Thomas Jefferson_FY2024 Drydock Repair Package_20JUN2023_Rev (A).pdf
PDF 4 MB Posted
- Solicitation number
- 1305M223QNMAN0122
About this file
This solicitation is for drydock repairs and maintenance services for NOAA's Ship Thomas Jefferson for fiscal year 2024. The work includes routine drydocking, hull cleaning and inspection, tank cleaning and testing, sea valve overhauls, cathodic protection maintenance, propeller and rudder servicing, and upgrades to the ship's EM710 multibeam sonar system. The solicitation attachments provide a statement of work, past performance forms, pricing tables, and reference materials to support contractor bids. The solicitation also includes drawings, manuals, and NOAA standard specifications as references. The period of performance is August 8, 2023 through January 21, 2024.
View the file
Other files
Show 40 more
Latest 50 of 226 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA Ship Thomas Jefferson (S-222)
FY2024 Drydock Repairs
21 June 2023
Written by: Shelia Dailey Signature:
Marine Engineering Branch – MOA2 Marine Operation Center, Atlantic- MOC-A
439 West York Street Norfolk, VA 23510
NOAA Ship Thomas Jefferson TJ_FY2024_Drydock Repairs
Rev (A)
Page | 2
This Page Intentionally Left Blank
Page | 3
Record of Changes
Name Date Reason for Change Version
Initial Issue 10 May 2023 FY 2024 Drydock Repair Package Submission -
Rev A 21 June 2023
The following corrections were made to the work item listed:
1) 3.1.4.2.2 – Added requirements for High Speed internet to paragraph
2) 3.2 Item 302 – Revised reference (c) to read “TJ-562-001A”
Rudder Arrangement & Details
3) 3.9 Item 309 – Added new reference (f) and revised 3.9.7.c
4) 3.10 Item 310 – Revised TJ-085-002H to TJ-085-002G
5) 3.11 Item 311 – Added valve size to Item 39 on Table 311-1
6) 312 Item 312 – Added new Table 312-1 to reflect liferaft components nearing expiration
7) 312 Item 312 – Revised paragraph 3.12.4.8
8) 5.11 Item 511 – Revised numbers and descriptions to the
CFM list
A
Page | 4
Table of Contents
Record of Changes
1. SCOPE
2. GENERAL
3. BASE ITEMS
3.1 ITEM NO. 301: Temporary Services
3.2 ITEM NO. 302: Dry Docking and Routine Dry Dock Work
3.3 ITEM NO. 303: Dock Trials
3.4 ITEM NO. 304: Sea Trials
3.5 ITEM NO. 305: Cathodic Protection: Inspect & Repair
3.6 ITEM NO. 306: Rudders Inspections and Repairs
3.7 ITEM NO. 307: Propulsion Shaft Inspection and Repairs
3.8 ITEM NO. 308: Propeller Inspections and Repairs
3.9 ITEM NO. 309: ABS Tank Inspections
3.10 ITEM NO. 310: EM712 Transducer Upgrades
3.11 ITEM NO. 311: Sea Valves Overhaul
3.12 ITEM NO. 312: Liferaft Periodic Servicing
3.13 ITEM NO. 313: Underwater Body Coating - Maintenance
3.14 ITEM NO. 314: Refrigeration Units Groom
3.15 ITEM NO. 315: Fire Fighting System Periodic Servicing
3.16 ITEM NO. 316: Weight Handling Annual Inspection
3.17 ITEM NO. 317: Exhaust System (Galley & Quarters) Cleaning
3.18 ITEM NO. 318: Galley Equipment Servicing
3.19 ITEM NO. 319: Structural Replacements/Repairs
3.20 ITEM NO. 320: Anchor Windlass Overhaul
3.21 ITEM NO. 321: Main Engine Servicing
3.22 ITEM NO. 322: Detroit Diesel/MTU Servicing
3.23 ITEM NO. 323: Ship Service Diesel Generators No. 1- 3 Servicing and Repairs
3.24 ITEM NO. 324: Piping Repairs and Maintenance
3.25 ITEM NO. 325: HSL Davits Overhaul Industrial Support
4. OPTIONAL ITEM 400: ADDITIONAL ITEM REQUESTS
Page | 5
4.1 OPTIONAL ITEM 400: Additional Item Requests
5. OPTIONAL ITEMS
5.1 ITEM NO. 501: Various Deck Covering Replacements
5.2 ITEM NO. 502: Weather Deck Non-Skid Renewal
5.3 ITEM NO. 503: Interior Shelving Installation
5.4 ITEM NO. 504: Reduction Gear and Clutch Servicing
5.5 ITEM NO. 505: HVAC Systems Pressure Test
5.6 ITEM NO. 506: Machinery Space Bilges Preservation
5.7 ITEM NO. 507: Side Scan Sonar Winch System Replacement
5.8 ITEM NO. 508: Fiber Backbone Cabling Upgrade
5.9 ITEM NO. 509: Dial Telephone (Voice) and LAN (Data) System Modifications
5.10 ITEM NO. 510: Bridge Gyro System Replacement
5.11 ITEM NO. 511: Gyrocompass Repeater Replacement
5.12 ITEM NO. 512: Stateroom 01-34-4 Conversion
REFERENCES
Page | 6
1. SCOPE
1.1 These Detail Specifications contain the requirements for drydocking and general repairs on the NOAA Ship Thomas Jefferson (formerly USNS Littlehales, T-AGS 52, Hull 1169).
