This is a Statement of Work (SOW) for the National Weather Service requiring complete replacement of existing irrigation systems and landscape drainage repair at three locations in Texas: Corpus Christi (426 Pinson Drive), Midland (2500 Challenger Drive), and New Braunfels (2090 Airport Road). The contractor must deliver fully functional and operational systems at all three locations within 120 days from the date of award, with earlier completion desired. The project requires a turnkey solution encompassing all management, supervision, engineering, design, labor, equipment, materials, tools, and testing necessary for completion using industry standards and best practices.
Key deliverables include system design and mapping with government approval, backflow preventor inspection and replacement where needed, removal of existing irrigation equipment with abandonment of old piping and wiring in place, installation of new weather-based controllers with seasonal scheduling and rain-shutoff sensors, installation of new pressure-regulating high-efficiency sprinkler heads with proper coverage adjustments, and location-specific landscape restoration. Corpus Christi requires topsoil and sod installation (20 cubic yards topsoil, 2,500 square feet sod); Midland requires mulch replacement with rock (4 cubic yards), weed barrier repair, and topsoil addition (2 cubic yards); New Braunfels requires culvert cleaning, topsoil and sod installation in multiple areas (14 cubic yards topsoil, 1,600 square feet sod), rock addition (6 cubic yards), and landscape edging replacement (280 feet). The contractor must provide system testing with government demonstration, staff training, and complete as-built drawings. The contractor shall provide a minimum five-year written warranty on parts and one-year written warranty on workmanship. Work hours are 7:00 AM to 5:00 PM Monday through Friday, excluding federal holidays. All work must comply with OSHA, EPA, NEC, NFPA standards and applicable local and state codes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Background:
The National Weather Service (NWS) is in need of complete replacement of the existing irrigation system and landscape drainage repair in the following three (3) locations in Texas:
Corpus Christi, Midland and New Braunfels.
Objectives:
The objectives of this project are to:
• Improve the efficiency, uniformity and reliability of water irrigation system to ensure optimal landscape health.
• Automate watering schedules with a modern, weather-based irrigation controller.
• Replace inefficient equipment to reduce water waste and overspray.
• Ensure the system is operating in compliance with all relevant state and local codes and standards.
• Restore landscape rock, soil and sod to ensure issues are addressed at each location.
Scope:
The NWS expects a ‘turnkey solution’ for this contract. The work to be performed under this project requires the Contractor to provide all management, supervision, engineering, design, labor, equipment, materials, tools, testing, and other services necessary for the completion of all tasks. All work is to be completed using industry standards and best practices.
Attachment 1 – Site Photos (in the Statement of Work) outlines the areas needing sprinkler coverage for all three (3) locations.
Places of Performance:
NWS - Corpus Christi 426 Pinson Drive Corpus Christi, TX 78406-1824
NWS - Midland 2500 Challenger Drive Midland, TX 79706-2606
NWS - New Braunfels 2090 Airport Road New Braunfels, TX 78130-2744
Period of Performance:
Provide a fully functional and operational system at each of the three (3) locations no later than 120 Days from Date of Award, however, sooner is desired.
Government Point of Contact at Each Location:
To be provided in award.
General Requirements:
The Contractor shall provide all supervision, labor, tools, materials and equipment necessary to perform work in accordance with the Statement of Work the manufacturer’s specifications and requirements; all applicable federal, state, and local laws; Occupational Safety and Health Administration (OSHA), Environmental Protection Agency (EPA), National Electrical Code (NEC), and National Fire Protection Association (NFPA) standards; building and facilities codes and criteria; and according to standard industry practices.
The Contractor Shall:
Task 1: All Locations
System design and mapping:
• Design irrigation system to accommodate requested coverage areas.
• Map locations for controller, backflow preventor, manifolds, piping, valves, heads and zone layout.
• Provide a copy of the irrigation system map to the Government Point of Contact for review and approval.
Existing equipment:
• Inspect backflow preventor and insure it functions properly and is code compliant.
Replace or install new where needed.
• Remove existing heads, valves, manifold and valve boxes.
• Abandon in place- piping and wiring
Controller replacement:
• Replace the existing irrigation controller with a new weather-based controller.
• Program the new controller with a seasonal watering schedule to optimize water use.
• Install a rain-shutoff device or other sensors to prevent watering during and after precipitation.
Pipe, valve and wire installation:
• Request survey of existing utilities prior to excavation. It will be the responsibility of the contractor to repair and replace any damages made during excavation.
• Locate existing piping under roadways and sidewalks to test and reuse or replace.
• Install piping and wiring in same trench using industry standards. Add a single insulated conductor tracer wire for future locating and troubleshooting.
• Install manifolds in below grade boxes for protection and future access.
• Install valves below grade with valve boxes to protect from damage.
Heads and nozzles:
• Install pressure-regulating, high efficiency designed heads to reduce misting and improve efficiency for uniform coverage.
• Install heads in a manner to protect from damage. Install protection rings or guards in areas with mower traffic as needed.
