12905B24R0007 - RFI Log_3-22-2024.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
Boiler Upgrade and Replacement
Solicitation number
12905B24R0007
Issued by

About this file

This document is an RFI (Request for Information) log related to a federal contract opportunity for the USDA Agricultural Research Service (ARS) to upgrade and replace the boiler system at the San Joaquin Valley Agricultural Sciences Center.

The RFI log details questions asked by potential offerors and the government's responses. The key details include: the requirement to potentially hold an additional site visit, questions on the scope of work for controls, piping, equipment replacement, site conditions, water treatment, and testing and balancing; the government's responses addressing these questions; and confirmation that the existing heating hot water pumps and expansion tank do not need to be replaced. The solicitation is for a Firm Fixed Price Construction Contract under NAICS code 238220 with an estimated value between $500,000 and $1,000,000. The contract is set aside for small businesses, and the requirement is to be completed by October 31, 2024.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFI #Date ReceivedDate sent to customerSpec/Drawing referenceQuestion / RFIGovernment Response
13/12/243/12/24Far 52.236-27 - Site Visit (Page 51) / Section LAccording to the RFP documents, an organized site visit is scheduled for 9:00am March 14th, 2024 at USDA SJVASC. To allow contractors who cannot make this visit an opportunity to inspect existing site conditions, will the government organize a second/follow up site visit prior to the RFI deadline?We can hold another site visit for 3/21/2024 @ 9:00AM. All RFI's due on 3/29/24 by 1600 hours. (4:00PM)
23/15/243/15/24Far 52.236-27 - Site Visit (Page 51) / Section Lpossibility of arranging an additional site visitSee RFI # 1 response above
33/20/243/20/24SOW - ControlsControls:
1)During the site visit, additional sensors for the BMS system were mentioned. Is the scope to include additional sensors? And if so, what additional sensors would you like added?Need a low water cut-off safety if not supplied with new boiler.
43/20/243/20/24SOW - PipingPiping:
SOW / 4. It states that “All new pipes shall be painted and insulated in accordance with industry standards.”Usually, the piping is insulated, and the insulation is painted. Please clarify.All piping that is not insulated shall be painted. Gas pipes do not need to be painted. All insulated pipes will be painted as industry standards require.
53/20/243/20/24SOW - EquipmentEquipment:

The existing boiler is larger than the door opening. May door and frame be removed to facilitate replacement of the boiler? During the site walk it was noted the pumps were desired to be in a lead/lag configuration. Please confirm.

After some quick calculations, the existing pumps may not be sufficient to run independent of each other. Would the government be open to including replacing with appropriately sized pumps and controlling with VFD’s?Entry door will need to be removed and reinstalled by contractor to allow for removal and installation of boilers. Pumps 9&10 have a VFD so would only need one pump running per boiler if sufficient to run only one per boiler. New electronic actuator for water flow needs to be closed when boiler is off. Need to have one boiler in a lead and the second on a lag. Second boiler starts on demand or on temp.
63/20/243/20/24SOW - Site ConditionsSite Conditions:

Can utility map outside of the boiler room be provided?

Will the shrubs be removed by USDA prior to beginning the scope? And will the Prime be responsible for replacing them?Location can provide as builds of boiler room specs. Shrubs will be removed by location prior to work beginning.
73/20/243/20/24SOW - Water TreatmentWater Treatment:
Is the current HHW loop treated on a regular basis? And if so, can a copy of the latest test results be provided? Is water treatment to be included in the scope?HW loop is treated with chemicals by location. Water treatment is not part of the contract.
83/20/243/20/24SOW - Test and BalanceTest and Balance:
Is TAB pretest and post test of the boiler to be included in the scope?Contractor should perform a Pretest and Post test of boilers to insure proper performance. To include the 4304 tunning of boilers.
93/22/243/22/24SOWThe SOW does not mention the existing heating hot water pumps and expansion tank to be replaced. Do these items need to be included in our bid?Pumps and expansion tanks are not being replaced.