This document is an amendment to a Request for Quotation (RFQ) for fiscal year 2025 drydock repairs to the National Oceanic and Atmospheric Administration (NOAA) Ship Bell M. Shimada. The amendment provides answers to contractor questions, revises the technical specifications, extends the response due date, and includes additional information and references.
Key details include:
- The purpose of the amendment is to 1) answer questions, 2) provide a revised specification with edits, 3) provide a more user-friendly specification document, 4) include requested photos and references, and 5) extend the response due date from July 15 to July 26, 2024.
- The RFQ is for a firm-fixed price contract for drydock repairs to the NOAA Ship Bell M. Shimada. The work includes overhaul of the ship's systems, tank inspections, preservation, and other maintenance activities.
- Contractors are required to acknowledge receipt of the amendment prior to the due date in order for their offer to be considered.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1305M224Q0181 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
EAD-OMAO
NORFOLK VA 23510
FED BLDG 200 GRANBY ST SUITE 815
EAD-OMAO
07/11/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/14/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See attached.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
ASHLEY PERRY
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
RFQ1305M224Q0181
Amendment 0001
The purpose of Amendment 0001 includes the following:
1. To answer questions set forth below.
2. Provide a revised specification to reflect answered questions and clarifications with edits marked in red.
3. Provide a PDF version of the specification that has copy and past abilities.
4. Include photos and references as requested.
5. Extend the response due date from July 15, 2024, to July 26, 2024.
Question (Q): It was noted by the National Oceanic and Atmospheric Administration (NOAA) that there is a separate contract for the replacement of the ship’s Phone and Public Address General Alarm System (PX/PA/GA) scheduled during the dry dock period of performance.
Answer (A): Yes this is a standalone contract. Government's contractor for this work will need access to the vessel during the dry dock period of performance.
Q: Item 4.8 Ship’s Emergency Diesel Generator Top End Overhaul - Spec says to inspect the connecting rod bearings. This inspection is labor intensive and you might as well change the bearings for the amount of labor required to inspect. What is the government's intent here?
A: It is not the government's intent to get into the lower end of this engine. Remove requirements to inspect oil suction screen, and connecting rod bearings. Please see revised specifications.
Q: Item 4.8 Ship’s Emergency Diesel Generator Top End Overhaul - What are the run hours of the E-Gen?
A: Please see revised specifications.
Q: Item 4.7 Bridge Systems Updates - It was noted during the shipcheck that Radar and GMDSS additional requirements. Can you provide those additional requirements?
A: Yes, please see revised specifications.
Q: Item 3.25 SSDG Intake / Uptake - Contractor did not have access to the top of the stack. Can you provide photos?
A: Yes - Photos are attached.
Q: Item 3.19 Pipe Repairs - Para 4.b. What are the inlet and outlet valves?
A: Inlets are two inch threaded bronze body ball valve 2-piece. Outlets are 3 inch bronze globe valve 150# bolted flange. Please see revised specifications.
Q: Item 3.10 Hull Protection Anodes - The specification does not speak to preservation of the flanges or high hats for the Cathelco anodes. What is the government's intent?
A: The flanges and high hat shall be preserved. Add Para 4.b.5.i. to Item 3.10. With the anodes removed, provide a 3 to 5 mil profile to clean bare steel to the anode flange and high hat tube. Provide protective coating as per sea chest or high turbulence area paint schedule. Please see revised specifications.
Q: Item 3.7 Sea Valve Overhaul - Stainless steel split body ball valves Frame 90 could not be found during ship check. What is the government's intent here?
A: These valves have been removed from Shimada and the penetrations inserted. These two valves shall be removed from the requirements of this item. Please see revised specifications.
Q: Item 3.4 Propulsion Line Shaft Inspection - Are there pictures available of the stern tube pinhole area?
A: Yes - Photos are attached.
Q: Item 3.4 Propulsion Line Shaft Inspection - Frame 58 does not seem correct for this.
A: Correct. This pinhole is located between frames 85 and 86. Please see revised specifications.
Q: Item 3.4 Propulsion Line Shaft Inspection - 15% clad weld seems excessive. What is the intent here?
