Attachment 1 - SOW.pdf
PDF 246 KB Posted
- Attached to
- 480 Volt Line Relocation Federal contract opportunity
- Solicitation number
- 12805B24Q0367
About this file
This document is a Statement of Work (SOW) for a 480-Volt Line Replacement project at the Biosciences Research Laboratory in Fargo, ND. The key requirements include:
The USDA-ARS in Fargo requires the rerouting of a 480-Volt line that currently runs through a generator scheduled for removal and near underground utilities that will be excavated. The contractor must demolish and rebuild the 480-Volt line in accordance with the attached drawings, ensuring minimal downtime with 7-day written notice. The work includes trenching, paving restoration, and providing as-built drawings. The period of performance is 60 days after award. No government-furnished equipment or travel is required. The contractor must provide a point of contact and have a licensed journeyman on site at all times.
This SOW is associated with Federal Contract Opportunity #b4cc8c5dd107431d87f21564de31acfd, Solicitation #12805B24Q0367 for a 480 Volt Line Relocation project, issued by the USDA-ARS Plains Area.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 4 - ARS-371.pdf | ||
| Sol_12805B24Q0367.pdf | ||
| Attachment 3 - 480V Drawings.pdf | ||
| Attachment 2 - ND20240013 - WAGE RATES.pdf | ||
| Attachment 5 - ARS-372.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) April 24, 2024
Project: 480-Volt Line Replacement
Location: Biosciences Research Laboratory, 1616 Albrecht Blvd N, Fargo, ND 58102
GENERAL INFORMATION
1.0 Statement of Work: USDA-ARS in Fargo, ND, requires a reroute of the 480Volt line from the existing secondary circuit breaker around the inside of building two, through the parking lot and tied back into the existing 480-volt panel board located on the outside west wall of building 1.
2.0 Background: The existing line runs through our generator that is scheduled to be removed under a separate contract. In addition, it runs through the parking lot in close proximity to steam tunnels and an underground fuel storage tank that will be excavated and removed under a separate contract. The intent is to relocate this 480-volt line before excavation occurs.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks:
• Demolish and rebuild the 480-volt line in accordance with the attached drawings.
o Sheet E 00 Electrical General Information o Sheet E 01 Electrical Specifications o Sheet E201 Floor Plan – Power and Auxiliary Systems
Trenching detail Patch Paving, re-sodding, back-filling Pavement Detail o Sheet E501 Power Riser Diagram
• Ensure that minimal amount of down-time is maintained. A 7-day written notification is required with an estimate of total down-time needed.
• Remove all conduit and conductors for generator and ATS controls and accessories complete back to source within building 2.
• Existing underground ducts and conduits may require hand digging to locate. Provide as-built drawings of all found utilities and final routing of new conduits.
• Provide patch paving and grass re-sodding to restore construction area to near existing conditions.
4.0 Deliverable / Schedule:
• Provide as-built drawings of the new line route. Add existing utilities as noted during trenching and installation.
• Period of performance: 60 days after award.
5.0 Government Furnished: Not Applicable.
6.0 Travel: Not Applicable.
7.0 Contractor’s Key Personnel: Point of contact’s name and phone number is required.
Minimum of one licensed journeyman must be on site at all times.
8.0 Security Requirements: Not Applicable.
9.0 Data Rights: Not Applicable.
10.0 Section 508 – Electronic and Information Technology Standards: Not Applicable.
11.0 Performance Requirement Measures: Items will be inspected before payment will be rendered.
ATTACHMENT: Attachment 3 480V drawings 12 Apr 24.pdf
6.0 Travel: Not Applicable.
File details come from the government source that posted it. Updated .