About this file

Revised Attachment D, Past Performance Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Technical Contract Support for Laseriche ERMS, newest first.
File Type Posted
Amendment_0002.pdf PDF
Attachment_B_Price_Schedule_rev.xlsx XLSX spreadsheet
Attachment_A_SOW_rev.pdf PDF
Amendment_0001.pdf PDF
Brand_Name_Justification_redacted_Redacted.pdf PDF
RFQ.pdf PDF
Attachment_B_Price_Schedule.xlsx XLSX spreadsheet
Exhibit_I_Labor_Category_Description.pdf PDF
Attachment_C_-_Past_Performance_Information_Form.docx DOCX document
Attachment_D_Past_Performance_Questionnaire.docx DOCX document
Attachment_A_SOW.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 1305M2-18Q-NCNR0123

ATTACHMENT D - PAST PERFORMANCE QUESTIONNAIRE

REFERENCE CONTRACT #: ___________________________

(Contract number of the Past Performance this information is based on)

VENDOR EVALUATED: _________________________________

SEND COMPLETED QUESTIONNAIRE TO CONTRACTING OFFICER, TIFFANY SQUYRES NO LATER THAN AUGUST 21, 2018, 11:00 AM, EST AT TIFFANY.SQUYRES@NOAA.GOV.

1. QUALITY OF SERVICE

Assess the contractor’s performance to contract requirements, specifications, and standards of good workmanship (e.g. commonly accepted technical, professional, or environmental standards).

(Check the appropriate rating box.)

RATING
ADJECTIVAL RATING
DEFINITION

EXCEPTIONAL

Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.

VERY GOOD

Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.

SATISFACTORY

Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.

MARGINAL

Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.

UNSATISFACTORY

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.

Comments:

2. SCHEDULE

Assess the timeliness of the contractor against the completion of the contract, task orders, milestones, delivery schedules, and administrative requirements (e.g. efforts that contribute to or affect the schedule variance).

(Check the appropriate rating box.)

RATING
ADJECTIVAL RATING
DEFINITION

Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.

Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.

Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.

Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.

3. COST CONTROL

Assess the contractor’s effectiveness in forecasting, managing, and controlling cost.

(Check the appropriate rating box.)

RATING
ADJECTIVAL RATING
DEFINITION

Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.

Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.

Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.

Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.

4. MANAGEMENT

Assess the integration and coordination of all activities needed to execute the contract, specifically the timeliness, completeness and quality of problem identification, corrective action plans, proposal submittals, the contractor’s history of reasonable and cooperative behavior, and customer satisfaction.

(Check the appropriate rating box.)

RATING
ADJECTIVAL RATING
DEFINITION

Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.

Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.

Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.

Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.

ADDITIONAL COMMENTS, IF ANY:

Rater’s Name: ___________________________ Rater’s Signature: ________________________ Date: ____________________________________

SEND COMPLETED QUESTIONNAIRE TO CONTRACT SPECIALIST, TIFFANY SQUYRES NO LATER THAN AUGUST 21, 2018 AT 11:00 AM, EASTERN TIME:

TIFFANY.SQUYRES@NOAA.GOV