A: The government expects up to 8 individual clad weld areas approximately 6" by 6".
Q: Item 3.3 Tank Inspection - Para 4.g. is not clear; is this for 100% or 10% ?
A: Please see revised specifications.
Q: Item 3.12 Life Raft Annual Inspection - What make and model are the vessel life rafts?
A: Please see revised specifications to include raft details.
Q: Item 3.3 Tank Inspection - Para 4.d. calls for 10% spot repair in the waste water tank. Line g calls for 100% preservation of the waste water tank. Which are we to quote?
A: 100% Para 4.d. to be deleted. Please see revised specifications.
Q: Item 3.3 Tank Inspection - Para 4.g. calls for 100% preservation of the 4 listed tanks but line g.2 calls for 10% spot preservation. Which are we to quote?
A: 100% for listed tanks, 10 % for 3 starboard. Please see revised specifications.
Q: Item 3.17 Inspect Anchor Windlass and Capstans - Para 4.b.2 simply says to preserve the chain lockers IAW the supplied reference. However, the reference has 2 options...full blast to SP-10 or spot power tool to SP-3. Which are we to quote?
A: 100% preservation.
Q: Item 3.21 Preservation General - Para 4.a.6 calls for non-skid IAW MIL-PRF-24667, however the paint schedule lists an Amercoat #385ASA pedestrian non-slip system. Please clarify which system is correct.
A: Use non-skid IAW MIL-PRF-24667. The General Requirements 2.3.28 Painting 2.3.28.1 is also helpful for this question. The paint schedule is a list of installed coatings and can and does indicate obsolete systems. Coating from the specification takes precedence, then the NOAA standard specification, then the paint schedule.
Q: Please provide the specification in a PDF version that allows for copy and paste.
A: A copy of the Work Specification is attached in a more user-friendly PDF format.
Q: Item 3.24 MSD System Maintenance - The provided tech pub references the serial number of the Oscar Dyson. In order to verify the correct replacement media is ordered, will NOAA provide the serial number of the MX-5 installed on board Shimada?
A: The serial number is 13762.
Q: Item 3.29 - No references were provided for this work item and KTR is unable to accurately assess the areas to be preserved without a layout drawing or an estimated square footage area. Will NOAA provide either a layout drawing of the wet lab with dimensions or an estimated square footage of areas to be preserved?
A: NOAA has provided SH-085-FA02 General Arrangements as a general reference (applicable to all items). This scale drawing depicts the wet lab on Seet 006.
Q: Item 3.7 Sea Valve Overhaul - Please provide the missing valve sizes at 4.b Table 3.7-1 Sea Valves.
A: Macerator overboard is a 4 inch stainless steel ball valve. Please see revised specifications.
Q: Item 3.15 Steel / Hull Inspection Repairs - Please provide missing reference 2.b SH-085-FC02 Shell Expansion.
A: Reference is attached.
Q: Item 3.19 Pipe Repairs - Please provide missing reference called out at 5.a.
A: Please see revised specifications.
Q: Item 3.21 Preservation General - Please provide / clarify references at 4.a.5.
A: These are General References listed on page four of the Specifications, previously provided.
Q: Item 3.22 Pump Maintenance - Please clarify the following at 4.d.3, “6.21.1.d.3.1.”
A: This appears to be an erroneous "return" that should read "deleted." Please see revised specifications.
Q: Item 3.28 Deck Equipment - Please provide technical manual for net sound winch at 4.c.
A: References are attached.
Q: Item 3.28 Deck Equipment - Please clarify piping to be tested at 5.a.
A: Please see revised specifications.
Q: Item 3.29 Wet Lab - Listed vendor (Cospolich) reviewed ship check photos and reports units are not theirs. Please provide make and model numbers of units.
A: Shimada walk in coolers are International Cold Storage M#7400529 SPL S#09148101-2.
Please see revised specifications.
Q: Item 3.13 Small Boat Maintenance - Please provide Work Boat & Rescue Boat Engine Models & Serial Numbers.
A: Model numbers are provided in the specification.
Q: Item 3.28 Deck Equipment - Please identify what hose to provide and specs for hose noted under 4.a.6.
A: List of hoses provided via reference attached.
