This is an addendum Statement of Work for a project to replace eight non-operational air conditioning units in the Nematology Lab at the Tropical Plant Genetic Resources and Disease Research Unit (TPGRDRU) located at 928 Stainback Highway in Hilo, Hawaii. The contractor must remove and dispose of the current AC units, seal four openings (Units 3, 4, 5, and 6) using treated plywood, hardiplank, trim, caulk, and matching exterior paint, and install four wall-mounted LG LW1223HRSM 12,000 BTU units (230/280V with LCDI plug) on Units 1, 2, 7, and 8 with interior and exterior framing and trim. Additionally, the contractor shall install one 36,000 BTU double-head mini split system with dual indoor heads to replace Units 3 and 6, including a reinforced concrete foundation pad (minimum 3,000 PSI, 4 inches thick, extending 6 inches beyond unit footprint), concealed refrigerant lines with covers, and duct work to both rooms. The contractor is responsible for electrical connections and breaker panel modifications.

The period of performance is 60 calendar days following the Notice-to-Proceed, with a five-day completion notification requirement to the Contracting Officer Representative (COR) and Contracting Officer (CO) for scheduling a final walkthrough and punch list. The contractor must submit manufacturer's technical data sheets within 10 calendar days of NTP and provide a one-year warranty from the date of final acceptance per FAR 52.246-1. Work hours are limited to 7:00 a.m. to 3:30 p.m., with utility interruptions requiring three business days' advance notice and written COR permission. The contractor must comply with all OSHA standards, state and local regulations, maintain a clean work area, coordinate with the COR on staging and storage areas, and remove all waste materials upon completion. Smoking and controlled substances are prohibited on the project site.

View the file

Other files

File Type Posted
127EAX26Q0106 0002.pdf PDF
127EAX26Q0106 QA3.docx DOCX document
127EAX26Q0106 QA2.docx DOCX document
Revised 2.0_127EAX26Q0106 QA1.docx DOCX document
127EAX26Q0106 0001.pdf PDF
Attachment 2 - Wage Determination.pdf PDF
Attachment 1 - Statement of Work.docx DOCX document
127EAX26Q0106.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

(ADDENDUM)

Project Title: Replacement of air conditioning units in Nematology lab Project Number: (Internal number)

GENERAL

This project is for replacing the air conditioning (AC) units in the nematology lab. The AC units are located for the Tropical Plant Genetic Resources and Disease Research Unit (TPGRDRU) at 928 Stainback Highway in Hilo, Hawaii.

These AC units will replace current units which are not operational and/or are covered with mold and mildew from the standing humidity.

PROJECT DESCRIPTION

The contractor shall provide all necessary services, labor, equipment and materials to complete the scope of work as outlined below, including Construction Contract Administration. The work includes, but is not limited to, the following:

A. Site Preparation

· Remove and dispose of current AC units (total of 8 units)

· Refer to Image 1

· Seal openings from Units 3,4,5, and 6 that will no longer be used.

· ¾” treated plywood, hardiplank, trim & caulk, and paint to match existing exterior color-

· Set foundation for (1) Mini Split AC unit base.

· Foundation Specs:

· Concrete: Minimum 3,000 PSI

· Thickness: Minimum 4 inches

· : Extend 6” beyond unit footprint on all sides

· Base: 4 inches of compacted ¾” base coarse aggregate

· Reinforcement: Reinforce with welded wire mesh

· Elevation: Top of pad should be 3”-4” above surrounding finished grade

· Anchoring Mechanically anchor unit using corrosions-resistant anchors/hardware B. Wall AC installation

· Wall units (4). (2) On each end of the building, will be framed with interior and exterior trim to accommodate for new AC units (to be provided by government).

1. Relace Unit 1, 2, 7, 8

· Refer to Image 1

2. Unit Details

· LG

· LW1223HRSM

· 12,000 BTU

· 230/280 Volts LCDI Plug,

· Fits 27”-39”W x 16” H

· Dimensions Depth: 22.05” Height: 23.62”

· Electrical plugs and connection to breaker panel will provided by vendor.

· Once installed units will be insulated for heat and sound and sealed to prevent direct openings to the outside.

C. Mini Split System

· Provide (1) 36,000 BTU Double head system to cool the two main rooms in nematology lab.

· Mini Split system will replace units 3 & 6 for cooling.

· Refer to Image 1

· Install heads in the middle of each room

· Breaker will be modified as needed to accommodate AC systems.

· Conceal lines with covers and provide duct to both rooms.

