This is a Questions and Answers (Q&A) amendment to solicitation 12FPC126Q0025 for insulation repair and replacement work at a facility in Booneville, Arkansas.
The project requires removal of approximately 2,360 square feet of existing insulation and installation of spray foam insulation in wall and ceiling areas totaling 1,120 and 1,240 square feet respectively. The work must comply with Climate Zone 3 energy code requirements with a minimum wall R-value of R-10. No coating, barrier, or covering is required for the installed spray foam. The contractor is not responsible for mold or hazardous condition mitigation; any such work discovered during performance will be handled through contract modification. No permits, Arkansas contractor licenses, or certified payroll reports are required, though if insulation is not specifically listed in Davis-Bacon wage classifications, general laborer rates apply. The Government will provide electrical power, water, ventilation access, dumpster placement, temporary material storage, and equipment shop access during authorized work hours. A one-year warranty is required for spray foam materials and workmanship. Award is anticipated between July 27, 2026, and August 1, 2026, with Notice to Proceed issued promptly thereafter, and all work must be completed by September 30, 2026. The resulting contract will be classified under PSC Z2JZ (Repair or Alteration of Miscellaneous Buildings). Site visits are available upon request, and the stated square footages are firm quantities for pricing.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 01 - 12FPC126Q0025 - Insulation Repair and Replacement, Booneville, AR
1. Question - The Statement of Work table of contents references Climate Zone 4, while the technical requirements state Climate Zone 3. Please confirm which climate zone and energy-code requirement govern the project.
Answer – Climate Zone 3
2. Question - The wall insulation requirement states a rating of R-5/10. Please clarify the minimum required wall R-value.
Answer – R-10 minimum
3. Question - The solicitation states that the offeror, product, or service must meet a qualification requirement. Please identify the specific qualification requirement and any supporting documentation that must be submitted with the quotation.
Answer – This statement will be removed.
4. Question - Please confirm whether the installed spray foam must receive an ignition barrier, thermal barrier, fire-retardant coating, protective coating, or other covering.
Answer – No coating required.
5. Question - Please clarify the extent of mold or hazardous-condition mitigation that must be included in the firm-fixed price. If concealed mold, moisture damage, asbestos, or another hazardous condition is discovered, will the additional work be handled through a contract modification?
Answer - No mold or hazardous condition mitigation. Additional work would be handled with a contract modification, if needed.
6. Question - Please confirm whether any permits or Arkansas contractor licenses are required for this work and whether the contractor is responsible for related fees.
Answer – No permits required
7. Question - Please confirm whether certified payroll reports will be required under the Davis-Bacon requirements and which wage classifications should be used for spray-foam installers and supporting laborers
Answer - No, the job should not take weeks to perform. If insulation is not listed specifically, then general laborer.
8. Question - The SF 1449 lists a period of performance beginning July 27, 2026, which is also the quotation due date. Please confirm the anticipated award date, notice-to-proceed date, and intended performance start date.
Answer - General date for award anywhere from 7/27/2026 to 8/1/2026 and NTP issued prdomptly but must be completed by 9/30/2026. Again, not a lengthy service.
9. Question - Please confirm whether the Government will provide electrical power, water, ventilation access, dumpster placement, temporary material storage, and uninterrupted access to the equipment shop during authorized work hours.
Answer – Yes to all.
10. Question - Please identify any required warranty period for the spray-foam materials and workmanship.
Answer – 1 year warranty
11. Question - Please confirm whether the stated quantities, including approximately 2,360 square feet of existing insulation, 1,120 square feet of wall area, and 1,240 square feet of ceiling area, are firm quantities for pricing or Government estimates.
Answer – all correct square footages
12. Question - Please confirm whether a site visit is available or whether additional photographs, measurements, drawings, or building information can be provided.
Answer - Site Visit upon request
13. Question - The SAM.gov opportunity lists PSC Z2JZ, Repair or Alteration of Miscellaneous Buildings, while the SF 1449 lists PSC 5640, Wallboard, Building Paper, and Thermal Insulation Materials. Please confirm which PSC applies to the resulting contract.
Answer - PSC Z2JZ