This document contains an amendment and solicitation related to a federal contract opportunity. The amendment changes the contract line item structure to include CLIN 0001 for an HR1 Feed Upgrade and warranty and CLIN 0002 for an HR2 Feed Upgrade, each with a 36 month period of performance. It also modifies the payment milestones and schedules to allow for non-simultaneous completion. The statement of work and period of performance are updated.
The solicitation seeks proposals for upgrades to the HR1 and HR2 antenna feeds to support the DSCOVR and GOES-R missions. Offerors should respond by July 7th, 2020 and proposals will be evaluated based on technical approach, past performance, and price. The work includes a preliminary design review, detailed design review, installation and test readiness review, in-plant acceptance test, and on-site acceptance test. Payments will be made at 10%, 10%, 20%, 20%, and 40% upon completion of each milestone. The National Oceanic and Atmospheric Administration is seeking these antenna feed upgrades to support their weather monitoring missions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - SOW - Amendment 0001 8-26-20.docx | DOCX document | |
| Request for Proposal Amendment 0001 8-26-20.pdf | ||
| HR1 Noise Density Test 07.20.2020.docx | DOCX document | |
| Questions and Answers 7-20-20.pdf | ||
| Attachment 3 - PPQ.docx | DOCX document | |
| Request for Proposal 6-22-20.pdf | ||
| Attachment 2 - QASP.docx | DOCX document | |
| Attachment 1 - SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 Changes
1. Contract Line Item Structure has been changed to the following
a. CLIN 0001 - HR1 Feed Upgrade and Warranty (36 months)
b. CLIN 0002 - HR 2 Feed Upgrade (36 months)
2. RFP “Payment Schedule” has been changed to the following:
CLIN 0001 - HR1 Feed Upgrade
Milestone % Payment Price (completed by Offeror)
Kickoff Meeting 10%
Preliminary Design Review 15%
Detailed Design Review 15%
Installation and Test Readiness Review 20%
In-plant Acceptance Test 20%
On-site Acceptance Test 20%
CLIN 0002 - HR2 Feed Upgrade
Milestone % Payment Price (completed by Offeror)
Kickoff Meeting 10%
Preliminary Design Review 15%
Detailed Design Review 15%
Installation and Test Readiness Review 20%
In-plant Acceptance Test 20%
On-site Acceptance Test 20%
*Note: Milestones for each Feed Upgrade may occur simultaneously. The Milestone Payment Schedule has been split into two, so that non-simultaneous milestones, such as On-Site Acceptance Test, can be invoiced at the time they are successfully completed. Considering the sequential nature of installation on the two antennas, this may be beneficial to the contractor.
3. RFP clause CAR 1352.270070 “Period of Performance” is changed as follows:
The Period of Performance of the contract shall not exceed 36 months from contract award date.”
4. SOW 4.5 “Period of Performance” is changed as follows:
The period of performance for the delivery of HR1 and HR2 Feed Upgrades is 24 months. The period of performance for the manufacturer’s warranty, which begins upon acceptance of each feed upgrades, is 12 months. The total contract period of performance is 36 months (24 months feed upgrades + 12 months for warranties.)
5. RFP “Clauses Incorporated in Full Text” is revised to include FAR 52.246-18 Warranty of
Supplies of a Complex Nature.
6. SOW Appendix A.2 “S-Band and L-Band LNA Assembly Upgrade Requirements” is revised so the LNA Gain Slope specification is changed from .005 to .005 dB / MHz.
File details come from the government source that posted it. Updated .