Sol_1305M327Q0042_Amd_0002.pdf
PDF 971 KB Posted
- Attached to
- Snow Removal Services WFO Johnston
- Solicitation number
- 1305M327Q0042
About this file
This is Amendment 0002 to Request for Quote (RFQ) 1305M327Q0042 issued by the National Oceanic and Atmospheric Administration (NOAA) National Weather Service for snow removal services at the Weather Forecast Office in Johnston, Iowa. The amendment was issued on November 17, 2026, with an effective date of November 17, 2026, and includes answers to 40 questions submitted by potential quoters, an updated snow removal map with revised trigger amounts, and an amended CAR 1352.270-70 Period of Performance clause. The closing date and time remain unchanged.
The solicitation is set aside for small business and covers snow removal and ice-melt services at the Johnston WFO facility on a firm-fixed-price basis. The base period runs from December 14, 2026, through December 13, 2027, with four one-year option periods extending through December 13, 2031. Services include snow removal triggered at two inches of accumulation or upon request, with a two-hour response requirement operating 24/7/365. The contractor should estimate 12 snow events per season for pricing purposes and quote a fixed annual lump sum regardless of actual snowfall occurrences. The total estimated price range is $28,500 to $38,500 over the entire period of performance. No specific insurance minimums or bonding requirements apply. Service Contract Act Wage Determination 2015-4979, Rev. 30 (dated 08/22/2026) governs labor rates. The requirement is a new contract with no incumbent, and the solicitation requires demonstration of two separate and distinct completed snow removal projects within the past three years for prior experience evaluation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
JENNA L. TAULMAN
See continuation page
WAD-NOS
7600 SAND POINT WAY NE BLDG 1
SEATTLE WA 98115
WAD-NOS
1305M327Q0042
11/17/2026
11/13/2026
1 12
SF30 (continued)
1305M327Q0042 Amendment 0002
Amendment 0002 is issued to complete the following:
A. Answer questions received in response to solicitation 1305M327Q0042 in a separate attachment.
B. Provide an amended Attachment 2 Snow Removal Map for solicitation 1305M327Q0042, which:
1. Updates the trigger amount.
C. Provide an amended CAR 1352.270-70 Period of Performance (APR 2010) for solicitation 1305M327Q0042, which:
1. Updates the period of performance.
D. The closing date and time remains unchanged.
****** END AMENDMENT 0002 ******
Request for Quote (RFQ) 1305M327Q0042 National Oceanic and Atmospheric Administration (NOAA)
National Weather Service (NWS) Weather Forecast Office (WFO) Johnston
Snow Removal Services
QUESTIONS AND ANSWERS
1. Q: The solicitation states the questions deadline in three places: Section 2(xii) and Section 6 state 2:00 PM PST on November 19, 2026; the Section 4 addendum states 2:00 PM PST on November 20, 2026; and Section 5 states no later than 6 calendar days after issuance. Could you please confirm the correct deadline for submitting questions?
A: Section 2 (Combined Synopsis/Solicitation) and Section 6 (Instruction to Offerors) are correct, 2:00 PM PST on November 19, 2026.
2. Q: A site visit is encouraged but no date or time is stated, and the solicitation states site visits are permitted until the end of the questions period.
Q6a: Is a site visit scheduled, and if so, when and how do we arrange to attend?
A: Please see RFO 52.237-1 Site Visit. (APR 1984) for site visit instructions.
Q6b: Please also confirm the Technical Point of Contact — the solicitation names Jessica Busch with the email address jessica.tweedt@noaa.gov.
A: The Technical Point of Contact information is correct.
3. Q: The Statement of Work and the Schedule of Items state the base period as December 14, 2026 through December 13, 2027, with option years running December 14 through December 13, but CAR 1352.270-70 states the base period as December 14, 2026 through November 30, 2027, with option periods running December 1 through November
30. Which period-of-performance dates govern, for the base year and each option year?
A: The anticipated base period of performance is December 14, 2026 - December 13, 2027 with potential options running as follows:
Option Period I December 14, 2027 - December 13, 2028 Option Period II December 14, 2028 - December 13, 2029 Option Period III December 14, 2029 - December 13, 2030 mailto:jessica.tweedt@noaa.gov
Option Period IV December 14, 2030 - December 13, 2031
4. Q: Does FAR 52.219-14, Limitations on Subcontracting, apply to this requirement, and if so, how is the limitation measured (percentage and basis)? (The clause does not appear in the solicitation.)
