This document package provides details for a federal solicitation seeking drydocking services for NOAA's Ship Thomas Jefferson in fiscal year 2024. The solicitation includes statements of work, past performance questionnaires, pricing schedules, and technical references such as vessel drawings and manuals. Interested vendors are to provide pricing and past performance information for ship repair and maintenance services including hull treatments, tank and equipment testing and repairs, joinery repairs, lifesaving equipment servicing, electrical and electronic systems work, machinery repairs and testing, and other tasks by July 7, 2023. The solicitation is issued by the National Oceanic and Atmospheric Administration within the Department of Commerce.
View the file
Other files
Show 40 more
Latest 50 of 226 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
1305M223QNMAN0122
9B. DATED (SEE ITEM 11)
06/01/2023
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
2. AMENDMENT/MODIFICATION NUMBER
A0003
3. EFFECTIVE DATE
06/22/2023
4. REQUISITION/PURCHASE REQUISITION NUMBER
NM-AN2120-23-01077
5. PROJECT NUMBER (If applicable)
CODE AJ930073 7. ADMINISTERED BY (If other than Item 6) CODE 6. ISSUED BY
NOAA/EAD
200 GRANBY STREET, NORFOLK, VA 23510
Elizabeth Eichelberger, elizabeth.eichelberger@noaa.gov, (757)441-6557
See Block 6
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
15A. NAME AND TITLE OF SIGNER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE OF PAGES
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers x is extended.
Elizabeth Eichelberger
06/22/2023
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
TJ DRY DOCK FY24
Please see attachment list.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
X
1. This Amendment is issued to respond to the following questions that were received:
Question Answer (Work Item 312) WI 312 mentions servicing 6 x 25 mn Elliot liferafts. In 2022 Vane Brothers Marine Safety serviced 4 each 20mn USCG approved Elliot liferafts, 1 each 20mn USCG approved Crewsaver liferaft, 2 each 4mn USCG approved Survitec liferafts, and supplied 1 each NEW 20mn USCG approved Elliot liferaft. The first inspection will not be due until Nov 1st 2024. See the initial service date on the certificate for the NEW 20mn Elliot we provided in 2022. Can NOAA confirm that servicing of 6 x 25 mn Elliot liferafts will be required for this availability?
Contractor should see Table 312-1 added via Rev A. New Elliott liferaft will not require servicing.
(Work Item 508) Neither the specs nor the reference describes the cable types or lengths that require replacement. Will NOAA please provide cable types and approximate lengths?
Estimate qty (2) each 100 Ft runs of 24F 50/125 OM3 (OFCP PNU-ILPA) armored cabling and 1100lf - OM1 6 x 62.5/125 (series 300 orange jacket) See 5.8.4.5.
(Work Item 312) Can you send me a copy of the last inspections on these 6 rafts? or any info about them like manufacture dates what kind of equipment pack they are? Otherwise, I would have to assume that everything is expired inside and that they need to be gas inflated which could drastically swing the estimate cost.
Contractor should see Table 312-1 added via Rev A. New Elliott liferaft will not require servicing.
(Work Item 509) Please, provide 5.9.2 References- 1) NOAA Thomas Jefferson Site Survey Telephone Layout Rv (1) Zenitel 2) NOAA Thomas Jefferson2_XLS Zenitel.
Requested references attached.
(General) Paragraph 2.3.12.a on page 10, This paragraph requires QP-1 certification. If a Sub does not have a QP-1 cert but has a NACE Inspector present, would that satisfy the requirement?
A NACE inspector is acceptable.
(General) Paragraph 2.5.8 on page 13, This paragraph mentions encountering zinc chromate during work onboard the vessel, but there is no abatement requirement anywhere in the Spec.
Please clarify if abatement costs must be included in the Spec and if so, provide estimated quantities and areas.
Do not include abatement costs. Contractor may or may not encounter Zinc chromate.
(Work Item 301) Reference (a) 4.14 on page 6, is internet service required for this vessel’s availability?
Yes; High-Speed Internet Service: Provide high-speed, broadband internet connectivity via a local Internet Service Provider (ISP), or privately owned, internal internet connection. High-speed, broadband internet is defined as Digital Subscriber Service (DSL), Cable Network, or Fiber Optic Network services with minimum download speeds of 50 Mbps and upload speed of 10 Mbps. The service provided shall be a business- type account that supports Virtual Private Network (VPN) connections. Provide the proper number of connections necessary to satisfy the ship’s wet berth and drydock locations, as well as the ship and COR’s dockside office space(s). All necessary cabling, DSL or cable modem(s), or fiber translators shall be provided for an RJ-45 network connection to the ship and office(s) routers.