D. Site Cleanup

· At the completion of the Work, the Contractor shall remove all waste materials and rubbish from the project site as well as all equipment.

· Refer to all local and state laws for proper disposal procedures

· The contractor shall provide a five-day notification to the COR and CO when work is completed for a walk through to be scheduled. A final punch list, if needed, will be provided to the contractor. The final punch list must be completed prior to final invoice approval.

E. Warranty

· The contractor shall provide a 1 year (one year) warranty from the date of final acceptance of work per FAR 52.246-1.

· All Warranties shall be turned over to the COR prior to final invoicing.

PERIOD OF PERFORMANCE:

The contractor shall employ all necessary resources to ensure all work is substantially completed within 60 calendar days following the Notice-to-Proceed. The contractor shall provide a five-day notification to the COR and CO when work is complete to develop a final punch list, which must be completed prior to final invoice. Final walk through should be completed prior to the period of performance end date to give enough time for completion of punch list items and final invoicing.

COORDINATION WITH OWNER:

F. Full owner occupancy: owner will occupy structure but limit entry when work is being conducted.

G. Staging and Storage Areas: The Contractor is allowed to utilize a limited portion of the area to be coordinated with the COR. The Contractor shall protect all roadways from damage caused by their equipment and shall repair or pay for the repair of any damaged roads, curbs and sidewalks. The Contractor shall be responsible for all security of his equipment and materials. The Contractor shall be responsible for complying with all OSHA standards for the safe storage of equipment and materials, including the safe handling of flammable liquids under 29 CFR 1926.152(a).

H. Utility Mark-Up: The contractor shall coordinate with the COR to contact utility companies for shut off as needed.

WORK RESTRICTIONS:

I. General: Comply with limitations concerning the use of public streets and with other requirements of authorities having jurisdiction.

J.On-Site Work Hours: The facility is open from 7:00 a.m. to 3:30 p.m., coordinate working hour limitations with the COR at the pre-construction conference or during construction.
K.Existing Utility Interruptions: Do not interrupt utilities serving occupied facilities or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

· Notify COR not less than three business days in advance of proposed utility interruptions.

· Obtain COR’s written permission before proceeding with utility interruptions.

L. The contractor is permitted to use the sanitation facilities. The headhouse restroom located outside the main facility will be open during normal business hours.

M. Smoking is not permitted anywhere on the project site.

N. Controlled Substances: Use of tobacco products and other controlled substances on project site is not permitted.

O.Work shall be performed in strict accordance with all terms, conditions, specifications, schedules and drawings. Performance shall be in accordance with the requirements, conditions, terms and representations contained in this solicitation, any pertinent OSHA Occupational and Safety regulations, and any State and/or local regulations, laws and codes.
P.The Contractor shall always keep the work area and adjoining areas free from accumulation of excess materials, except in areas that have been approved for stockpiling removed materials. At the completion of the Work, the Contractor shall remove all waste materials and rubbish from the project site as well as all equipment.

Other Information:

A. Staging: All supplies and materials for this contract shall be delivered to the work area specified by the COR.

B. Submittals: The contractor shall submit the manufacturer’s technical data sheets for the list of items within 10 calendar days of receipt of NTP. Each submittal shall be attached to a Submittal Transmittal Form, signed by the Contractor, and delivered via email to the COR with a carbon copy to the Contracting Officer (CO) and/or Contracting Specialist (CS).

C. Coordination: The contractor shall coordinate with the COR, with adequate advance notice, for all deliveries.

Image 1

Table 1 (Existing Unit Notes)

Unit
Brand
Appox. Cut Out Dimensions
Receptacle Type
1
Quasar
18” x 15”
20A, 125V
2
Friedrich
18” x 15”
20A, 125V
3
Carrier
26” x 17 ½”
30A, 250V
4
Carrier
26” x 17 ½”
30A, 250V
5
Carrier
26” x 17 ½”
30A, 250V
6
Frigidaire
26” x 17 ½”
20A, 125V
7
Frigidaire
18” x 15”
20A, 125V
8
Frigidaire
18” x 15”
20A, 125V

Image 2

Image 3 (Interior Electrical Panel)

Image 4 (Interior Electrical Panel List)

Image 5 (Exterior Electical Disconnect and Safety Switch)

Image 6 (Location of Foundation Pad and Mini Split Unit to be installed)

Building Elevation (Layout)

Wall 1

Wall 2

Wall 3

Wall 4 image3.png image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image1.png image2.png