1.1.1 The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of research vessels that supports research and mapping for the National Marine Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provides support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful. At the end of each sailing season the vessels enter a repair period (drydock or dockside) to address repairs that have been previously identified, perform upgrades to mission systems or ship systems that either extend the life of the ship or provide new data collection capabilities or for safer operations of ships systems as well as address any emergent work that would adversely affect the ships ability to safely perform its mission on schedule , while meeting all regulatory body requirements (American Bureau of Shipping and United States Coast Guard) and all habitability requirements, including any that may be required as a result of contracts for personnel to augment ship staff.
1.1.2 The work items in the repair specification are identified well in advance of the performance period in order meet the contracting lead times. Additional work items (emergent work) may arise during the period between the work package submittal, contract award, or even prior to the start of or during the contract performance period. In accordance with Commerce Acquisition Regulation (CAR) clause 1352. 271- 72, the Contracting Officer may order additional changes during the contract period of performance to address any additional work items identified as necessary to ensure the intent of the drydock or dockside repair contract is met; that is, that the vessel shall be able to safely perform its mission, that it will meet all habitability requirements and regulatory body requirements, and that such repairs will be timely performed to ensure to the maximum extent practicable that the ship's schedule is not adversely impacted.
Page | 7
2. GENERAL
2.1. References
2.1.1. NOAA Standard Specification 000-1H, “General Requirements for Ship Repair Contract Work on NOAA Ships”
2.1.2. NOAA Standard Specification MOC-631-2D, “Coating Systems for Steel Surfaces”
2.1.3. NAVSEA Standard Item 009-32, “Cleaning and Painting Requirements: Accomplish”
2.1.4. NOAA Ship Thomas Jefferson drawing TJ-085-002G, “Booklet of General Plans”
2.1.5. NOAA Form 57-17-09, Hot Work Permit
2.1.6. NOAA Standard Specification 000-2D, “Temporary Services at Contractor Facilities”
2.1.7. NOAA Standard Specification 997-1B, “Drydocking and Routine Drydock Work”
2.1.8. ABS Marine Vessel Rules
2.1.9. NOAA General Technical Requirements
2.1.10. NOAA Standard Specification 630-1, “Preservation of Ship Structures”
2.1.11. NOAA Standard Specification MOC-635-1, “Thermal Insulation for Piping”
2.1.12. NOAA Standard Specification AMC-635-2, “Thermal Insulation for Compartments”
2.1.13. NOAA Standard Specification MOC-300-3, “General Requirements for Electrical/Electronic Items”
2.1.14. NOAA Standard Specification AMC-634-1A, “Deck Coverings”
2.1.15. NOAA Standard Specification AMC-505-2, “Hydrostatic Pressure Tests”
2.1.16. Weight Report
2.2. Government-Furnished Material
2.3 Requirements
2.3.1 The period of performance is August 8, 2023 – January 21, 2024.
a) Start of production execution begins November 6, 2023 through January 21, 2024.
b) Contractor shall hold an onsite post-award kick-off meeting with the COR seven
(7) days after contract award.
c) Contractor shall assign a Project Manager who will be the primary point of contact for the contract within seven (7) days to the COR.
d) Contractor shall hold a monthly status meeting beginning the month after the post-award kick-off meeting with the COR until the actual start of production on November 6, 2023. After which, weekly progress meetings will commence.
e) The performance period is currently scheduled to cross the Thanksgiving and
Page | 8
Veteran’s Day holidays. During the week leading up to Thanksgiving Day, there will be limited NOAA support and onboard hot work will be restricted. The period of performance has already taken into account the limited NOAA support and onboard restriction during this period is not a justification for a contract extension.
f) Weekly progress meetings will commence after the first full week of production.
The assigned Project Manager shall be present during this meeting to discuss the actual progress, material statuses, weekend work, schedule updates, and etc.
2.3.2 Include in the Production Schedule work that requires the contractor’s presence (competent person) and other work the contractor desires to accomplish during the week that contains Thanksgiving Day and Veteran’s Day.
2.3.3 Contractor shall provide a Project Coordinator or equivalent delegated employee to be onsite at all times Contractor or sub-contractor personnel are working on the vessel.
Project Coordinator shall oversee the execution of all ongoing work, including sub-contractor work, and shall serve as a point of contact on the vessel to coordinate between COR, Ship’s Force, Contractor, and sub-contractor personnel.
2.3.4 Review and have all subcontractors regardless of tier review all work items under this contract to determine the interrelationship/interdependency between each of the work items. Many of the definitions relating to performance of these work items are found in references included in each work item.
2.3.5 Reference 2.1.1 forms a part of these Detail Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.
a. Provide an electronic copy, in Adobe Portable Document Format (PDF), and two hard copies of all Condition Reports.
b. Include in the Safety Plan detailed procedures for the following:
1. Confined and Enclosed Spaces and Other Dangerous Atmospheres – All confined spaces must be considered to have a hazardous atmosphere until demonstrated to be safe via testing by the Competent Person. Confined spaces may contain high concentrations of harmful gases and other environmental conditions that can cause injury, illness, or death. Include in this section the procedures for personnel to enter and work within confined spaces.
2. Control of hazardous energy (lockout/tagout (tags-plus)) – All machines, equipment, and pressurized systems are to be isolated from their energy source and at a minimum tagged out in addition to locking out (if the equipment can be fitted with a locking device) before any servicing or repair work is performed where the unexpected start up or release of energy could cause injury or death. In addition, lockout/tagout shall be used whenever personnel are required to remove a guard or other safety device or required to place any part of personnel’s body in a danger zone of any machine, equipment, or system. Include in this section the procedures for lockout/tagout for servicing of
Page | 9 machinery, equipment, and systems when the energization or startup of machinery, equipment, or systems, or the release of hazardous energy, could endanger personnel.