Provide a minimum of one Internet Protocol (IP) address with Directory Name Server (DNS) service for each of the ship and dockside office(s) locations. The ship’s electronic technician (ET) will provide the necessary routers and switches needed. Wi-Fi Internet shall also be provided in the office spaces.
(Work Item 301) 3.1.4.2.1 on page 14, How many KWH/day do you want us to include for electrical usage?
This is a standard item part of the SOW. NOAA does not dictate in the SOW the amount of KWH/day for usage but we will electrical power.
(Work Item 301) 3.1.4.2.4 on page 14, What is the length of the unhabitable period? Saw in Reference (a) one toilet required per 15 persons of ship’s on-site crew. How many crewmembers are projected to be on-site?
Estimate of 15 or less to be onsite.
(Work Item 301) 3.1.3.4.2.11 on page 16, How many tons of water do you want us to include for usage?
NOAA is unable to predict how many tons of water will be required during the duration of this contract.
(Work Item 301) 3.1.4.2.12.b and .c on page 17, How many square feet are estimated to be covered with temporary deck coverings?
Deck coverings are subjective and actual footage will be determined by the contractor. Contractor should refer to the General Booklet of Plans for spaces impacted and protect the deck prior to industrial work. Ship must be returned to condition found upon arrival save any modifications made by this SOW.
(Work Item 301) 3.1.4.18 on page 17, How many gallons of sewage do you want us to include for sewage disposal?
For estimating purposes assume 10K; this number is subjective depending on who wins the award.
(Work Item 302) 3.2.4.3.8 on page 21, Please provide the amount and the type/specs for the zinc anodes.
Estimates can't be provided. Contractor should order zincs after the ship is drydocked.
(Work Item 302) Ref A, 4.8.3.b.2 – For the part that states, “Coat all rubber-faced transducers with 2 coats of MIL-P-22298 formula 133 and 2 coats of MIL-P-22299 formula 134.” Only info I can find is that it is an antifoulant coating that contains TRIBUTYLIN, which is a heavy metal, probably outlawed, and requires a license to apply that we do not have. Please suggest an alternative.
Interlux brand INT-2002G Interlux Interprotect White Gallon kit and INT-YBD103/1 Micron CF Black Gallon are alternatives. Whites for primer and black is for the paint.
(Work Item 303/304) For the dock or sea trials, please specify which vendors must be present.
Contractor must test impacted systems and include it in their test plan with their perspective vendors. The COR doesn't dictate or know what vendors the contractor will use for the SOW but systems such as Engine Servicing EM712, Phone System Upgrades, etc. are examples.
(Work Item 306) 3.6.4.4 on page 30, Please provide the amount and the type/specs for the zinc anodes.
NOAA is unable to provide an estimate Contractor should order equivalent size and quantity as the original size of the removed zincs.
(Work Item 307) 3.7.4.4.3 on page 33, Please provide the amount and the type/specs for the zinc anodes.
NOAA is unable to provide an estimate.
Contractor should order equivalent size and quantity as the original size of the removed zincs.
(Work Item 308) Missing OEM manual referenced in 3.8.4.3.b
Spurs Prop Mounted MV-19/15 drawing attached.
(Work Item 309) 3.9.4.e on page 38, For estimating purposes, how many gallons of fuel to be stored? How many gallons of lube, hydraulic and dirty oil to be disposed? Please specify a type and amount of lube and hydraulic oil if you want those tanks refilled.
We estimate between 75,000-80,000 gal of fuel aboard when we dock. We further estimate that none of the tanks (oil) will have more than 200 gallons but refer to the Trim and Stability book attached for the tank levels and soundings.
(Work Item 309) 3.9.5.a on page 38, Can you confirm that the only tanks being air tested are the 16-fuel oil and lube/hydraulic/dirty oil tanks?
Tanks listed in 309 should be included in estimate but contractor should review all other work items in the SOW to ensure if additional tank openings are required.
(Work Item 309) 3.9.4.e.1 on page 38, Please provide a list of fuel block valves and stripping valves required for overhaul and include the valve specs (size, type, material, etc.).