Component additions and adjustments:
• Adjust all heads and rotors to ensure proper coverage and eliminate overspray onto buildings, sidewalks, driveways, and non-landscaped areas.
Turf and landscape restoration:
• Perform any necessary landscape restoration, such as soil and sod replacement, in areas disturbed during excavation, valve removal and head removal.
Project closeout:
• Perform a complete system test with the Government Point of Contact to demonstrate full function.
• Perform any adjustments needed and address any concerns from the Government Point of
Contact.
• Provide the staff with training explaining the functions and settings of the controller.
• Provide the NWS with a complete as-built drawing of the complete system.
Exclusions:
• Installation of a new water meter or replacement of the main water line.
Task 2 -: CORPUS CHRISTI, TX:
Turf and landscape restoration:
• Add topsoil and sod in low areas around trees with exposed roots, ensuring a match with the existing sod. (Approximate measurements: Topsoil - 20 cu yd; Sod - 2500 sq ft)
Task 3: MIDLAND, TX:
• Remove exiting mulch and replace with rock. Match existing rock. (Approximate measurement: Rock- 4 cu yd)
• Ensure weed barrier is intact. Replace as needed.
• Add topsoil in low areas along sidewalks and around trees with exposed roots.
(Approximate measurement: Topsoil- 2 cu yd)
Task 4: NEW BRAUNFELS, TX:
• Clean out culvert, add topsoil and sod to allow for proper drainage. (Approximate measurements: topsoil- 6 cu yd; sod- 800 sq ft)
• Add topsoil and sod in low areas around trees with exposed roots and along sidewalks.
(Approximate measurements: -topsoil- 8 cu yd; sod- 800 sq ft)
• Add rock to low areas around buildings. Match existing. (Approximate measurement: -rock- 6 cu yd)
• Replace existing landscape edging. (Approximate measurement: edging 280 ft)
• Once work is complete check for proper drainage slope to avoid ponding.
Project Warranty:
The Contactor shall provide a minimum five (5) year written warranty on parts and one (1) year written warranty on workmanship.
STANDARD CLAUSES
A. Compliance.
The Contractor shall comply with all local, state, and Federal environmental, health, and safety regulations while conducting this work. In addition, the Contractor shall ensure that all work is in compliance with the applicable codes and be responsible for all licenses, permits and fees required to complete this project.
B. Disposal.
The Contractor will be required to properly remove and dispose of all waste material in an environmentally friendly manor off site.
C. Guidelines.
The Project shall follow the guidelines stated in the Statement of Work, site diagrams, blueprint, and any Contractor-provided quote documents. All modifications must be submitted and approved by the Contracting Officer.
D. Hours of Operation.
Work shall be performed between 7:00am & 5:00pm Monday thru Friday unless otherwise approved by the Government Point of Contact.
Contractor agrees to observe all Federal holidays, and any other day off work designated by Federal Statute, Executive Order, or Presidential Proclamation.
Federal Holidays:
New Year’s Day Martin Luther King Day Presidents Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veteran’s Day Thanksgiving Christmas
E. Facility Access.
A project sign in sheet shall be completed each day for all contractors, contractor employees and subcontractors on site.
F. Government Contact.
The Government Point of Contact for each location will be provided in award.
SAFETY AND EMERGENCY PLAN:
A. The Contractor shall observe and institute all applicable OSHA safety requirements and procedures to prevent accidents and injuries to both Contractor and Government employees including 40 CFR 1926 Subpart M for fall protection requirements.
B. The Contractor shall designate one person as Safety Coordinator for purposes of communication between the Contractor and the Government Point of Contact.
C. Contractor shall provide a Safety Plan and Procedure to protect employees from being injured while on the job site. Submit plan to the Government Point of Contact for review and approval.
D. Contractor shall provide an Emergency Plan and Procedure to provide immediate care for an employee injured while on the job site. Submit plan to the Government Point of Contact for review and approval.
GOVERNMENT PROVIDED MATERIALS AND/OR SERVICES
A. EXCLUSIONS:
Unless otherwise indicated elsewhere in this Statement of Work, the Government will provide no data, materials, equipment and/or services to the Contractor. Any and all research required to fulfill the Statement of Work described herein, shall be the responsibility of the Contractor. The Government retains the right to request the Contractor to acquire additional information on behalf of the Government.
B. WARRANTY:
The Government does not warrant that any documents provided as attachments to be free from discrepancies, ambiguities, errors, omissions, or changing conditions. It is the responsibility of the Contractor to confirm existing conditions and resolve discrepancies between documents.
***All submittals shall become the property of the U.S. Government***
ATTACHMENT 1 – SITE PHOTOS
NWS - Corpus Christi 426 Pinson Drive
Corpus Christi, TX 78406-1824
Area Needing Sprinkler Coverage
NWS - Midland 2500 Challenger Drive
Midland, TX 79706-2606
NWS - New Braunfels 2090 Airport Road
New Braunfels, TX 78130-2744
Project Warranty: