Attachment 2 SOW.pdf

PDF 2 MB Posted

Attached to
GAOA Columbine Toilet Replacement
Solicitation number
1282B125R0027
Issued by

About this file

This Statement of Work (SOW) details the replacement of vault toilets at three campgrounds within the San Juan National Forest in Colorado as part of the Great American Outdoors Act (GAOA) FY25 Project. The project involves demolishing existing toilet facilities from the 1960s and installing new CXT Single Cascadian (Right Hand) vault toilets at Madden Creek, Miller Creek, and Sig Creek Campgrounds. Each site requires mobilization, demolition of the existing structure, installation of a new single-vault toilet building, and construction of a compacted 6-inch deep gravel path.

The contract period of performance is approximately June 16, 2025 to August 15, 2025. The government will provide Yale locks for installation on the new toilet facilities, while the contractor must supply their own power, water, and portable facilities for employees. The project is structured with three Contract Line Item Numbers (CLINs), one for each campground, with each CLIN including mobilization, demolition, toilet supply and installation, and gravel path construction. The project locations are in La Plata County, Colorado, with specific site directions provided for each campground, ranging from 11.6 to 39 miles from the city of Durango.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

2025 GAOA Columbine Toilet Replacement

San Juan National Forest Durango, CO

Great American Outdoors Act (GAOA)

FY25 Project

01/13/2025

Project Location:

La Plata County, CO

GAOA Columbine Toilet Replacement – FY25 San Juan National Forest

Scope of Contract

Background

Several campground toilets built in the 1960s have reached their end of useful life. These toilets can no longer meet the needs of the Forest due to either ongoing maintenance costs or a change in Forest requirements. Therefore, it has been determined that the best course of action is to demolish the existing structures and replace with new, more robust toilet systems. The new toilets are expected to meet the ongoing needs of the Forest over the next several decades.

Period of Performance

Approximately 06/16/2025 - 08/15/2025

Building Demolition, Disposal, and Installation

1. CLIN 0001: Madden Creek Campground Toilet Replacement

1) 151 – Mobilization

The Contractor is required to move personnel, equipment, material, and incidentals to the project before beginning work at the project site.

2) 203 – Removal of Structures and Obstructions

The Contractor will be required to provide all materials, equipment, and labor to pump the existing vault toilet prior to building and vault demolition. The existing building and vault are to then be completely demolished and removed from the site.

3) 637 – Facilities and Services

The Contractor will then be required to provide all materials, equipment, and labor to install a contractor supplied vault toilet. The building will be a CXT Single Cascadian (Right Hand) model or approved equal and have a footprint of approximately 14’-7.5” by 15’-2.75”, stands 11’-6” high, and contains 1 toilet. See attached 3.1 – FS Construction Drawings – FY25 – Columbine for an overview of the site, general building layout, and other details.

The Contractor will work in coordination with COR to select the color and style of the new building prior to placing the order with the manufacturer.

The Contractor will be required to install a government furnished Yale lock on all exterior doors and vault hatches of the new toilet facility.

4) 311 – Stabilized Aggregate Surface Course

The Contractor will be required to construct a compacted gravel path as specified in the attached drawings. The gravel path shall be ¾” road base material, compacted to a depth of 6” deep. The

Contractor is required to get COR approval prior to final placement of material. The approximate volume of material used for this site is 10 cubic yards.

5) Directions to Site

The site is located at the Madden Creek Campground. From the city of Durango, go west on US- 160 approximately 11.6 miles. Turn right onto County Road 124 for approximately 7 miles. The campground will be on the right-hand side of the road. The site coordinates are 37.38779, -

108.07668. See Figure 1: Map - Durango, CO to Madden Creek Campground below.

Figure 1: Map - Durango, CO to Madden Creek Campground

2. CLIN 0002: Miller Creek Campground Toilet Replacement

2) 203 – Removal of Structures and Obstructions

The Contractor will be required to provide all materials, equipment, and labor to pump the existing vault toilet prior to building and vault demolition. The existing building and vault are to then be completely demolished and removed from the site.

3) 637 – Facilities and Services

The Contractor will then be required to provide all materials, equipment, and labor to install a contractor supplied vault toilet. The building will be a CXT Single Cascadian (Right Hand) model or approved equal and have a footprint of approximately 14’-7.5” by 15’-2.75”, stands 11’-6” high, and contains 1 toilet. See attached 3.1 – FS Construction Drawings – FY25 – Columbine for an overview of the site, general building layout, and other details.