Q: Item 2.3.15 Habitability and Temporary Berthing, Para 2.3.15.2 - In the past NOAA has put the crew in hotels during the shipyard availability. Please confirm whether or not this is the plan. Should the KTR be required to provide temporary berthing, what size of crew should be anticipated?
A: It is the government's intent to berth crew off the vessel during the period of performance. No this would not be part of the drydock work. 25 crew is typical crew size.
Q: Item 3.2 Drydocking, Para 3.d.1 - Should bow thruster EAL be included one (1) time as part of item 4.10?
A: Correct, this standard grease Item is redundant to the overhaul Item 4.10
Q: Item 3.2 Drydocking, Para 3.f.1-4 - What is being changed that prompts the need for a revised docking drawing?
A: Changes generated in the performance of this item.
Q: Item 3.3 Tank Inspections, Para 5.a - Can KTR assume all ballast tanks will require hydro testing vice air testing per ABS requirements? Can KTR assume the vessel's master will confirm "pressure testing" of all fuel/lube oil tanks per ABS requirements?
A: No. Air Test shall be for all tanks.
Q: Item 3.4 Propulsion Line Shaft Inspections - Withdrawal, Para 3.i.4 - Could NOAA provide a detailed specification for the blasting and painting of the stern tube.
A: Standard paint specifications previously provided. Page three of the Paint schedule gives an example of what has been done in the past.
Q: Item 3.9 Underwater Body Preservation, In Reference 00 63 11_00, Underwater Body Preservation - It appears that statement 3.4.2.2 requests no topcoat of Anticorrosive Epoxy. Please confirm that only 1 coat of Anticorrosive Epoxy is to be applied to the spot preservation areas identified in 3.2.2.
A: Bidder appears to be mixing freeboard reference with underwater body, 3.2.2. of the underwater body refers to hull markings. Para 3.4.2.2. speaks only to areas prepared in a very specific manner. Bidder shall follow the specification for the preparation utilized.
Q: Item 3.9 Underwater Body Preservation, In Reference 00 63 11_00, Underwater Body Preservation - Are spot preservation areas described for the Maintenance coating in 3.2.2 applicable to the Underwater Body, or to both the Underwater body, inclusive of the Boot Top square footage?
A: Bidder appears to be mixing freeboard reference with underwater body, 3.2.2. of the underwater body refers to hull markings. Underwater body includes the Boottop.
Q: Item 3.9 Underwater Body Preservation, In Reference 00 63 11_00, Underwater Body Preservation - Is it acceptable to perform a fresh water wash or high-pressure air “blow down” rather than vacuuming requested in 3.3.3.3?
A: Para 3.3.3.3 specifically calls for no blow down.
Q: Item 3.19 Pipe Repairs - Can NOAA provide a Drawing? More info on valves & valve operators?
A: 10" Lug Style Butterfly Valve Epoxy Coated Iron with Aluminum Bronze Disc, gear Operator DETAILS: Disc: Aluminum Bronze Seat Material: EPDM Stem Material: 416 Stainless Steel Operator:
Local gear Body: Epoxy Coated Ductile Iron Bolt Pattern: 12 Holes
Q: Item 3.28 Deck Equipment - Can NOAA provide reference drawings and/or tech manuals for trawl doors, trawl door rams, slide pads, flag blocks and 3rd wire winch?
A: References attached.
Q: Item 3.28 Deck Equipment - Can NOAA provide reference drawings for the gangway swivel?
A: Reference attached.
Q: Item 3.28 Deck Equipment - Can NOAA provide reference drawings for the outrigger yoke and hinged gap guard plate?
A: "804-2255404 C Accom Ldr Upper Rot Pltfm" provides details of the yoke. Guard plate, no.
Q: Item 3.28 Deck Equipment - Can NOAA provide a detailed list of the hydraulic hoses that are to be replaced?
A: Reference attached.
Q: Item 4.4 Radio Repeater System, Para 2 - Provide reference?
A: Reference attached.
Q: Item 4.5 Lighting System Update - Can you confirm the government's intent that the lighting circuit wiring shall not be replaced?
A: Correct, wiring from the breakers to the light should not be replaced.