A: RFO 52.219-14, Limitations on Subcontracting, does not apply to this requirement.
5. Q: Please confirm that Service Contract Act Wage Determination 2015-4979, Rev. 30, dated 08/22/2026, governs this requirement, and which labor categories apply to this work (for example, Laborer, Grounds Maintenance 11210, and/or a Truckdriver classification for plow-truck operators)?
A: Yes, the Service Contract Act Wage Determination 2015-4979, Rev. 30, dated 08/22/2026, governs this requirement. Please see RFO 52.222-42, Statement if Equivalent Rated for Federal Hires (MAY2014) in the solicitation for a list of labor categories.
6. Q: FAR 52.232-18, Availability of Funds, is incorporated in the solicitation. Are funds presently available for the base year of this requirement?
A: Yes.
7. Q: Factor 2 (Prior Experience) allows a quoter to rely on a proposed subcontractor's experience. Could you please confirm what qualifies as "similar in size and scope" for this requirement — for example, would two commercial snow-removal projects of comparable annual value in the Des Moines area within the last three years satisfy the factor?
A: Yes.
8. Q: Section 6 states the total estimated price range of $28,500.00–$38,500.00 is "over the entire period of performance." Please confirm this range covers the base year plus all four option years combined, and that each option year is priced as a single firm-fixed-price annual lump sum.
A: The total estimated price range includes the base plus the potential four option periods.
9. Q: Must NAICS 561730 be active on the offeror's SAM registration at the time of quote submission?
A: No, however, if a NAICS is not explicitly listed on the offeror’s SAM registration, they must represent their company size for NAICS 561730 in RFO 52.219-1 and provide the representation to the Contracting Office. RFO 52.219-1 is included in the solicitation for offerors to fill.
10. Q: No insurance coverage or minimum limits are stated in the solicitation, and no insurance clause appears in the form. Please confirm no specific insurance minimums are required for this requirement.
A: No specific insurance minimums are required for this requirement.
11. Q: Attachment 2 (the site snow map) is dated season 2019–2020 and lists the salt and ice-melt application rates as "undefined."
Q11a: Is that map current?
A: Yes.
Q11b: Is there a specified ice-melt product, brand, or application rate, or is the choice of granules left to the contractor provided they will not harm grass, shrubs, concrete, or asphalt?
A: The choice is left to the contractor's discretion.
12. Q: The Statement of Work sets a 2-inch trigger but does not state an estimated number of snow events per season. Is there an estimated number of plowing events or ice-treatment applications per season we should use for pricing, or is pricing to be a seasonal lump sum regardless of event count?
A: Based on historical data, quoters should use an estimate of 12 events per season to calculate pricing. Please price the services according to standard commercial (non-government) rate structure.
13. Q: We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services.
A: This is a new contract.
14.Q: The Schedule of Items lists CLINs 0001 through 4001 as "1 Year" quantities under a Firm-Fixed-Price structure, but SOW Section 5 references monthly billing in arrears based on performance of tasks upon occurrence (2-inch triggers and on-demand calls).
Could the Government clarify whether offerors are expected to propose a flat, all-inclusive monthly/annual seasonal price regardless of actual snowfall occurrences, or if the Government intends for monthly billing to reflect fixed per-push/per-event rates based on recorded service tickets?
A: Please see the answer to Q12.
15.Q: To establish fair, reasonable, and competitive pricing across the Base Year and four Option Periods, could the Government provide the historical average number of snow clearing and ice melting service events (or average annual billable push events) experienced at the Johnston WFO over the past three winter seasons?
A: Please see the answer to Q12.
16.Q: SOW Section 3.1 states that snow removal shall begin when accumulation reaches two (2) inches or within two (2) hours of a request, and that snow shall not exceed four
(4) inches during ongoing storms. For sustained, multi-day winter storms with continuous accumulation exceeding four inches, does the Government anticipate continuous multi-pass clearing under a single fixed event, or are separate billable runs recognized for each distinct accumulation cycle?
A: Multi-day storms with continuous accumulation can be on the same invoice broken down by the service performed. For example, if in a single day, one comes out to clear 3 separate times the invoice would state ‘date - snow removal - 3(qty) - cost per - total’. A new line item is needed per date and service type.