3. Hot work Operations –
a) Include in this section the procedures used for preparing for hot work including Marine Chemists and Competent Persons requirements, notifications of hot work operations, fire prevention during hot work operations and fire prevention after completion of hot work operations. Procedure must meet or exceed the requirements of reference (2.1.5).
b) Use reference (2.1.5) for identification of hot work. Ship’s force will be available to verify and sign completed copies of reference (2.1.5) at the beginning of each day hot work is anticipated.
4. Fall Protection – The ship is equipped with systems to protect personnel from falls during normal operations. Include in this section temporary safe guards, systems, equipment, restraints and/or procedures used to protect personnel from falls during accomplishment of work required by these Detail Specifications.
c. Definition of terms as related to drawings:
1. As-built drawing – A drawing that reflects the as-constructed conditions of the system. As-built drawings include current and previous undocumented changes to the system.
2. Develop ACAD “As-Built” drawing – Convert the drawing from the provided format and create in an ACAD format.
2.3.6 Project Schedule - Provide an electronic copy, in Adobe Portable Document Format
(PDF)
a. Develop and maintain a Project Schedule for the work required by this specification using a Gantt chart format.
b. Include the following minimum information in the Project Schedule for each Work Item:
1. Major tasks within each Work Item
2. Planned start and completion dates for all tasks
3. Actual start and completion dates for all tasks
4. Milestones
5. Critical path
c. Keep the schedule current with schedule modifications and completed tasks.
Submit the Project Schedule weekly along with the Progress Report. The provided information will be used to evaluate overall progress.
2.3.7 Prepare and submit daily a Plan of the Day (POD), in Adobe Portable Document
Page | 10
Format (PDF), identifying by work item anticipated work that will be accomplished onboard the ship that day, attending subcontractors, and areas of hot work.
2.3.8 Maintain a Quality Assurance (QA) Test and Inspection Plan applicable to all work items, including all additional work items which are authorized by the Contracting Officer.
The form shall include the following minimum information for each work item and additional work item:
• Specification item and paragraph number
• Component/Equipment name
• Test or Inspection description
• Acceptance Criteria
• QA Inspection Report
2.3.9 Develop and maintain a separate Test Schedule.
2.3.10 Develop, in consultation with the local attending ABS Surveyor, a written ABS Survey Schedule that lists the items to be inspected and the scheduled dates and times of the inspections. The ABS survey schedule shall list all initial inspections required by the ABS Surveyor. Submit the ABS Survey Schedule to the COR within 48 hours after the start of the contract performance period and update weekly at the Progress Meeting.
2.3.11 Provide a copy of ABS approved welding procedures and active welder certificates prior to starting any work. Update the active welder certificates throughout the contract performance period as changes occur.
2.3.12 Unless otherwise stated in these work items, prepare and coat all new steel, disturbed, or otherwise required painted surfaces in accordance with reference 2.1.2. If no paint system is identified in the item, apply the appropriate coating system to the area being coated as identified by paragraph 5.2 of this reference except that the topcoat color shall match the surrounding area. Reference 2.1.2 may be amended with reference 2.1.3 when approved by the COR.
a. For all surface preparation and coating applications, use contractors and subcontractors who have current and active QP1 certification. Provide copies of QP1 certificates
b. Maintain environmental records for days when coating systems are applied.
Obtain environmental readings prior to application of any coating and at maximum of 1-hour intervals during application of the coating.
2.3.13 Weight Report: Weigh all materials and items removed, installed, or relocated on the ship using reference 2.1.16. Provide a summary report to the COR indicating the total weight in pounds of the item and a breakdown of their locations by space, deck, frame, distance from centerline, and height off of the deck.
2.3.14 The cleanliness of the ship at the time of redelivery to NOAA shall be equal to or better than the cleanliness of the ship at the time of delivery to the contractor. Digital
Page | 11 documentation may be helpful to validate existing conditions prior to commencing any work.
2.3.15 NOAA Ship Thomas Jefferson is ABS Classed. All fabrication and materials are to be in accordance with reference 2.1.18 so as to retain her ABS Class.
2.4 Deliverables
2.4.1. General – Condition Reports
2.4.2. General – Project Schedules
2.4.3. General – Progress Reports
2.4.4. General – List of Contractor’s Supervisors
2.4.5. General – Safety Plan (see requirement in reference 2.1.1)
2.4.6. General – Gas Free Certifications (see requirement in 2.1.1)
2.4.7. General – Completed NF 57-17-09, “Hot Work Permit (Multiple) (see requirement in references 2.1.1 and 2.1.5)
2.4.8. General – Hazardous Material List and MSDS
2.4.9. General – Plan of the Day (Daily)
2.4.10. General – Quality Assurance Test and Inspection Plans (s)
2.4.11. General – Test Schedule (s)
2.4.12. General – ABS Approved Welding Procedure
2.4.13. General – ABS Approved Welder Certificate (s)
2.4.14. General – ABS Survey Schedule (s)
2.4.15. General – QP1 Certification (s)
2.4.16. General – Coating Environmental Report (s)
2.4.17. General – Weight Report
2.5. Notes
2.5.1. Hazardous Materials:
a) NOAA Ship Thomas Jefferson was constructed between 1988 and 1991. There was no asbestos used during the construction and any asbestos requirements contained in the referenced Standard Specifications do not apply.
b) Several items in this specification require gas freeing of tanks, in order to accomplish the required work. Prospective bidders should be careful not to duplicate the costs of gas freeing where tank(s) are required to be gas freed to perform work in more than one item.
c) The contractor is responsible for the control, handling, and disposal of any hazardous materials generated during accomplishment of this contract.
Page | 12
d) Ensure COR and/or Ship’s force are provided SDS for ALL cleaning, prep, and/or coating products brought on board by contractors
2.5.2. NOAA Reference 2.1.4 was used in the id identification, location, and naming of spaces within these Detail Specifications. Even though reference 2.1.4 has been modified since construction, differences still exist.
