This document is Amendment 0001 to Solicitation 1305M326Q0052, issued by the Wave-Satellite Activity Program (WAD-SAP) at the National Oceanic and Atmospheric Administration (NOAA), located at 325 Broadway, Boulder, Colorado 80305. The amendment is effective February 3, 2026, and includes vendor questions and government responses received as of February 4, 2026, with no other changes to the solicitation.
The amendment addresses five vendor inquiries regarding sewer line repair and replacement work beneath a raised access floor. Key findings include: the Government has confirmed multiple CCTV inspections were performed on the affected sewer line but recordings are not available; the existing pipe is 4-inch cast iron transitioning to PVC in the bellied and slumping section, with an estimated 20 linear feet requiring repair or replacement; contractor verification via CCTV inspection is at the contractor's discretion; the raised access floor system consists of reusable modular panels and stanchions that can be removed and reinstalled with proper care, eliminating the need for full architectural floor replacement; and if actual repair length exceeds the estimated 20 linear feet, any additional footage will be handled through proper change order procedures. The amendment requires offerors to acknowledge receipt prior to the specified offer deadline by completing and returning the form, acknowledging receipt on offer copies, or submitting separate written communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt may result in offer rejection.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
KERRI COFFEY
See continuation page
WAD-SAP
325 BROADWAY, SOU6
BOULDER CO 80305
WAD-SAP-B
1305M326Q0052
02/03/2026
02/03/2026
1 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1305M326Q0052/0001
AMENDMENT NUMBER 0001 (02/05/2026): VENDOR
QUESTIONS RECEIVED AS OF 02/04/2026 AND
GOVERNMENT RESPONSES NO OTHER CHANGES.
QUESTION 1: Sewer Line Condition Verification
- The SOW references an estimated approximately 20 linear feet of sewer line beneath the raised access floor requiring repair or replacement.
Question a: Has a recent CCTV inspection or sewer camera video been performed to confirm the location, extent, and condition of the failed section?
Question b: If so, can that documentation be provided? If not, please confirm that the 20 LF is an estimate based on drawings and observed symptoms.
ANSWER to Question a: Yes, there have been multiple sewer camera videos done on the affected line.
ANSWER to Question b: We do not have recordings of the sewer camera videos. The 20
LF section is based on where the line descends from 4' to 6 ', levels out and extends to the septic system manhole.
QUESTION 2: Pipe Size and Material - Please confirm the existing sewer pipe size(s) and material(s) within the area of repair (e.g., cast iron, PVC, clay, etc.), to the extent known.
ANSWER: As stated in the statement of work "4 inch cast iron" that transitions into PVC where it is bellied and slumping.
QUESTION 3: Access and Verification
Expectations - Does the Government anticipate that the contractor will perform initial verification (e.g., CCTV inspection once access is obtained) to confirm the actual limits of repair prior to replacement?
ANSWER: Verification is at the discretion of the contractor.
QUESTION 4: Raised Access Floor Restoration -
Please confirm that the raised access floor system consists of removable modular panels intended to be temporarily removed and
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1305M326Q0052/0001 reinstalled, and that full architectural floor replacement is not anticipated provided panels are properly protected and reinstalled.
ANSWER: Yes, the stanchions are glued and in some places anchored to the concrete and can be reused with proper care. The raised floor tiles can easily be removed and reused.
QUESTION 5: Scope Adjustment for Additional
Length - In the event the actual required repair length exceeds the estimated 20 LF once conditions are verified, please confirm whether additional footage would be handled via a change order or other contractual mechanism.
ANSWER: In the chance that this should happen it will have to go through the proper channels to address this.
1305M326Q0052 0001
Section II - Supplies or Services and Price/Costs
CLIN List
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |