Solicitation No. 12805B19RFQMD03
ATTACHMENT I
United States Department of Agriculture Agricultural Research Service
SPECIFICATION/STATEMENT OF WORK
Installation of New Fence
USDA-ARS-PA
Central Plains Experimental Range (CPER)
Nunn, Colorado
THIS PAGE IS BLANK
STATEMENT OF WORK/SPECIFICATIONS
For
Installation of New Fence
USDA-ARS-PA Central Plains Experimental Range
Nunn, CO
TABLE OF CONTENTS
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENTS
C-1 SPECIFICATION CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01010 - SUMMARY OF WORK
SECTION 01050 - FIELD ENGINEERING
SECTION 01300 - SUBMITTALS
SECTION 01400 - QUALITY CONTROL
SECTION 01545 - PROTECTION OF WORK AND PROPERTY
SECTION 01560 - TEMPORARY FACILITIES
SECTION 01600 - MATERIAL AND EQUIPMENT
SECTION 01620 - STORAGE AND PROTECTION
SECTION 01710 - CLEANING
SECTION 01711 - WARRANTY
SECTION 01712 - CONTRACT CLOSEOUT
Enclosures:
October 24, 2018
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01010 - SUMMARY OF WORK
A. GENERAL: It is the intent of these general conditions, specifications, together with the contract, to include all labor, materials, equipment, transportation, permits and fees, temporary protection and supervision necessary to complete the required work. All work shall be done under the direction of and completion to the satisfaction of the Contracting Officer.
1. Project Description:
Work includes: Installation of new fencing at the USDA, ARS, PA, Central Plains Experimental Range, 58009 Weld CR 37, Nunn, CO 80648.
A Base of approximately 31,680 feet (6 miles) of new 4-wire, wood post fence is needed to be installed at the USDA-Agricultural Research Service (USDA-ARS) Central Plains Experimental Range, near 18908 Weld County Road 114 Nunn, CO. There are two (2) sections of new fence to be installed: 1) south side of Weld County Road 114 from US Highway 85 to the west to Weld County Road 37 on the east, approximately 21,120 feet, 4 miles; 2) south side of Weld County Road 114 from Weld County Road 37 to east boundary of the property, approximately 10,560 feet, 2 miles, as shown on the attached files. All materials (posts, wire, staples – see below for specs) will be provided by the USDA-ARS. Installation will be provided by the contractor. Removal of existing fence shall be done by the USDA-ARS.
The contractor is expected to install 21, 2 post-H-braces (terminal) and 13 single in-line corner posts, and approximately 5 Deadman.
For terminal 2 post H-braces (21 of these), both the primary and secondary corner posts in each of these braces will be 7-inch diameter posts with length of 10 feet (120 inches). These posts need to be installed to a minimum of 60 inches, thereby leaving approximately 60 inches aboveground. H brace posts will be connected by a steel pipe (minimum 1.5-inch diameter and a minimum length of 120 inches (or 10 feet)). A diagonal wire (using #9 wire) will be wrapped around both posts, with it tied to the bottom of the corner on the H brace using an earth anchor and at top of the other post (see pictures at end of attached file).
Single in-line corner posts (13 of these) will also be a 7-inch minimum diameter post with length of 10 feet (120 inches). These posts need to be installed to a minimum of 60 inches, thereby leaving approximately 60 inches aboveground.
Line posts will be wood (minimum 4-inch diameter at top, pointed/capped/round and doweled, with a length of 7 feet (or 84 inches). Line posts will be installed every rod (16 feet), and to a minimum depth of 28 inches, thereby leaving approximately 56 inches aboveground. Posts cannot be hammered in – all holes for posts must be augured or dug.
Four strands of fence wire will be as follows, top 3 strands barbed wire (12 ½ gauge, Class I, 2pt, 4-inch spacing) and the 4th (bottom) strand being smooth (barbless) wire (12 ½ gauge, Class I). Each roll of barbed/barbless wire is approximately 1,320 feet (1/4 mile) in length. The smooth wire will be attached to wood line posts by barbed, galvanized staples (minimum length of 1.75 inches) at a minimum height of 16 inches from the ground. The 3 top strands of barbed wire will also be attached to wood line posts by barbed, galvanized staples (minimum length of 1.5 inches) at heights of approximately 28, 40 and 52 inches from the ground.
All sixteen-foot tubular steel gates will be provided by the USDA-ARS and installed by USDA-ARS personnel.
The contractor shall furnish all labor, tools, material, equipment, transportation to the job site, and supervision for the job indicated above.
2. Pre-Bid Meeting/Site Visit: will be held on November 28, 2018, 9:30 a.m. MST at the USDA, ARS, PA, Central Plains Experimental Range, 58009 Weld CR 37, Nunn, CO 80648. For directions to the site please contact Melissa Johnston, Agricultural Research Technician, Email:
Melissa.Johnston@usda.gov, Phone: (970) 897-2226.
