PWS_UAIB_DomeRemoval_Feasiblity Appendix D v1.0.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Radiosonde Frequency Migration Project (RFMP) Upper Air Inflation Buildings (UAIB) Feasibility Study
Solicitation number
1305M222QNWWG0480
Issued by

About this file

This combined synopsis and solicitation requests quotations for feasibility studies of Upper Air Inflation Buildings as part of the Radiosonde Frequency Migration Project. The National Oceanic and Atmospheric Administration seeks feasibility reports from contractors that will evaluate each building site, document the condition of the inflation building and radome support structures, provide removal and site restoration cost estimates, identify any electrical, grounding or lighting system modifications required, investigate for hazardous materials, evaluate equipment access needs, and research applicable local, FAA and environmental regulations. Contractors must determine if removing the radome will negatively impact building integrity or require repairs, and identify special preparation needed to access sites with heavy equipment. Feasibility studies must include labeled photos and sketches where appropriate. The NAICS code is 541330 for engineering services and there is no small business set-aside. Quotations are due by the date specified in SAM.gov.

View the file

Other files

File Type Posted
Amendment 0002.doc DOC document
Amendment 0001 Final.doc DOC document
Feasibility Study Combined Synopsis-Sol_v.1.pdf PDF
PWS_UAIB_DomeRemoval_Feasibility_Study_V1.1.pdf PDF
PWS_UAIB_DomeRemoval_Feasibility_Study_V1.0.docx DOCX document
PWS_UAIB_DomeRemoval_Feasiblity Appendix A v1.0.xlsx XLSX spreadsheet
Feasibility Study Combined Synopsis-Sol.pdf PDF
Past Performance Questionnaire.docx DOCX document
Past Performance Information Form.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 NWS - Upper Air Inflation Building Dome Removal Feasibility Study Report

Site Name:
Site Location:

Each feasibility study report shall contain at a minimum the following:

Requirements IDRequirementsResponse/ Finding/ Recommendations
B.1Describe the condition of the inflation building and the roof structure: identify any damage, corrosion, or rot that requires immediate attention or will affect the dome removal process.
B.2Configuration of the radome support structure
B.2.1Document how the radome is connected to the support structure (digital photo) and how its support structure is attached (digital photo) to the building.
B.2.2Determine if the removal of the radome will negatively impact the structural integrity of the building and roof requiring additional building repairs or modifications.
B.3Provide a recommendation and itemized cost for the dome removal and any required site restoration of Upper Air Inflation Building as well as (ground based) concrete slabs.
B.4. Configuration of the electrical system inside the radome and associated roof penetrations
B.4.1Identify the circuit breakers for each radome power circuit in the building's service panel (digital photos)
B.4.2Determine what work is required to properly remove the electrical components from the dome area (digital photos).
B.5Identify the type of roof water-proofing material used and current condition (digital photos).
B.6Condition of the roof access stairway and rooftop railings
B.6.1Determine if stairway and railings are safe to use and in good repair (digital photos).
B.6.2Provide repair recommendations and itemized cost (if applicable)
B.7Configuration of the rooftop grounding system, lightning protection system, and aircraft collision avoidance lights, if existing:
B.7.1Determine if collision lights will still be required after the overall height of the building is lowered by removing the dome.
B.7.2Document how power is provided to the collision lights.
B.8 Utilize multiple methods to identify (non-destructive and testing) structural areas where asbestos, lead paint, or other hazardous materials may be present.
B.8Method(s) Utilized for HazMat Discovery
B.8.1Location of hazardous materials (digital photos)
B.8.2Types of hazardous material
B.8.3Estimated remediation and itemized disposal costs
B.8.4Estimated length of time to complete remediation and disposal
B.9Evaluate access to the site for heavy equipment: identify special site preparation work (removal of fences, removal of structures, grading, road reinforcement, etc.) that will be required to get large vehicles (cranes, semi-trailers, etc.) near the Inflation Building.
B.9.1Equipment rental type
B.9.2Estimated itemized rental cost
B.9.3Estimated duration of rental(s)

B.10 Investigate if the site is subject to any restrictive local regulations that will require submitting special applications before dome removal work can proceed:

B.10.1State and local building codes, local building permits, and land use permits.
B.10.2Federal Aviation Administration (FAA) flight clearance rules. FAA Form 7460
B.10.3Environmental regulations (ie: wildlife habitat restrictions, burial site, landfill sites, etc.).
B.10.4Security access restrictions.
B.10.5Regional or site specific requirements.
B.10.6.1Permit and Fee Type
B.10.6.2Prerequisites (if needed)
B.10.6.3Estimated Itemized Cost

Note: The findings from each inspection shall be presented in a feasibility study report that will include labeled digital photographs and engineering sketches where appropriate.