A10_Q_A_1282B123R0004.pdf
PDF 61 KB Posted
- Attached to
- Cloudburst Bridge Replacement Federal contract opportunity
- Solicitation number
- 1282B124R0079
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a series of Questions and Answers (Q&A) related to the Cloudburst Bridge Replacement project, Solicitation Number 1282B124R0079, issued by the U.S. Department of Agriculture Forest Service.
The key details are:
- The project involves supply and construction of a 16' x 50' prefabricated bridge superstructure with concrete grade beam foundations to replace an existing bridge.
- There is a limited operating period (LOP) where on-the-ground disturbance may not begin until August 1, 2025, and the current contract period ends December 31, 2025.
- A Fish and Wildlife permit is not required if the equipment does not enter the stream channel.
- Poured-in-place concrete footings are acceptable, but the bridge deck must use the specified aggregate base per the drawings and specifications.
- The contractor is responsible for unloading the Bailey Bridge components at the Forest Service yard.
- Anchor bolts can be epoxied in after the bridge beams are set.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A10_QA_1282B123R0004.pdf | ||
| Amd_0002_Extension.pdf | ||
| A10_Amd_0001_Site Visit.pdf | ||
| A9_SOI_CloudBurst.xls | XLS spreadsheet | |
| A10_RFP_1282B124R0079_Complete.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cloudburst Bridge Replacement
1282B124R0079
QUESTIONS & ANSWERS
1) Is there an LOP on this project?
Yes
2) If there is an LOP, what is the time period?
On-the-ground disturbance may not begin until August 1, 2025. And the current contract period ends December 31, 2025.
3) If the equipment for construction doesn't enter the stream channel can the Fish and Wildlife permit be waived?
A Fish and Wildlife permit will not be required. Per the NEPA process, Fish and Wildlife has already been consulted with on this project.
4) Can a poured in place concrete deck be used verses road base, assuming the bridge designer will accept it? No, please adhere to the drawings and specifications, which call for aggregate base on the galvanized bridge deck.
5) Can the concrete footings be poured in place verses pre cast using the same dimensions and rebar plan? Yes, as long as the contract drawings and specifications for concrete properties are still being met, that will be acceptable.
6) If the footings can be poured in place, can the need for road base under the footings be eliminated? Yes, as long as the native soil underneath the footings is undisturbed.
7) If the sub grade is native soil verses road base, can the compaction test be waived? Compaction testing will not be required for the native soil.
8) Confirming that the Baily Bridge gets hauled to the forest service yard just north of Bridgeport?
Please see the Questions and Answers previously posted on Sam.gov on September 3.
9) Will the forest service provide a forklift to unload the Baily Bridge at the FS yard?
No, the contractor will be responsible for unloading the bridge components.
10) Would it be acceptable to epoxy in the anchor bolts after the bridge beams are set?
Yes