wet N N N

Builidng 2 Building 2 - Mechanical Room 0105

Building 2 - Basement, Various Level 1 and 2 Areas, and Mechancial Equipment Tunnel (Main Entry) Wet N N Y

Building 2 Buidling 2 - Mech Room 0105 Building 2 Dock Dry N N N

Builiding 3 Main Entry - Mechanical Room

Entire Building including Standpipe - All Levels North and South Stairwells Wet N Y Y

Building 3 Mechanical Room 1126 Level 1 Wet N N N

Building 3 Mechanical Room 1126 Standpipes (North and South) and Levels above Level 1 Wet N N N

Building 3 South Stair (Stair 02) Level 2 Wet N N N

Building 3 South Stair (Stair 02) Level 2 - Public Safety Equipment - Room 2112 Pre-Action N N N Building 3 South Stair (Stair 02) Level 3 Wet N N N

Common Components and Valves Summary Building 1 (B1) has five (5) automatic sprinkler water entry systems identified by fire alarm panel Node as follows:

Node 1: Water Entry in Spine Basement Room 1049 interconnected to water entry in Wing 1 Room 2142. Includes standpipe system throughout B1 Spine all levels (1-5). Includes Spine Fitness Center Room 1006 automatic sprinklers.

Node 2: Water Entry in Wing 1 Room 2142 interconnected to water entry in Basement Room 1049. Includes sprinklers throughout Wing 1 including pre-action automatic sprinklers for Lab 2106 and 2108.

Node 2 includes pre-action sprinklers for Lab 2226 in Wing 2 fed off of standpipe system. Also includes separate water entry for Annex D wet sprinklers.

Node 3: No water entry.

Node 4: No water entry. Includes automatic sprinklers for very west end of Level 4 Spine and B81 connector wet sprinklers fed off of stanpipe system. Also includes automatic sprinklers for Spine Level 5 Penthouse fed off of standpipe system.

Node 13: Dedicated Wing 3 water entry. Automatic sprinklers for all systems feeding Wing 3.

Node 16: Dedicated Wing 6 water entry. Automatic sprinklers for all systems feeding Wing 6.

Wing 4 and Wing 5 are not provided with automatic sprinkler protection.

The Spine of B1 is without automatic sprinkler protection except in the Fitness Center (Room 1006), a very small area at the west end of Level 4 Corridor to include B81 connector, and the Level 5 Penthouse - All fed from the sandpipe system.

Building 1 has standpipe hose connections throughout at each exit stairwell (count estimate is 29 hose connection stations).

Building 2 (B2) has one automatic sprinkler water entry monitored by Node 5.

Standpipe hose connections are located at exit paths. Hose connection count estimate is 7 hose connection stations.

Building 3 (B3) has one automatic sprinkler water entry monitored by Node 33.

Standpipe hose connections are located in the north and south exit stairwells. Hose conection count estimate is 8 hose connection stations.

NIST Boulder Automatic Sprinkler Systems Water-Based Fire Protection Systems Appendix B

Building # Automatic Sprinkler System Riser

Location Area Protected System Type Fire Pump

(Y/N) Standpipe

System (Y/N)

Backflow Preventer

(Y/N) Common Components and Valves Summary

Building 3 Sout Stair (Stair 02) Roof Stair Penthouse - Roof Manifold Wet N Y N

Building 4 Building 4 Room 1310 Building 4 Above and Below Lay-in Ceiling and in Warehouse Dry N N Y

Building 22 Building 22 - Mechanical Room 1122 Building 22 Wet N N Y

Building 23 Building 23 Bathroom Building 23 Wet N N Y

Building 24 Building 24 Basement North - Room 0300 Building 24 First Level Lab 1300 Single Interlock Pre-Action N N N

Building 24 Building 24 Lab 1500 NW Corner Building 24 First Level Lab 1500 Single Interlock Pre-Action N N N

Building 24 Building 24 Basement North - Room 0300 Building 24 Basement Wet N Y Y

Building 24 Building 24 Mechanical Room 0114 Building 24 Basement, First Level, Second Level Wet N Y Y

Building 26 Building 26 Room 123 Closet (SW Corner of B26) Building 26 Wet N N Y

Building 42 (CUP) Building 42 Room 106 B42 All Levels Wet N y Y

Building 42 (CUP) Tunnel Building 42 Outside Room 106 Tunnel Wet N N N Building 42 Tunnel West Doghouse

Building 42 Tunnel @ West Doghouse West Tunnel Doghouse Antifreeze N N Y

Building 42 Tunnel Central Doghouse

Building 42 Tunnel @ Central Doghouse Central Tunnel Doghouse Antifreeze N N Y

Building 42 Tunnel East Doghouse

Building 42 Tunnel @ East Doghouse East Tunnel Doghouse Antifreeze N N Y

Building 81 Main Riser Entry - Mechanical Room 1K112 Entire Building - Main Entry w/ Fire Pump Wet Y N Y

Building 81 West Stair 7 - Level 1 Laboratory North - Level 1 Wet Y N N Building 81 West Stair 7 - Level 1 Laboratory South - Level 1 Wet Y N N Building 81 West Stair 7 - Level 1 Cleanroom Level 1 Wet Y N N Building 81 West Stair 7 - Level 2 Interstitial Level 2 North Wet Y N N Building 81 West Stair 7 - Level 2 Interstitial Level 2 South Wet Y N N Building 81 West Stair 7 - Level 3 Mechanical Level 3 - North Wet Y N N Building 81 West Stair - Level 3 Mechancial Level 3 - South Wet Y N N Building 81 Building 81 Room 2K101 Building 81 Dock Antifreeze Y N N

Building 23 (B23) has one automatic sprinkler water entry monitored by Node 23 protecting all of B23. No hose connecitons in

Building 24 (B24) has two interconnected automatic sprinkler water entries monitored by Node 24 protecting the two pre-action systems for Lab 1300 and Lab 1500.

Building 24 has standpipe hose connections for each level located at exit stairwells. Hose connection count is estimated at 11 hose connection stations.

Buildign 26 (B26) has one automatic sprinkler water entry monitored by Node 26 protecting all of B26.

Building 42 (B42) has one automatic sprinkler water entry monitored by Node 45 proteting all of B42 including the Tunnel.

Building 42 has standpipe hose connections for each level located in exit paths.

Hose connections are provided one each level, with two (2) on Level 2, three (3) on Level 1, two (2) in the Basement, and three (3) in the B42 Tunnel. A total of (ten) 10 standpipe hose connection stations are provided in B42.

Building 81 (B81) has one automatic sprinkler water entry that includes the only fire pump on the NIST site, monitored by Node 60.

Building 81 has no hose connection stations.

Building 4 (B4) has one automatic sprinkler water entry monitored by Node 30 protecting all of B4.

There are no hose connections in B4.

Building 22 (B22) has one automatic sprinkler water entry monitored by Node 22 protecting all of B22.

Hose connections are located at exit paths and estimate is 2.

FY00

Gas Dock added, CW line routed outside dock footprint