This document contains a set of questions and responses related to a federal solicitation for the Electrical Upgrade project at the Atlantic Oceanographic and Meteorological Laboratory (AOML). The solicitation was issued by the U.S. Department of Commerce (DOC), National Oceanic and Atmospheric Administration (NOAA), Western Acquisition Division (WAD) on behalf of the Oceanic and Atmospheric Research (OAR) division.

Key details include:

  • The solicitation number is 1305M324R0086 and the solicitation is for a Firm-Fixed-Price (FFP) contract.
  • The solicitation includes a site visit on August 20, 2024 and September 11, 2024, with proposal submissions due by September 25, 2024.
  • The solicitation provides responses to inquiries regarding as-built drawings, site visit attendance, font and formatting requirements for the technical proposal, and construction schedule submission.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1305M324R0086 Solicitation Inquiries and Responses

1. Are there any as-built drawings that show the electrical system including a ONE LINE diagram of the facility?

GOVERNMENT RESPONSE: All applicable documentation is available on SAM.gov.

2. Is it presolicit or solicit phase?

GOVERNMENT RESPONSE: This is a solicitation.

3. Is it mandatory to attend the Site Visit?

GOVERNMENT RESPONSE: Attendance to the site visit is recommended, but not mandatory in accordance with FAR 52.236-27.

4. Are there were any special instructions or requirements to attend the site visit?

GOVERNMENT RESPONSE: No special instructions beyond what is listed in the solicitation.

Refer to FAR 52.236-27 Alt 1, Site Visit, for site visit details.

5. Will there be another site visit?

GOVERNMENT RESPONSE: FAR 52.236-27 Alt I Site Visit, is revised to add a second site visit on

September 11, 2024 at 0930 Eastern.

FAR 52.236-27 Alternate I

(b): An organized site visit has been scheduled for - August 20, 2024 at 09:00 AM Eastern Time and September 11, 2024 at 09:30 AM Eastern Time

(c): Participants will meet at -

Enter through the loading dock door and check in with the receptionist in the lobby at: Atlantic

Oceanographic and Meteorological Laboratory, 4301 Rickenbacker Causeway, Miami, FL 33149

6. Page 65 of the solicitation, paragraph (2), says the proposal shall be typed, double-spaced, with one inch margins, using size 12-font or equivalent etc. Will the Government please allow all resumes, schedules, tables, figures, charts, cover letters, cover pages, table of contents, acronym list, and headers/footers to be 10-Point Times New Roman Font, single spaced? Applying 12 point font, double space to any of these mentioned items is almost impossible and makes answering the RFP questions extremely difficult. By allowing all resumes, schedules, tables, figures, charts, cover letters, cover pages, and headers/footers to be 10-Point Times New Roman

Font, single spaced will allow us to provide enough detail to answer all RFP questions.

GOVERNMENT RESPONSE: CAR 1352.215-70(a)(2) is revised to read: (2) “…The Technical

Proposal shall not exceed 25 pages, exclusive of the table of contents, resumes and construction schedule. Tables, charts, figures, header/footers, construction schedule and resumes are exempt from the 12-font requirement. Any pages in excess of these limitations will be disregarded, and will not be included in the proposal evaluations…”

7. Page 65 of the solicitation, paragraph (iii Specific areas to be addressed), says offeror shall provide a detailed narrative describing its technical approach for the project including methodology, project management approach, schedule, and logistical considerations. Please confirm a preliminary construction schedule is not required to be submitted to meet the requirements of Factor 1. If a preliminary construction schedule is required to be submitted to meet the requirements of Factor 1, please allow the schedule to be excluded from the page count allowed for the Technical Proposal, and please allow the schedule to be 10-Point Times

New Roman Font, single spaced.

GOVERNMENT RESPONSE: See response to inquiry #6.

8. Could you please share with us the bid documents to participate in?

GOVERNMENT RESPONSE: All applicable documentation is available on SAM.gov. Refer to

Section L of the solicitation for proposal submission instructions.