COR cannot provide list of affected valves. When the tanks are opened, the actual number can be determined.
(Work Item 309) Table 309-1 on page 40, Can you confirm the DO tanks listed as 4-34-1 and 4- 34-2 are supposed to be 4-43-1 and 4-43-2?
There are no 4-34-1 and4-34-2 fuel tanks on the reference drawing (d).
See Note (g); Also, contractor shall refer to new reference (f). Reference (d) was using for obtaining information.
(Work Item 310) 310.4.1.10 on page 44, For estimating purposes, how many UT shots should be included for this paragraph?
Para 310.4.1.10 provides the number of UT shots to be taken. Actual linear footage cannot be verified until ship is drydocked.
(Work Item 310) 310.4.1.11/.16 on page 45, Please provide the amount and the type/specs for the zinc anodes.
Contractor should order equivalent size and quantity as the original size of the removed zincs.
(Work Item 311) Table 3-11-1 on page 51, What is the valve size for the grey water drain flanged gate valve (valve 39)? Please provide material descriptions of all valves where it is missing on the table. Are these valves tax exempt?
Valve size included on Rev A; On tax exemption, NOAA has no input on this, as the contractor is procuring the materials; All valves have sizes listed on the table.
(Work Item 316) Please provide a more detailed scope of work, including a more descriptive equipment listing and any system manuals. Not enough information to accurately price.
SOW is descriptive - OSHA representative should inspect and test weight handling equipment.
Suggested vendor who has performed that numerous times onboard the TJ is Tidewater Testing.
(Work Item 318) 3.18.4.1 and 3.18.4.2.1 mention to provide repairs, but do not state what repairs are required. Please provide what repairs are required.
SOW states to get an OEM to service and repair stated equipment. OEM servicing should provide necessary repairs required.
(Work Item 319) 3.19.4.2.1 on page 71, Is the 48”x24” insert on both tanks or that is the total steel to be cut-out?
48" x 24" is the total steel to be cut and inserted in way of new manholes.
(Work Item 319) What interferences are required to be removed in paragraphs 3.19.4.1.1.f, 3.19.4.2.2, 3.19.4.6.4, 3.19.4.11.
NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 319) 3.19.4.2.4 on page 71, Please provide the specs for the hatches.
Manhole hatches 20-inch round (steel ring, steel hatch) with gaskets and should be ABS approved.
(Work Item 319) 3.19.4.2.6 on page 71/72, What are the approximate sizes of the deck insert interferences to be removed.
Deck insert is 48" x 24".
(Work Item 319) 3.19.4.5.c.2 on page 75, For estimating purposes what size cut-out? Or should we wait to include any steel removal until after the UT survey?
UT report should identify areas of wasted steel if replacement is necessary.
(Work Item 319) 3.19.4.6 on page 75, For estimating purposes what size of the mast and deck should be cut-out?
The amount of steel replacement will be determined by the contractor and applicable UT shots where necessary. SOW states to remove excessive corroded steel and replace.
(Work Item 319) General Door Installation: a) Is the existing door bolted or welded to the bulkhead? B) Is the new OEM door frame same size as existing doorframe? C) Confirm new OFM door and frame is to be installed by mechanical fasteners (botling) to bulkhead?
a) welded to the bulkhead b) new is the same size as existing but may require minor modifications c) see (a).
(Work Item 319) 3.19.4.2 Ballast Tank Access: a) Structural drawing not included. Request drawing for Frame 22-30 from 14' above base line to keel.
b) Request details of equipment & interferences in way of steel renewal.
a) drawing attached. b) Some exterior interferences were shown on pictures included in SOW and NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 319) 3.19.4.3 Hand Grab Inspections and Repairs: a) Request details of equipment attached to hand grabs noted on picture. b) Request details of equipment & interferences below and in way of hand grab steel renewal.
a) Picture provided of handrails to be examined and/or removed is from existing "as built". No equipment is attached to the handrails. b) NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 319) 3.19.4.4 Hatch Removal and BERP Plate Installation: a) request hatch location. b) request details of equipment & interferences below and in way of steel renewal.
a) Hatch is on Main Deck and shown on the Booklet of General Plans. b) NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 319) 3.19.4.5 XO Stateroom Bulkhead:
a) Request steel renewal locations (s) & anticipated area allowance. B) Request details of equipment & interferences beow nd in way of steel renewal.
a) Steel renewal will be determined by the UT shots taken. b) NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 319) 3.19.4.6 Fly Bridge Main Mast: a) Request steel renewal locations (s) & anticipated area allowance. B) request details of equipment & interferences below and in way of steel renewal.
a) Contractor should plan to take UT shots to determine amount of steel wastage. b) NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 319) 3.19.4.7 Sewage Tank Shore Discharge Cofferdam Corrosion: a) Will sewage tank be cleaned gas free prior to arrival? Not on list of tanks for inspection. B) request steel renewal location (s) & anticipated area allowance.