2.5.3. Ship’s force may schedule work items to be accomplished by ship’s force concurrent with these Detail Specifications. Ship’s force work items will be scheduled and coordinated with the contractor to not interfere with the work required in these Detail Specifications.
2.5.4. Ship Safety Procedures. NOAA Ship Thomas Jefferson has her own safety procedures to include Confined Space Entry Program, Lockout/Tagout, Hot work Operations, and Marine Operations Fall Protection Program. Ship’s force will continue to use the ship’s safety procedures during accomplishment of ship’s force work items.
2.5.5. Ship’s force is scheduling to demobilized from their last mission at the beginning of the shipyard availability and mobilize for their next mission at the end of the shipyard availability. Anticipate additional ship’s force activities during these times.
2.5.6. Habitability
a) The ship shall be deemed uninhabitable when any one or a combination of the following conditions exist and it is impossible for management to correct the problem in a timely manner (4 hours or as noted below):
1. Heat and/or air conditioning is not furnished.
2. Potable water (hot or cold) is not provided for a period of 12 or more consecutive hours.
3. When a working toilet, shower, and sanitary drainage are not furnished.
4. At all times when the vessel is in drydock overnight, unless the ship is fully habitable with all facilities including heat and/or air conditioning, lights, hot and cold running water, shower and sanitary facilities (working toilets and sanitary drainage). Portable toilets do not meet the requirements for sanitary facilities.
5. Work such as such as chipping, welding, riveting, hammering and/or pounding, or other noises of a similar nature are being performed in or around vessel personnel quarters or noxious fumes are present that disrupts the employees’ ability to rest for more than three (3) hours. Note:
Wage mariners not assigned to a watch, are assigned to work during eight
(8) hours of duty between 0800- and 1700-hours Monday through Friday.
6. Flooding of quarters or common areas due to bilge or sewage backup not repaired within 24 hours.
b) When a vessel is in port and declared uninhabitable, no employee will be allowed to live on board. Individual quarters may be deemed uninhabitable when the respective quarters have been painted, the paint is not absolutely dry, and other suitable
Page | 13
E quarters are not furnished aboard. It is also not intended that any wage mariner shall be assigned to sleep in a flooded berthing area.
2.5.7. Shipcheck: Contractors are encouraged to review ship’s drawings and are expected to attend the Thomas Jefferson’s pre-bid inspection to inspect the locations and shipboard conditions of the work items in this package prior to submitting a bid proposal. This inspection should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the sites during the pre-bid inspection constitute grounds for growth work, change order or claim after contract award.
a) The date of the shipcheck will be within 1 week of the solicitation or during during the ship’s inport period. Location will be in Galveston, Texas and at the expense of the contractor.
2.5.8. Much of the ship’s original paint contains zinc chromate. Contractors will encounter this paint during the work aboard the vessel and should take this into account when preparing their bid as it relates to the necessary work required to accomplish the specific tasks.
2.5.9. The contractor and all subcontractors, regardless of tier, shall review other work items under this contact to determine their effect on each other.
2.5.10. The following general characteristics of the ship are provided for information:
ABS Class Number...9105067 Delivery Date….01 Dec 1991 Length Overall.........208 feet Beam (Molded)...........45 feet Propulsion.............Diesel, single screw Cruising Speed..........12 knots Electric Service.......345 KW, 225/450 volts AC Officer size Crew size ABS Class Notations.... ✠A1, ,✠AMS, ✠ACC
End of Item
Page | 14
3. BASE ITEMS
3.1 ITEM NO. 301: Temporary Services
3.1.1 Abstract – This item covers the requirements for providing temporary services during the contract period of performance at the contractor’s facility.
3.1.2 References
a) NOAA Standard Specification 000-2D, “Temporary Services at Contractor Facilities”
3.1.3 Government-Furnished Material
a) None.
3.1.3.2 GFM Support
3.1.3.2.1 Receipt of Material Requirements
a) The Contractor shall receive all GFM listed in this work package, whether on board the ship or delivered to the Contractor by common carrier, or other means.
b) The Contractor shall inspect the GFM at the time of receipt and verify that the material received is the same as that indicated on the GFM listing. Any physical / visible damage or defects to the equipment / packaging will be noted on the carrier’s Bill of Lading or Delivery Confirmation to include obtaining a printed name and signature of the individual transferring custody indicating acknowledgement of condition at time of delivery. The Contractor shall immediately notify the COR of the condition and schedule a joint surveyed with the COR.
c) Contractor receiving report which notes discrepancies of document observed damage to the GFM will only be signed by the COR if the COR concurs that the discrepancy/damage was not the result of Contractor negligence.
3.1.4 Requirements
3.1.4.1 Provide all temporary services required in accordance with reference (a).
3.1.4.2 The following additional information and requirements apply:
3.1.4.2.1 Electric power: Provide and maintain 400 amps, 60 hz, 460 volts ac, 3 phase electrical shore power services. Estimated demand load is 250 amps average when the ship is habitable. The ship’s two receptacles are for NATO (Joy type) plugs rated at 400 amps each. Ship’s force will identify which of the ship’s receptacles to connect to for this availability at the time of hookup.
3.1.4.2.2 Telephone Service: Not required. High-Speed Internet Service: Provide high-speed, broadband internet connectivity via a local Internet Service Provider (ISP), or privately owned, internal internet connection. High-speed, broadband internet is defined as
Digital Subscriber Service (DSL), Cable Network, or Fiber Optic Network services with minimum download speeds of 50 Mbps and upload speed of 10 Mbps. The service provided shall be a business- type account that supports Virtual Private Network (VPN)
Page | 15 connections.
Provide the proper number of connections necessary to satisfy the ship’s wet berth and drydock locations, as well as the ship and COR’s dockside office space(s). All necessary cabling, DSL or cable modem(s), or fiber translators shall be provided for an RJ-45 network connection to the ship and office(s) routers. Provide a minimum of one Internet Protocol (IP) address with Directory Name Server (DNS) service for each of the ship and dockside office(s) locations. The ship’s electronic technician (ET) will provide the necessary routers and switches needed. Wifi Internet shall also be provided in the office spaces.
3.1.4.2.3 Steam: Not required.
3.1.4.2.4 Toilet Facilities: Required during the uninhabitable period. Include a hand washing station that is serviced daily.
3.1.4.2.5 Parking Spaces: Provide parking spaces for eight vehicles. Provide the following labels for the parking spaces:
a) 3.1.4.2.5.1 One each: “NOAA – COR”
b) 3.1.4.2.5.2 One each: “NOAA – CO”
c) 3.1.4.2.5.3 One each: “NOAA – CME”
d) 3.1.4.2.5.3 Five each: “NOAA”
3.1.4.2.6 Dockside Office Space: Three Office Spaces plus a Common Space for the crew.
Two office spaces to include ten chairs and power receptacles for five remote workstations (laptops) and three admin machines and 1-2 printers that NOAA will setup. The Common Space to include a full size refrigerator, tables with chairs, drinking water service with dispensing of hot and cold water (a bathroom sink is unacceptable), and power receptacles for a microwave and coffee pots. Provide an additional drinking water service onboard the ship.
a) Provide janitorial services to empty the wastebaskets on daily basis, clean office facilities twice weekly, clean bathroom daily, and mop the floor on a weekly basis.
3.1.4.2.7 Security Services: Required from and including November 6, 2023 to and including January 21, 2024.
Provide onboard Security Service from 1600 to 0800 on weekdays and 24 hour on-ship security on weekends and federal holidays. In addition to reference (a) requirements, increase security round frequency from two-hour intervals to one-hour intervals from 1600 to 0800 on weekdays. Additionally, the contractor shall provide 24 hour on-ship security during weekends and holidays, and security rounds should be completed every hour. Performance standards for security members are as follows:
a) Training and vessel familiarization will be provided by the ship’s officers or designated crew members for the security watch supervisor and one initial group of security watch standers. Watch standers must be in uniform or a safety vest that identifies them as a security watch stander. Watch standers are for security and must be unarmed.
Page | 16
The company must have Security Guard Credentials, Certifications or Licenses; individual guards do not. Security watch standers will present themselves for their watch in sufficient time to be briefed on any changes to the routine or special instructions from the off going watch. Approximately 10-15 minutes may be required to exchange the watch and transfer information. Security watch standers will not depart the ship without being properly relieved following their watch.
b) The security watch standers shall provide hourly security rounds, inspecting all spaces of the ship, excluding staterooms.
Specific stations will be set up with Detex security stations, which will be logged using a ship provided Proxipen security wand. The security watch standers are required to contact the designated Officer of the Day (OOD), duty engineer or CO if any unusual events occur.
Unusual events are defined as, but not limited to: bridge alarms, fire, flooding, unauthorized personnel boarding, and other dangers that can affect the security and safety of the vessel, or spills affecting the marine environment. Security rounds and all unusual events shall be noted in the vessel’s watch stander log. Security watches shall be attentive to the responsibilities of their position and should limit the use of their personal phones to emergencies and duties related to their security detail. Perceived excessive use of phones during security watches will asked to be investigated by the contractor by the COR.
3.1.4.2.8 Air: Provide 32 CFM (minimum), 125 psi dry, filtered compressed air connected to the ship's service airline on the Main Deck.
3.1.4.2.9 ABS Surveyor: Schedule the services of an ABS Surveyor as required by ABS for performing inspections of all new installations, modifications, and tank inspections. NOAA will pay for all normal ABS surveys and surveys associated with the work required by these specifications. The contractor shall provide a credit for any additional ABS charges associated with rescheduling of surveys and rework surveys which are directly under the control of the contractor.
3.1.4.2.10 Crane Service: Provide crane operator and riggers for ship's force equipment and material lifts needed during normal working hours. Provide crane lifts with a 5-ton minimum capacity. The COR will provide a minimum of four hours’ notice prior to any lifting required for ship’s force needs. For bidding purposes, assume 5 lifts with the crane each week.
1. Additional Crane Services: Provide 30 hours of crane service for loading /offloading ship’s supplies and equipment.
a) Ship’s force will pack and unpack the storage unit.
b) Only ship’s force will be allowed access to the storage facility.
3.1.4.2.11 Cooling Water: Provide 300 gpm @ 100 psig capacity, for ship’s auxiliary sea water system which supports all refrigeration plant cooling water, air conditioning plant cooling water, and sanitary system toilet flushing needs (NOTE, the ship’s sea water system provides 600 gpm for full load – engines running). In the event the sea water or cooling water provided to these systems is disrupted or disabled, an alternate means of providing
Page | 17 water service to these systems shall be the Contractor’s responsibility. Provide a pressure regulator on the discharge side of the Contractor’s cooling water supply to the ship’s systems capable of regulating pressure between 25 psig and 80 psig. Contractor may provide separate cooling water service connections to meet the ship’s cooling water systems needs at designated hook-up locations. See ship’s Chief Engineer for individual cooling water service hook-up locations and pressure requirements for the separate systems. Make-up temporary by-pass hose and/or piping arrangements to support the ship’s AC, firemain and refrigeration plant cooling water needs, in conjunction with the work requirements of other items in these specifications.