17.Q: Attachment 2 designates primary and secondary snow storage areas on site. In the event of severe, consecutive winter storms where designated on-site storage areas reach maximum physical capacity, will off-site hauling and relocation be required, and if so, how should offerors account for off-site hauling in the pricing schedule?
A: Due to our large adjacent grass areas, we have historically not needed off site hauling.
18.Q: Section 7 (Evaluation Criteria), Factor 2 states: "If relying on a proposed subcontractor's experience to meet this requirement, the quote must satisfy all criteria listed in Section 6 for this factor." Please confirm that if a prime quoter teams with an operational subcontractor performing on-site clearing, submitting two (2) recent, relevant snow removal project references completed by that proposed subcontractor satisfies all requirements of Factor 2.
A: If the Quoter relies on the experience or past performance of a proposed subcontractor to meet the evaluation criteria, the quote must identify the subcontractor by name and specify the portion of work they will perform. Formal teaming agreements or commitment letters are not required at the time of quote; however, by submitting a quote that relies on a subcontractor's experience or past performance, the Quoter certifies that the named subcontractor has agreed to perform the stated scope upon award, and any subcontractor whose experience is credited toward award shall not be replaced after award without the Contracting Officer's prior written consent. The Quoter must perform a meaningful portion of the primary and vital contract requirements and may not act merely as a pass-through for another business; all subcontracting arrangements must comply with applicable small business size, affiliation, and subcontracting regulations.
19.Q: SOW Section 3.2 mandates the application of ice melting granules that will not damage concrete, asphalt, or adjacent grass and shrubbery. Could the Government clarify if a specific chemical compound or certification (e.g., Calcium Magnesium Acetate [CMA], encapsulated urea, or USDA BioPreferred certified products under FAR 52.223-1) is required or preferred for environmental compliance at this facility?
A: The choice is left to the contractor's discretion as long as it meets the described standards.
20.Q: Will the awarded contractor be permitted to stage operational equipment (such as a plow truck or skid steer) or maintain a covered/palletized on-site cache of approved ice melting granules at the facility throughout the active winter operational season (October through April)?
A: We do not have space for long-term parking of a truck or skid steer. We could arrange space for one pallet of ice melt.
21.Q: Given that meteorological shift staff operate 24/7/365 and contractor mobilization is required within two (2) hours, what are the specific physical entry procedures for nighttime, weekend, or holiday dispatches (e.g., electronic gate access codes, proximity cards, or on-duty staff escort)?
A: Open Lot for the office - no gate code needed or escort due to outside service. For the Radar - the drive up entry to the first gate is only needed to be cleared so no entry into the gated area is necessary. A REAL ID is required at all times.
22.Q: We request clarification regarding the ice-treatment requirement for the Johnston Weather Forecast Office. The SOW requires ice-melting granules that “will not kill grass and/or shrubs or damage concrete and asphalt surfaces,” but our snow-removal contractor advises that no available de-icing product is completely harmless to all of those surfaces and vegetation; magnesium chloride and calcium magnesium acetate each have tradeoffs.
Q22a: Is there an approved product or acceptable performance standard the contractor should use?
A: Our priority is the safety of people coming and going from the office and parking lot.
Limiting damage to the parking lot takes priority over minor damage to grass and shrubs.
Q22b: Alternatively, may the contractor propose the least harmful granular product and disclose its limitations?
A: This would be an acceptable option.
23.Q: Some pages in the solicitation have November 19 as the questions deadline and others as November 20. Can you please confirm which date?
A: Please see the answer for Q1.
24.Q: The period of performance is different in the SOW compared to that stated on page 14 of the solicitation document. I’m assuming that on the SOW is the one to go by but could you please confirm which.
A: Please see the answer for Q2.
25.Q: Could you please confirm whether a site visit is planned, and the deadline for questions before the 11/24 due date?
A: Please see amendment 0001.
26.Q: Please confirm for 1305M327Q0042: (1) whether it is, or may be, set aside for small business or WOSB/EDWOSB.
A: In accordance with the Standard Form 1449 and Section 2 - Combined Synopsis/ Solicitation, this requirement has been set aside for small business.
27.Q: Please confirm how to be on the bidders list.
A: The Government does not maintain a bidders list for this solicitation.