C) request details of equipment & interferences below and in way of steel renewal.
a) Sewage cleaning and disposal is addressed in a prior work item 301. Contractor is urged to review all work items in the SOW. b & c) NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 320) 3.20.4.1.3 on page 81, What’s the length of the brake band liner?
This will be determined by the contractor upon removal; see manual listed in the work item.
(Work Item 321) Can you provide a possible source for OEM?
Possible vendors: Western Branch Diesel (757) 673-7000 or Bay Power Solutions (757) 485-0075.
(Work Item 323) Can you provide further pictures of the SSDG? Will an access cut be required for removal of the SSDG? If so, which side shell plate and how large should the cut be?
SSDG No. 1 generator pictures included in the SOW. Access cut will not be required as the generator can be rigged up through the hatch in the engine room.
(Work Item 324) 3.24.4.1.a on page 90, Is the copper tubing 1/4” or ½” that needs replacement and what length is needed for rip out/replacement?
The A/C drawing supplied identifies the actual piping to be replaced. The picture in the scope shows the piping.
(Work Item 324) 3.24.5 on page 92, Provide the number of tanks to be air tested that aren’t already being air tested in item 309.
No additional tanks other than what has been identified will require opening to accomplish this scope.
(Work Item 324) 3.24.4.1.2.b.ii. on page 92, For estimating purposes, please provide the estimated number of access cuts needed.
The actual number will or should be determined by the videoscope. If the videoscope shows blockage and/or gets hung and cannot produce a clear run of the piping then an access cut will need to be made.
(Work Item 325) Please provide the estimated number of days or manhours that the Vestdavit onsite representative quoted for this item.
Estimate 40 hours for industrial support.
(Work Item 325) 3.25.4.3 on page 94, What interferences are required for removal/reinstallation?
NOAA has no way to determine all things a contractor may determine to be an interference.
(Work Item 501) 5.1.4.3 on page 98, CG LKR (1-8-
2) please provide a square footage.
Contractor should refer to the Booklet of General Plans.
(Work Item 501) 5.1.4.4 on page 99, Stair tower (3-25-2) is not listed on drawing, please provide a square footage
Contractor should refer to the Booklet of General Plans.
(Work Item 502) 5.2.4.1.A.2 on page 105, What interferences are known for this item?
NOAA is unable to determine all things a contractor may determine to be an interference.
(Work Items 505, 507, 510) Can you provide a suggested POC to perform this work?
1) WI 505 – Suggested Vendor is Omega Marine Refrigeration, 5816 Chesapeake Blvd, Norfolk, VA 23513 (757) 469-1117.
2) WI 507 – Proposed contractor should provide the labor to accomplish the ripout of the existing Side Scan Sonar and accomplish the fabrication and install of the associated foundations. NOAA is only providing the new Side Scan Winch as GFM.
3) WI 510 - Proposed contractor should provide the labor and materials to accomplish this scope of work.
(Work Item 511) 5.11.5.6 on page 143, For estimating purposes, can you provide the type of cable and estimated length required for this item?
For the bridgewing repeater NMEA cabling, "shielded NMEA interface cabling" is required.
Estimate 100lf and refer to the Geneal Plans for frames and spaces impacted.
(Work Item 511) 5.11.4 on page 142, For the CFM required, Sperry said that the part numbers provided in the Spec are out-of-date. The provided numbers, 4422-AB and 4894-AD are sold as kit now. New part number- 074887-0000-000 (1450mm) or 074911-0000-000 (1300mm). What size do you want? 074880-0001-000 stays same except for the 0001. Do you want cover plate P/N 060227-0000-000? The provided number 2000-7 Sperry does not see in their inventory. The options they have are P/N 075135-0000-000 or 060280- 0000-000 Which one do you require? *See attached file, please provide new list of CFM with up-to-date part numbers.