3.1.4.2.12 Protective Covering: In addition to the protective coverings specified in paragraph 4.5.1 of reference (a), place a layer of heavy duty (minimum thickness of 4 mils) plastic sheeting between the deck and the protective covering of all habitable spaces were contractors will transit or work.
a) 48 hours prior to completion of the contract repair period, remove temporary deck covering.
b) Wash all non-carpeted decks that were covered with temporary deck covering including each decks’ passageway and the Ship's Mess.
c) Steam clean all carpets that were covered with temporary deck covering.
3.1.4.2.13 Drinking water shall be provided aboard the ship in the mess deck, inside the COR and Ship’s dockside offices. Water dispensers for drinking water shall be capable of dispensing cold and hot water in each location. A minimum of 10 gallons of reserve drinking water shall be in each location at all times to prevent running out. Biodegradable disposable cups for hot and cold water shall be provided in both locations.
3.1.4.2.14 Provide the following safety equipment:
a) Five (5) ea. Hard hats
b) Five (5) ea. Safety glasses.
c) 200 pack of EARsoft yellow neon corded earplugs, or equivalent – NRR 33 dB.
3.1.4.15 Trash and Garbage Disposal: Provide a receptacle within 100 feet of the gangway for disposal of ships garbage and refuse. This container shall be emptied as required. The contractor shall clean up dirt and debris incidental to shipyard work on board daily and remove same from the ship.
3.1.4.16 Gangways: Two suitable gangway or ladder shall be provided while the ship is drydocked or berthed at the yard. Safety nets will be provided at all gangways. One gangway shall be located forward and the second aft.
3.1.4.17 Fire Protection: All times when the ship is pierside or on drydock in the Contractor’s facility, provide 2 each charged fire manifolds each served by 2-1/2- inch hose shall be located on the foredeck and fantail. Provide firefighting water at 100 PSIG and 400 GPM to the manifolds. Each manifold shall be fitted with enough 1-1/2” hose to reach any space on the Ship. Each fire hose so supplied shall be fitted with fog fire nozzle.
Page | 18
3.1.4.18 Sewage Disposal: Provide a shore connection for disposal of the Ships’ sewage.
3.1.419 Ship’s Boats: Provide covered storage on cradles or boat trailers furnished by the contractor for the Ship’s Fast Rescue Boat and the Ship’s Ambar Utility Boat for the duration of the availability. Moorage and storage facilities shall have 110VAC power available for each craft. Note: the 110VAC requires either a 30- amp or 50-amp plug-in.
The ship’s boats require access to stable power to preserve battery life.
3.1.4.20 Pump, clean and maintain dry the Main Engine Room and Shaft Alley bilges.
Dispose of up to 8,000 gallons of oily bilge water. Main Engine Room and Shaft Alley bilges shall be cleaned free of oil, sludge or other liquids, dirt, rags, foreign material and industrial debris and maintained in this condition for the entire period the contractor is working on the ship.
3.1.4.21 Ship’s Mooring: The contractor shall provide adequate pier or dock space acceptable to the Contracting Officer for safely mooring the ship.
a) The facilities and services shall be sufficient to permit the contractor to comply with all other requirements of the contract.
b) The contract is based, in part, on information provided by the contractor during the pre-award survey regarding the pier or dock facilities which will be used to moor the ship. Unless specifically approved in writing by the COR, the ship shall not be moored at any pier or dock space other than those proposed during the pre-award survey.
c) When shifting of the ship is required, the COR shall be given a minimum of three days advance notice of the proposed shift. Shifting the ship shall be performed only during regular work days and hours except when dry docking and refloating the ship.
d) The mooring space to for the ship shall be under the complete and legal control of the contractor. If the contractor proposes to use any mooring space which is not owned by the contractor, a legally binding lease or agreement must be signed by the owner which clearly gives the contractor complete control of the mooring for the entire period of the contract, including any time extensions which may be approved by the Contracting Officer.
A copy of the agreement will be required to be submitted as part of the pre-award survey.
3.1.4.22 Transiting and Mooring Requirements:
a) Water Depths and Height Restrictions: At no time will the ship be moored at any dock or transit any waterway which has a water depth less than that required to provide a minimum clearance of one foot under the lowest underwater projection.
b) Vessel Arrival Conditions: The minimum liquid load, drafts and displacement of the ship at which the government intends to transit and arrive at the Contractor's facility will be provided upon request prior to arrival. Also included will be information concerning any changes in the ships liquid load which the Contractor will be permitted to make in order to meet the minimum underwater clearance requirements.
c) Transit Restrictions: At no time will the ship transit a waterway which has non-opening bridge or other overhead structure that would cause less than one-foot
Page | 19 clearance over the ship's highest projection. In order to permit passage of the ship under bridges or other overhead structures in the waterway, the government will lower masts which have hinged connections for that purpose. However, the government will not remove, and will not permit the Contractor to remove, any part of the ship's structure or equipment for the purpose of providing the required overhead clearance.
3.1.4.23 Provide 10 color copies of all pages of the contract specification turned over to the COR on the first day of the contract period. Specification shall be full size on 8 ½ x 11 inch and be hard covered (front and back) - spiral bound book.
3.1.4.24 Provide the COR a mailing address at the shipyard for the ship’s crew and COR to send and receive mail.
3.1.5 Quality Assurance
a) No additional requirements.
3.1.6 Notes
3.1.6.1 Contractors are encouraged to review ship’s drawings, reference documents and submit written questions requesting any needed additional details, photos, or measurements necessary to provide an accurate bid package prior to submitting a bid proposal. These questions should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to submit questions constitute grounds for growth work, a change order or claim after contract award.
Page | 20
3.2 ITEM NO. 302: Dry Docking and Routine Dry Dock Work
3.2.1 Abstract: This item provides the ship specific requirements for routine and additional work to be accomplished while the ship is hauled.
3.2.2 References
(a) NOAA Standard Specification 997-1B, “Drydocking and Routine Drydock Work”
(b) NOAA Ship Thomas Jefferson drawing 161-6634743, “Shaft Strut”
(c) NOAA Ship Thomas Jefferson drawing TJ-562-001A, “Rudder Arrangement and Details”
(d) NOAA Ship Thomas Jefferson drawing 243-6634740, “Propeller Shafting, Arrangement and Details”
(e) NOAA Ship Thomas Jefferson drawing 801-6634640, “Hull Lines”
(f) NOAA Ship Thomas Jefferson drawing 801-6634641, “Table of Offsets”
(g) NOAA Ship Thomas Jefferson drawing TJ-568-004D, “NOAA Ship Thomas Jefferson Bow Thruster Installation”
(h) NOAA Ship Thomas Jefferson drawing 245-6634744, “Propeller Diagram”
(i) NOAA Ship Thomas Jefferson drawing TJ-079-03, “Trim & Stability Booklet”
3.2.3 Government-Furnished Material
a. One box: HSS-GF0-HPMP-1 High Performance Marine packing; (Estimated value $1,500)
3.2.4 Requirements
3.2.4.1 Prior to hauling the ship, prepare a Liquid Transfer/Removal Plan (Plan) containing comprehensive procedures for transfer and removal of all liquids loads. Include the quantities and location of transfer liquids between tanks, the quantities and location of liquids to be removed, quantities to be stored off the ship, estimated quantities to be disposed of and quantities and locations to be returned. The dockmaster shall approve the Plan if there are plans to transfer liquid loads while the ship is on blocks. Submit a copy of the Plan to the COR at least 3 work days prior to hauling the ship.
3.2.4.2 Provide dry-docking and routine dry-dock work in accordance with GENERAL Section reference 2.1.4 and reference (a).
3.2.4.3 The following additional requirements apply:
1. Haul the ship within 72 hours of arrival at the contractor’s facility.
2. The minimum acceptable forward and after drafts and corresponding displacement tons permitted to dry-dock the ship consistent with safe stability and structural integrity are as follows:
a) Fwd = 10 feet - 3 inches
Page | 21
b) Aft = 10 feet - 9 inches
c) Displacement ≈ 1440 LT
3. Haul the ship in position 2 at a minimum keel block height of 5 feet.
4. After positioning and before hauling the ship, conduct a diver’s inspection of the underwater keel blocks positions relative to the centerline multi-beam dome to verify that the keel blocks will not come in contact with the dome.
a) When the vessel is set on the keel blocks, prior to lifting it out of the water, have divers ascertain that the bilge blocks are contacting the hull properly and not landing on any underwater appendages or in between frames. The divers shall inform the Dockmaster and COR and then lifting shall continue.
1) The COR shall be given a radio used by the divers and dockmaster to listen to communication during the docking and undocking.
5. Record inspection results on the attached NOAA DOCKING REPORT S0700/SWB997 in lieu of Docking Report form 2410.
6. Additional requirements for the propeller:
a) CLEANING AND POLISHING: Clean and polish forward and after surface of the propeller blade tips between 0.7 and 1.0 radius lines and the leading edges of the propeller blades over 0.2 of the blade width to a finish equal to the “B” specimen of the Rubert Comparator having a roughness average (RA) of 76.8 micro-inch. The remainder of the propeller blades shall be polished to a finish equal to the “C” specimen of the micro-inch.
b) Measure and record the following data on the propeller:
1) Pitch of each blade at 0.7 radius, and 0.9 radius.
c) Read and record all data stamped on the propeller to include
1) Diameter
2) Manufacturer and propeller number
3) ABS number(s)
4) Weight
7. Additional requirements for the bow thruster:
a) CLEANING AND POLISHING: Clean and polish to a finish equal to the “C” specimen of the Rupert Comparator having an RA of 188.0 micro-inch.
8. Renew the zinc anodes located in the three sea chests. Note: scrap the existing.
Clean, prime and paint the areas behind the anodes per [(Item 3.6) - Underwater Body Coating- Maintenance] prior to installing the new anodes.
Page | 22
a) New anodes shall be equivalent in size and installed in the same locations as those removed.
b) After completion of anodes renewals, visually inspect each new anode with the COR to determine proper attachment, and to ensure that the anodes were not painted during the painting of the hull.
9. Install GFM packing for the tailshaft and rudder post instead of the “TFE-impreganted square flax packing”, as required in reference (a), para 3.8.
3.2.5 Quality Assurance
3.2.5.1 Inspect the condition of the dielectric Capastic shield around the four cathodic protection anodes and identify repair areas in lots of 10 square foot sections.
3.2.6 Deliverables
a) Docking Report S0700/SWB997
b) Propeller Inspection Data
3.2.7 Notes
3.2.7.1 References (b) through (i) are listed as sources for obtaining information.
3.2.7.2 Intersleek 1100SR with a final coat FXA992-Blue is an approved coating system for all transducer faces.
3.2.7.3 Contractors are encouraged to review ship’s drawings, reference documents and submit written questions requesting any needed additional details, photos, or measurements necessary to provide an accurate bid package prior to submitting a bid proposal. These questions should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the
Page | 23
3.3 ITEM NO. 303: Dock Trials
3.3.1 Abstract – This item provides the requirements for support for a dock trial of the ship to verify completed work.
3.3.2 References
a) None.
3.3.3 Government-Furnished Material
a) None.
3.3.3 Requirements
3.3.3.1 Develop a written test procedure to accomplish the work required by this work item and thoroughly test and evaluate all work completed by these Detail Specifications.
Provide the test procedure to the COR, for review, at least two weeks prior to the scheduled dock trials. The written test procedure shall include the following:
1. List of equipment and systems to be tested
2. List of tests
3. Test performance criteria
4. Test acceptance criteria
5. Test schedule
6. Test data to be recorded
7. Test data recording format
8. Instrumentation required
9. List of contractor personnel involved (including subcontractors)
3.3.3.2 Provide a “Statement of Readiness” 24 hours prior to the Dock Trials that indicates all required work is completed and the equipment is ready for dock trials in accordance with the accepted Dock Trial Plan.
3.3.3.3 Allocate eight hours for the Dock Trial
3.3.3.4 Obtain approval from the COR to accomplish any work on the ship that is not directly related to the Dock Trial.
3.3.3.5 Provide support to ship’s force to accomplish the Dock Trial test procedure as well as test run both propulsion engines, test run all three ship service diesel generators, test run the bow thruster, rotate the main shaft and propeller, and cycle the rudder. Provide the services of qualified personnel, including manufacturer’s representatives if necessary, for the duration of the dock trial.
3.3.3.6 Take immediate corrective actions to return equipment found defective during the Dock Trial to good working order prior to accomplishing the Sea Trial at no additional cost to the Government.
Page | 24
3.3.3.7 Mooring of the vessel shall be to the satisfaction of the ship’s Commanding Officer and the COR prior to conducting dock trials.
3.3.3.8 Provide extra lines for securing vessel during turning of the propeller and operation of the bow thruster.
3.3.4 Quality Assurance
a) No additional requirements.
3.3.5 Deliverables
a) Dock Trial test procedure
b) Dock Trial results
3.3.6 Notes
3.3.6.1 Contractors are encouraged to review ship’s drawings, reference documents and submit written questions requesting any needed additional details, photos, or measurements necessary to provide an accurate bid package prior to submitting a bid proposal. These questions should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the
Page | 25
3.4 ITEM NO. 304: Sea Trials
3.4.1 Abstract: This item provides the requirements for supporting a sea trial on the ship to prove completed work.
3.4.2 References
a) None.
3.4.3 Government-Furnished Material
a) None.
3.4.3 Requirements
3.4.3.1 Develop a written test procedure to accomplish the work required by this work item and thoroughly test and evaluate all work completed by these Detail Specifications.
Provide the test procedure to the COR, for review, at least two weeks prior to the scheduled dock trials. The written test procedure shall include the following:
1. List of equipment and systems to be tested
2. List of tests
3. Test performance criteria
4. Test acceptance criteria
5. Test schedule
6. Test data to be recorded
7. Test data recording format
8. Instrumentation required
9. List of contractor personnel involved (including subcontractors)
3.4.3.2 Provide a “Statement of Readiness” 24 hours prior to the Sea Trials that indicates all required work is completed and the equipment is ready for sea trials in accordance with the accepted Sea Trial Plan.
3.4.3.3 Allocate eight hours for the sea trials. River harbor, and bay transit time shall not be considered part of the sea trials.
3.4.3.4 Obtain approval from the COR to accomplish any work on the ship that is not directly related to the Sea Trial.
3.4.3.5 Provide support to ship’s force to accomplish the sea trials to prove operational of any and all individual equipment and systems to the satisfaction of Ship’s command, the Chief Marine Engineer, and the COR.
a) Contractor support shall include supervision and trades personnel associated with the major equipment/systems worked during the contract.
3.4.3.6 During the sea trials, all operating equipment and systems shall be thoroughly tested. As a minimum, the trials shall include the following:
Page | 26
a) Full speed operations of both the main and auxiliary propulsion engines.
b) Turning radius and reaction time for the steering system.
c) Propulsion control of both the main and auxiliary propulsion engines at all control stations.
d) Crash stop. Measure the reaction time and time delays in the pneumatic system during this test.
3.4.3.7 After completion of the sea trials, if any contractor worked equipment is found defective, immediate corrective action shall be taken to place the equipment in good operating condition prior to the ship’s departure at no additional cost to the Government.
3.4.4 Quality Assurance
a) No additional requirements.
3.4.5 Deliverables
a) Sea Trial test procedure
b) Sea Trial results
3.4.6 Notes
3.4.6.1 Contractors are encouraged to review ship’s drawings, reference documents and submit written questions requesting any needed additional details, photos, or measurements necessary to provide an accurate bid package prior to submitting a bid proposal. These questions should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the
Page | 27
3.5 ITEM NO. 305: Cathodic Protection: Inspect & Repair
3.5.1 Abstract: This item provides requirements for periodic servicing and repairs to the ship’s cathodic protection.
3.5.2 References
(a) NOAA Ship Thomas Jefferson drawing 633-6634726, “Cathodic Protection Elementary Wiring Diagram”
(b) NOAA Ship Thomas Jefferson drawing 633-6634907, “Cathodic Protection System”
(c) NOAA Ship Thomas Jefferson manual no. TJ-633-01, “Cathodic Protection System”
(d) NOAA Ship Thomas Jefferson drawing 633-67635, “Installation Drawing ICCP Equipment”
3.5.3 Government-Furnished Material
a) None.
3.5.4 Requirements
3.5.4.1 Perform the following work on the ship’s cathodic protection system under the on-site and off-site guidance of a manufacturer-authorized field service technician and references (a), (b), and (c):
1. Troubleshoot the reference anodes to ensure they are delivering the proper hull potential signal to the CAPAC controller.
2. Open, clean, and inspect the automatic controller and power supply for deterioration, damage, or excessive wear that may affect operation of the system. Tighten all connections.
3. Adjust the…