1282FT18R0009AME0002.pdf
PDF 131 KB Posted
- Attached to
- Fort Collins Main Building Reroofing Federal contract opportunity
- Solicitation number
- 1282FT18R0009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1282FT18R0009AME0004.pdf | ||
| 1282FT18R0009AME0003.pdf | ||
| 1282FT18R0009AME0001.pdf | ||
| Solicitation_1282FT18R0009.doc.pdf | ||
| Attachment_2_-_Drawings.pdf | ||
| Attachment_1_-_Specifications.pdf | ||
| Attachment_3_-_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1282FT18R0009
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
82FT
FORT COLLINS CO 80526
240 W PROSPECT STREET
ROCKY MOUNTAIN RESEARCH STATION
USDA FOREST SERVICE
06/27/20180002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/27/2018
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Fort Collins Main Building Reroofing
The purpose of Amendment 0002 is as follows:
Provide Questions and Answers through 07/20/2018.
Period of Performance: 08/06/2018 to 12/04/2018
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
ANTHONY O. SALAS
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Questions and Answers through 07/20/2018
Q1-The specifications are to mechanically attach the insulation into the existing 5.5” thick concrete deck, if the deck is that thick throughout then there is no concern of hitting electrical conduit mounted directly under the deck, but there must be a reason why the existing membrane roof overlay was done as a ballasted system, versus just mechanically attaching it, so do you really want all those fasteners in the concrete structure, obviously, the existing BUR roof was installed with hot asphalt and not mechanically fastened, again, do you want the insulation and cover board mechanically fastened, which, with the uplift specified will be a considerable amount at corners and the perimeter or do you want the insulation and cover board set in the manufacturers 2 part urethane adhesive which is more common with concrete decks?
A1 – The specifications for installation of the cover board and insulation will be updated to require adhesive applied, based upon discussions with designers.
Adhesive Attachment: Apply in accordance with membrane and insulation manufacturer's instructions and recommendations; "walk-in" individual roof insulation boards to obtain maximum adhesive contact.
Insulation shall be no larger than 48” x 48”.
Q2-Is the concrete deck 5.5” thick throughout the entire surface?
A2-The deck is 5.5” thick or thicker for the entire surface.
Q3-Do you want a vapor barrier, such as; Johns Manville SA Vapor Barrier and SA Primer installed over the concrete deck prior to the installation of the new insulation, which is another good practice on concrete decks?
A3- No we are not requiring a vapor barrier.
Q4-The plans show a 3” base layer of insulation with a full taper system over the base layer over the entire roof sections and crickets, please clarify that this is correct?
A4- There is a 3” base layer of insulation with taper system to roof drains, except for along North, South, and West walkway around 2nd floor (First Floor Roof) where no base layer is required in order to allow for drainage.
Q5-Do the concrete decks have any structural slope or are they flat?
A5- The concrete deck is flat.
| SF-30 |
| Questions |