074911-0000-000 for the repeater stand 1300mm 074880-001-000 for the repeater compass 60227- 0000-000 for the cover plate for the compass 60- 280 for the telescopic Alidae (or equiv. Atlas Instruments 2000-7).
(Work Item 306) NOAA Ship Thomas Jefferson drawing TJ-562-001A, “Rudder Arrangement and Details” There is a reference called 562-6634741D Rudder Arrangement and Details – is this an acceptable alternative?
TJ-562-001A attached to be used.
(Work Item 310) Thomas Jefferson – Hull Transducer Suite (Lkg Aft FY2022).
Hull Transducer Suite attached.
(Work Item 310) NOAA Ship Thomas Jefferson drawing TJ-085-002H, “Booklet of General Plans” There is a reference called TJ-085- 002G_Booklet_of_General_Plans – is this an acceptable alternative?
Reference "G" is acceptable. Rev "G" attached.
(Work Item 319) NOAA Ship Thomas Jefferson drawing 624-6634931 Rev C, “Joiner Door Schedule”.
Attached.
(Work Item 504) Lufkin Marine Gears Spare Parts List (RS2719S) drawing – LM584 Rev B.
Attached.
(Work Item 505) NOAA Ship Thomas Jefferson Diamond System Builder drawing “Thomas Jefferson HVAC System” (company proprietary).
Proposed contractor must obtain this drawing from the Diamond System Builder contractor.
(Work Item 507) NOAA Ship Thomas Jefferson drawing TJ-085-002H, “Booklet of General Plans” There is a reference called TJ-085- 002G_Booklet_of_General_Plans – is this an acceptable alternative?
Reference "G" is acceptable. Rev "G" attached.
(Work Item 510) iXBlue Quadrans Fiber Optic Gyro User’s Manual.
Attached.
(Work Item 510) iXBlue Netans N1 Technical Manual.
Attached.
(Work Item 310) Ref G. states to use latest REV, which is TJ-085-002H. Only Ref TJ-085-002G was provided. Should REV G be used for estimating? Or can NOAA provide REV H?
Reference "G" is acceptable. Rev "G" attached.
(Work Item 508) WI 508 doesn’t include any drawing references. Are there any existing drawings showing the existing Fiber backbone-network system and cabling? The work item doesn’t show a quantity of circuits to be replaced, type of ST connectors to replace, etc. Anything NOAA can provide would be helpful.
No existing drawings for this item. This is a legacy system. This will be a replacement of the existing cabling in numerous spaces throughout the ship and terminated with ST connectors.
2. The due date for the submission of quotes is hereby extended to July 7, 2023, at 10:00 am Eastern
Standard Time (EST).
3. Any suggested or possible vendors included in the answers provided are intended solely for informational purposes and do not impose any obligation or requirement to engage with or utilize these vendors.
4. Contractors are reminded of their obligation to promptly acknowledge receipt of this Amendment.
5. End Amendment 0003.
| 6 ISSUED BY CODE: | |
| AJ930073: | |
| 5 PROJECT NUMBER If applicableRow1: | |
| 8 NAME AND ADDRESS OF CONTRACTOR Number street county State and ZIP Code: | |
| undefined: | |
| 10A MODIFICATION OF CONTRACTORDER NUMBER: | |
| undefined_2: | |
| 10A MODIFICATION OF CONTRACTORDER NUMBER_2: | |
| 10B DATED SEE ITEM 13: | |
| 11 THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS: | |
| The above numbered solicitation is amended as set forth in Item 14 The hour and date specified for receipt of Offers: Off | |
| 13 THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTSORDERS: | |
| undefined_3: | |
| B THE ABOVE NUMBERED CONTRACTORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES such as changes in paying office: | |
| undefined_4: | |
| undefined_5: | |
| C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: | |
| undefined_6: | |
| 1: | |
| is not: Off | |
| is required to sign this document and return: Off | |
| 14 DESCRIPTION OF AMENDMENTMODIFICATION Organized by UCF section headings including solicitationcontract subject matter where feasible: | |
| 15B CONTRACTOROFFEROR: | |
| 15C DATE SIGNED: | |
| 2023-06-22T12:55:44-0400 | |
| EICHELBERGER.ELIZABETH.MARIE.1177422750 |