13 512-23-108 - Renovate C-Seg - Submittal Register.xlsx

XLSX spreadsheet 143 KB Posted

Attached to
Y1DA--512-23-108 - Renovate C-Segregated Compounding Area for Hazardous Compounding (CON)
Solicitation number
36C24525B0006
Issued by

About this file

This file is a Submittal Register for the VAMC C-Segregated Compounding Area renovation project (Project Number 512-23-108), managed by Alona Green. The comprehensive document details required submittals across multiple construction divisions, including Building Construction (Divisions 1-14), Building Services (Divisions 21-29), Site Infrastructure (Divisions 31-35), Process Systems (Divisions 40-48), covering a wide range of technical specifications such as shop drawings, product data, samples, certifications, and test reports.

The project is a renovation for a Hazardous Compounding Area for the Department of Veterans Affairs Veterans Health Administration, specifically within Veterans Integrated Service Network 5. The solicitation number is 36C24525B0006, and the submittal register provides a structured framework for contractors to methodically document and track technical submittals across electrical, mechanical, architectural, and infrastructural elements of the construction project. Key divisions with significant submittal requirements include Electrical (Division 26), HVAC (Division 23), Plumbing (Division 22), and Architectural Finishes (Division 9), indicating a complex medical facility renovation involving multiple technical disciplines.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building Construction Div 1-14

Project Name: VAMC C-Segregated Compounding Area
VDCI Project Number: 512-23-108
Project Manager: Alona Green
Division 1 General Requirements
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
As-Built Drawings01 00 00
Division 2 Existing Conditions
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 3 Concrete
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 4 Masonry
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 5 Metals
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 6 Wood/Plastic/Composites
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings06 10 00
Product Data06 10 00
Shop Drawings06 20 00
Product Data06 20 00
Samples06 20 00
Division 7 Thermal/Moisture Protection
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings07 92 00
Product Data07 92 00
Samples07 92 00
Division 8 Openings
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings08 11 13
Product Data08 11 13
Shop Drawings08 14 00
Product Data08 14 00
Samples08 14 00
Shop Drawings08 31 13
Product Data08 31 13
Shop Drawings08 33 13
Product Data08 33 13
Shop Drawings08 41 13
Product Data08 41 13
Samples08 41 13
Shop Drawings08 56 19
Product Data08 56 19
Samples08 56 19
Shop Drawings08 71 00
Product Data08 71 00
Samples08 71 00
Shop Drawings08 71 13
Product Data08 71 13
Shop Drawings08 80 00
Certificates08 80 00
Division 9 Finishes
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings09 05 16
Product Data09 05 16
Test Data09 05 16
Shop Drawings09 06 00
Samples09 06 00
Shop Drawings09 22 16
Product Data09 22 16
Test Data09 22 16
Shop Drawings09 29 00
Product Data09 29 00
Samples09 29 00
Shop Drawings09 51 00
Product Data09 51 00
Samples09 51 00
Shop Drawings09 65 13
Product Data09 65 13
Samples09 65 13
Shop Drawings09 65 16
Product Data09 65 16
Samples09 65 16
Shop Drawings09 91 00
Product Data09 91 00
Samples09 91 00
Division 10 Specialties
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings10 14 00
Samples10 14 00
Division 11 Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 12 Furnishings
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings12 31 00
Certificates12 31 00
Samples12 31 00
Division 13 Special Construction
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink

Yes

Division 14 Conveying Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
No

Building Services 21-29

Project Name: VAMC C-Segregated Compounding Area
VDCI Project Number: 512-23-108
Project Manager: Alona Green
Division 21 Fire Suppression
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings21 13 13
Division 22 Plumbing
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings22 05 11
Shop Drawings22 05 23
Product Data22 05 23
Shop Drawings22 07 11
Product Data22 07 11
Shop Drawings22 11 00
Product Data22 11 00
Shop Drawings22 13 00
Product Data22 13 00
Division 23 HVAC
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings23 05 11
Shop Drawings23 05 12
Certification23 05 12
Shop Drawings23 05 41
Product Data23 05 41
Load Calculations23 05 41
Shop Drawings23 05 93
Reports23 05 93
Shop Drawings23 07 11
Samples23 07 11
Shop Drawings23 09 23
Product Data23 09 23
Certifications23 09 23
Shop Drawings23 21 13
Product Data23 21 13
Shop Drawings23 31 00
Product Data23 31 00
Shop Drawings23 34 00
Product Data23 34 00
Shop Drawings23 36 00
Product Data23 36 00
Shop Drawings23 37 00
Product Data23 37 00
Shop Drawings23 40 00
Product Data23 40 00
Division 25 Integrated Automation
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 26 Electrical
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings26 05 11
Product Data26 05 11
Shop Drawings26 05 19
Product Data26 05 19
Shop Drawings26 05 26
Product Data26 05 26
Shop Drawings26 05 33
Product Data26 05 33
Shop Drawings26 27 26
Product Data26 27 26
Shop Drawings26 29 11
Product Data26 29 11
Shop Drawings26 29 21
Product Data26 29 21
Shop Drawings26 51 00
Product Data26 51 00
Division 27 Data/Telecom
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 28 Electronic Safety/Security
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Shop Drawings28 31 00
Certifications28 31 00

Site Infrastructure 31-35

Project Name: VAMC C-Segregated Compounding Area
VDCI Project Number: 512-23-108
Project Manager: Alona Green
Division 31 Earthwork
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 32 Exterior Improvements
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 33 Utilities
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 34 Transportation
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 35 Waterway/Marine Construction
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink

Process 40-48

Project Name: VAMC C-Segregated Compounding Area
VDCI Project Number: 512-23-108
Project Manager: Alona Green
Division 40 Process Interconnections
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 41 Material Processing and Handling Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 42 Process Heating/Cooling/Drying Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 43 Process Gas and Liquid Handling/Purification/Storage
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 44 Pollution and Waste Control Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 45 Industry Specific Manufacturing Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 46 Water/Wastewater Equipment
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink
Division 48 Electrical Power Generation
Submittal NumberSubmittal TypeInformational/ActionSpec SectionResponsible SubStatusDescriptionDays OutDate Received from SubDate Sent to A/E/PrimeDate Returned from A/E/PrimeDate Returned to SubRequired On-SiteLead Time (Days)Release DateCoordination Required?NotesLink

Dropdowns (DO NOT USE) Info/Action Status Coordination

Information OnlyAPPYes
Approval RequiredRRNo
AANCompleted