3. Codes and Standards: Construction shall comply with the requirements of ARS Facilities Design
Standards Manual 242.1, ARS Energy Management Plan 134.2 and all other applicable federal, state and local code requirements as well as current industry standards, (i.e. UBC, UPC, NFPA, UL, ASTM, ACI, NEC, NEMA. etc.,) and health and safety codes, in effect at the time of contract award. ARS Design and construction manuals can be found on the website under “P&P and Manuals” at http://www.afm.ars.usda.gov/facilities/pplist-FD.htm.
4. The Contractor must comply with the Farm Security and Rural Investment Act of 2002 (FSRIA), 7
U.SC. 8102; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February, 2012 to provide biobased products.
5. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions to lawfully proceed with the required work, Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the responsibility of the Contractor.
6. Installation: It shall be the responsibility of the Contractor to perform all work in accordance with the manufacturers’ recommendations and Industry Standards. If any item specified herein and/or on the drawings conflicts with applicable codes and recommendations, the contractor shall bring it to the attention of the Contracting Officer for immediate resolution.
SECTION 01050 - FIELD ENGINEERING/INSPECTION OF SITE
A. The Contractor shall be responsible for verifying site conditions, making quantity take-offs, obtaining accurate measurement of existing conditions, and performing any act or operation which may be necessary to properly bid the work and complete the same as depicted and specified. Failure to verify the existing site conditions shall not relieve the Contractor of the responsibility to complete the work as required.
mailto:Melissa.Johnston@usda.gov http://www.afm.ars.usda.gov/facilities/pplist-FD.htm
SECTION 01300 - SUBMITTALS
A. Manufacturer's descriptive literature sufficient to determine conformance of the proposed product to the contract requirements shall be submitted to the CO for review and approval. The descriptive literature shall be annotated/highlighted to show its conformance with contract requirements.
B. Installation procedures supplied by the manufacturer.
SECTION 01400 - QUALITY CONTROL
A. GENERAL: To satisfy the requirement for Quality Control, the work performed under this contract shall be subject to continuous audit by the Contracting Officers Representative (COR). Quality control is the exclusive responsibility of the Contractor.
B. FINAL ACCEPTANCE: Acceptance of the completed work will be based upon its conformance to the contract.
C. WARRANTY: The warranty period for workmanship shall be for one (1) year from the date the government accepts the work.
SECTION 01525 - SAFETY REQUIREMENTS
A. The Contractor shall implement, and provide to the Contracting Officer (CO) for review, a site specific, SITE SAFETY AND HEALTH PLAN in accordance with all local, state and federal regulations. The plan shall address, at a minimum all responsible parties by name, all safety/health hazards, personal protective equipment and other hazard controls, all required training, emergency procedures, and other required information to perform the work. The plan shall be implemented by contractor supervisor signature.
One copy shall be provided to the Contracting Officer and one copy will be maintained at the site. In the event of changing site conditions or hazards, the plan shall be appended in writing and a copy of the change provided to the CO and COR.
SECTION 01545 - PROTECTION OF WORK AND PROPERTY
A. The Contractor shall protect the work, the site, and all existing property and structures within the limit of construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.
B. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor.
The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities for protection and security.
SECTION 01560 - TEMPORARY FACILITIES
A. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through is own negligence.
B. Should the Contractor require any power or utility shutdown during construction, he shall receive approval for such shutdown from the COR three working days prior to this need.
SECTION 01600 - MATERIALS AND EQUIPMENT
A. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer's latest standard design.
B. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplier and Contractor before, during and after shipment in a manner to prevent warping, twisting, breaking, chipping, rusting and any injury, theft or damage of any kind whatsoever to the materials and equipment. All materials and equipment furnished by Contractor shall be subject to inspection and approval by the CO/COR.
C. GOVERNMENT FURNISHED PROPERTY:
(See Project Description above)
D. EXECUTION:
(a) The Contractor shall provide the necessary tools, equipment, labor, shoring, scaffolding, coordination, and related materials necessary for the completion of work.
(b) Erection and installation techniques employed by the Contractor must be in accordance with the manufacturing company's suggested procedures.
SECTION 01710 - CLEANING
Upon completion of project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
SECTION 01711 – WARRANTY
Submit data concerning the standard one-year warranty for workmanship, including the warranty period (dates), and warranty contacts with names, addresses and telephone numbers.
Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
SECTION 01712 - CONTRACT CLOSEOUT
A. SUBMITTALS REQUIRED PRIOR TO FINAL PAYMENT
(1) General and Subcontractors one (1) year warranty on work.
(2) All warrantees from manufacturers covering materials and equipment.
(3) O&M manuals for any equipment.
(4) Digital plans and specifications including As-Built drawings.
****END OF SECTION***