28.Q: The SOW and CLIN schedule indicate December 14–December 13 annual periods, while CAR 1352.270-70 specifies different dates. Could you confirm the controlling performance dates for the base and option years?
A: Please see the answer for Q3.
29.Q: The SOW requires snow removal after 2 inches of snowfall or upon MIC request, while the site map states "On call only." Should the contractor automatically initiate service at 2 inches, or wait for Government authorization?
A: The contractor should initiate service at 2 inches.
30.Q: Does the two-hour response requirement apply to all snow events, including nights, weekends, and holidays? Does the two-hour period begin upon Government notification?
A: Yes, the facility is 24x7. The 2 hour period begins when snow reaches 2 inches.
31.Q: Will the contractor receive standing authorization for emergency and after-hours access, considering the two-hour response requirement and the general 72-hour advance access notification provision?
A: Please see the answer for Q21.
32.Q: Could the Government provide the approximate annual number of snow removal and ice-treatment events from previous seasons to support accurate fixed-price calculations?
A: Please see the answer for Q12.
33.Q: Is the provided 2019–2020 snow removal map still current?
A: Please see the answer to Q11a.
34.Q: Could the Government confirm whether the entire radar-complex driveway and all SOW-designated areas are included in the required service boundaries?
A: If the question is asking if all required areas are included on the map, then no. The map depicts everything except the radar driveway. The radar driveway is located ¼ mile south of the office location on the same road.
35.Q: Should each annual CLIN be quoted as a fixed annual amount regardless of snowfall frequency?
36.Q: Will payments be made in equal monthly installments or based on services actually performed?
37.Q: Are there any specific approved deicing products, material specifications, or restrictions beyond the requirement to protect vegetation, concrete, and asphalt?
A: Please see the answer for Q11b.
38.Q: Are there any minimum liability insurance requirements, special licenses, or bonding requirements applicable to this contract?
A: Please see the answer for Q10a. There are no special licenses or bonding requirements.
39.Q: Please confirm whether separate pricing is required for the potential six-month extension under RFO 52.217-8, or whether it will be calculated using Option Year 4 pricing.
A: Please see RFO 52.217-5 Evaluation of Options. (JUL 1990) (Deviation JAN 2026) in the solicitation.
40.Q: Factor 2 (Prior Experience) asks for two snow removal projects completed within the last three years. Snow removal is usually contracted by the season, and many local providers hold multi-year agreements that renew each winter. Will a completed winter season (for example, November 2025 through April 2026) under an ongoing multi-year snow removal agreement count as a completed project for Factor 2?
A: No. A multi-year agreement constitutes one project. Quoters must submit two separate and distinct completed projects.
Trigger Amount
Hours of Operation
Ice Control
Type Rate
Salt undefined
Ice Melt undefined
Notes
N/A
Standard
24/7/365
See Statement of Work
N at io na l W ea th er
S er vi ce
N W
B ea ve r D riv e|
J oh ns to n, Io w a
Updated Nov 2026
D a t e
R e v i s i o n s
Snow Map
Stop snow removal at posted sign
Blow to this side
Concrete Wheel Stops
0' 20' 40'
North
N
N W
B e a v e r
D r i v e
LEGEND
Hazards
Exit Doors
Direction of Push
Primary Snow Storage
Secondary Snow Storage
Fire Hydrant
Walks/Pedestrian/
Handicapped Stalls
Special Area of Concern
Snow Site Boundary
1305M327Q0042 0002
1352.270-70 Period of performance. (APR 2010)
(a) The base period of performance of this contract is from December 14, 2026 through November 30 13, 2027. If an option is exercised, the period of performance shall be extended through the end of that option period.
(b) The option periods that may be exercised are as follows:
Option Period Period of Performance Option Period I December 1 14, 2027 - November 30 13, 2028 Option Period II December 1 14, 2028 - November 30 13, 2029 Option Period III December 1 14, 2029 - November 30 13, 2030 Option Period IVDecember 1 14, 2030 - November 30 13, 2031
(c) The notice requirements for unilateral exercise of option periods are set out in FAR 52.217-9.
(End of clause)
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Amendment 0002.pdf |
| Q&A RFQ 1305M327Q0042 Snow Removal Services, WFO Johnston.docx |
| DMX Snow Removal Map_2026 |
| Sheets and Views |
| 11x17 |
1305M327Q0042 3
File details come from the government source that posted it. Updated .