This document contains questions and answers related to the solicitation for the Cloudburst Bridge Replacement project (Solicitation Number: 1282B124R0079) issued by the U.S. Department of Agriculture Forest Service.
The key details are:
- The contractor will not be required to obtain a SWPPP, but will be responsible for erosion control measures.
- The contractor can draft limited amounts of water from the creek, with a screen required.
- The contractor can camp on site with permission from the Contracting Officer, and a portable restroom is required.
- The contractor shall disassemble and transport the metal superstructure components to the Bridgeport District Warehouse, and dispose of the remainder of the demolished bridge components off-site.
- The work will consist of supplying and constructing a 16' x 50' prefabricated bridge superstructure with concrete grade beam foundations, to replace the existing bridge.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A10_Q_A_1282B123R0004.pdf | ||
| Amd_0002_Extension.pdf | ||
| A10_Amd_0001_Site Visit.pdf | ||
| A10_RFP_1282B124R0079_Complete.pdf | ||
| A9_SOI_CloudBurst.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cloudburst Bridge Replacement
1282B124R0079
QUESTIONS & ANSWERS
Q: Is it the contractor’s responsibility to get a SWPPP?
ANS: No, the contractor will not be required to get a NOI or SWPPP with the water board.
However, they will be responsible for erosion control measures, such as monitoring and preparing for any precipitation, placing fiber rolls below any disturbed ground, and protecting the creek while cutting the concrete abutment walls.
Q: Can the contractor draft out of the creek?
ANS: Yes, the contractor can draft limited amounts of water out of the creek. A screen will be required.
Q: Can the contractor camp on site?
ANS: Yes, the contractor can camp on site with the permission of the CO. A portable restroom (such as a porta-potty) will be required.
Q: What will the contractor do with the superstructure?
ANS: The contractor shall disassemble and transport the metal superstructure components (Bailey bridge components) to the Bridgeport District Warehouse (7480 Buckeye Rd, Bridgeport, CA 93517). The remainder of the bridge components getting demolished shall be disposed of off-site by the contractor.