This document contains questions and answers regarding solicitation number 12905B24Q0010 issued by the Department of Agriculture Agricultural Research Service for an upgrade gravel driveway and fire access road project in Davis, California. The solicitation seeks removal of 10 inches of existing base and dirt, scarification of 8 inches of subgrade, and addition of gravel to match existing grades. Contractors must contact Underground Service Alert to locate utilities and take precautions when excavating, as the site contains sanitary sewer, water, gas and sewer force mains. Bidders should confirm acceptance of a Class B or C-27 contractor's license. No traffic control is required as the gravel area will not require public or staff access during construction. The government will provide areas near the site for contractor laydown and storage but debris should be piled minimally and hauled off as removed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12905B24Q0010 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ARS-12905B
ALBANY CA 94710
800 BUCHANAN STREET
USDA ARS PWA AAO ACQ/PER PROP
12/07/20230001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/07/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Q: Can you please confirm if a Class B / C-27 Contractors License will be acceptable per
Section C.5?
A: Yes.
Q: We see a few notes about traffic control; however, this seems to be a private gravel area. Can you confirm if the public/staff will need access to the gravel area mid
Construction? Or is this implying we should have the area blocked off so public/staff don¿t accidentally drive into the area?
A: No traffic control is required.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
LAM V. PHAM
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12905B24Q0010/0001
Q: Any specific details on how the existing
V-Ditch should be protected in place? Install a layer of foam against the ditch prior to installing and compacting gravel?
A: No means or methods are specified. Contractor must take necessary precautions to prevent damage to the existing v-ditch.
Q: There are no listed slopes, I¿m assuming we are to install the gravel even against the existing gravel on the sides?
A: The end result of the project will be to match existing grades.
Q: Will the government provide us with a laydown area / storage area for skid steers, excavators, and roller compactors?
A: There are several areas near the site which can be used for laydown.
Q: The debris should be removed from the site as it¿s excavated. There are small areas to stockpile material, but they should be kept to a minimum.
A: Will there be space for the contractor to pile up debris and haul off? or is the contractor expected to haul debris as it is removed?
Q: Will any underground utilities be marked out for us?
Underground Service Alert should be contacted by the Contractor utilities in the vicinity.
Contractor should take reasonable precaution when excavating. The area contains sanitary sewer, water, gas, and sewer force mains.
Q: Can you clarify note B on A1.2? We are to remove 10" of the existing base/dirt; then
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12905B24Q0010/0001 scarify 8¿ of the subgrade meaning a total of 18¿ will be disturbed (10¿ removed; 8¿ scarifired, add water & compacted?
A: Yes, 18" total depth will be disturbed.