The Contractor will work in coordination with COR to select the color and style of the new building prior to placing the order with the manufacturer.

The Contractor will be required to install a government furnished Yale lock on all exterior doors and vault hatches of the new toilet facility.

4) 311 – Stabilized Aggregate Surface Course

The Contractor will be required to construct a compacted gravel path as specified in the attached drawings. The gravel path shall be ¾” road base material, compacted to a depth of 6” deep. The Contractor is required to get COR approval prior to final placement of material. The approximate volume of material used for this site is 10 cubic yards.

5) Directions to Site

The site is located at the Miller Creek Campground. From the city of Durango, go East on Florida Road for 14.4 miles to County Road 243. Turn left (North) on County Road 243 for 3.4 miles. The picnic area with the toilet is located just before the campground entrance on the left. The site coordinates are 37.4039667, -107.659669. See Figure 2: Map - Durango, CO to Miller Creek Campground below.

Figure 2: Map - Durango, CO to Miller Creek Campground

3. CLIN 0003: Sig Creek Campground Toilet Replacement

2) 203 – Removal of Structures and Obstructions

The Contractor will be required to provide all materials, equipment, and labor to pump the existing vault toilet prior to building and vault demolition. The existing building and vault are to then be completely demolished and removed from the site.

3) 637 – Facilities and Services

The Contractor will then be required to provide all materials, equipment, and labor to install a contractor supplied vault toilet. The building will be a CXT Single Cascadian (Right Hand) model or approved equal and have a footprint of approximately 14’-7.5” by 15’-2.75”, stands 11’-6” high, and contains 1 toilet. See attached 3.1 – FS Construction Drawings – FY25 – Columbine for an overview of the site, general building layout, and other details.

The Contractor will work in coordination with COR to select the color and style of the new building prior to placing the order with the manufacturer.

The Contractor will be required to install a government furnished Yale lock on all exterior doors and vault hatches of the new toilet facility.

4) 311 – Stabilized Aggregate Surface Course

The Contractor will be required to construct a compacted gravel path as specified in the attached drawings. The gravel path shall be ¾” road base material, compacted to a depth of 6” deep. The Contractor is required to get COR approval prior to final placement of material. The approximate volume of material used for this site is 10 cubic yards.

5) Directions to Site

The site is located at the Sig Creek Campground. From the city of Durango, head 39 miles north on Highway 550. Turn into Purgatory Ski Resort and follow Hermosa Park Road (FSR 578) 6 miles west. The campground will be on the right-hand side of the road. The site coordinates are 37.63342, -107.88404. See Figure 3: Map - Durango, CO to Sig Creek Campground below.

Figure 3: Map - Durango, CO to Sig Creek Campground

Installation Specifications

See list of attachments on the last page of this document for more discussion about placement, building footprint, and general requirements for the project.

Pre-Bid/Pre-Proposal Conference

General Info

There will be NO pre-bid conference for this project.

Durango

Schedule of Items

Items Supplied by the Contractor

During the duration of the project, the Contractor will be required to provide their own power, water, and bathroom facility (portable toilet) for their employees. No use of Government facilities at the site will be allowed.

Items Supplied by the Government

For this contract, the Government will supply the Yale locks for the Contractor to install on the bathroom doors and vault hatches.

CLIN ITEM PAY

NO. DESCRIPTION PAY

UNIT QTY.

CLIN 0001

(Madden Creek)

1.1 15101 Mobilization LS 1

1.2 20301 Demolition of existing toilet LS 1

1.3 63704 Supply and delivery of new toilet

(single vault), installation, backfill, and grading

LS 1

1.4 31101 Constructed gravel path – ¾” road base material, compacted 6” deep CY 10

CLIN 0002

(Miller Creek)

2.1 15101 Mobilization LS 1

2.2 20301 Demolition of existing toilet LS 1

2.3 63704 Supply and delivery of new toilet

(single vault), installation, backfill, and grading

LS 1

2.4 31101 Constructed gravel path – ¾” road base material, compacted 6” deep CY 10

CLIN 0003

(Sig Creek)

3.1 15101 Mobilization LS 1

3.2 20301 Demolition of existing toilet LS 1

3.3 63704 Supply and delivery of new toilet

(single vault), installation, backfill, and grading

LS 1

3.4 31101 Constructed gravel path – ¾” road base material, compacted 6” deep CY 10

File details come from the government source that posted it. Updated .