RFQ Questions for Well Repair.docx

DOCX document 13 KB Posted

Attached to
Well Repair - Clay Center, NE
Solicitation number
12805B21Q0213
Issued by

View the file

Other files

File Type Posted
Drawings.pdf PDF
RFQ - 12805B21Q0213.pdf PDF
Attachment C - NDAA 889 Certification.pdf PDF
Attachment A - Wage Determination.pdf PDF
Attachment B - Performance Work Statement.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04/20/2021 Solicitation# 12805B21Q0213

Questions and Answers for Well Repair

1. Is the current pump still operational? It is operational, but we don’t operate it. If one of the problems is that there is a hole in the pipe and the pump is operated, the well could be damaged.

2. Items # 3, 4, 9, and 10 in the bid items refer to submersible parts. Do we need to put submersible parts on the price sheet or just the parts to replace the turbine? Replacement of pump motor power cables refers to above ground conductors to motor. The check valve refers to the above ground check valve. The motor is the above ground motor. Motor shroud is not applicable. The electric splice kit would not be applicable.

3. Item #4 is a check valve. Is this the check valve for the discharge piping? Yes, the check valve is for the discharge piping.

4. Item #11 is pipe wrap. Can tnemec coated pipe substitute pipe wrap? The tnemec coated pipe is acceptable as long as it is at least equal to the pipe wrap.