Sol_127EAX26Q0094_Amd_0001.pdf
PDF 132 KB Posted
- Attached to
- Replace Perimeter Fence Pasture 7 Federal contract opportunity
- Solicitation number
- 127EAX26Q0094
- Issued by
- Department of Agriculture Forest Service
About this file
This document is Amendment 0001 to solicitation 127EAX26Q0094, issued by USDA-FS CSA Southwest 7 in Albuquerque, NM on August 27, 2026, with an effective date of September 10, 2026.
The amendment adds clarifying information to support a perimeter fence replacement project at a USDA facility. The project requires the contractor to remove and replace approximately 3,500 linear feet of existing fencing with new 8-foot game fencing, including installation of new gates and posts. Specific requirements include: 10-foot T-posts spaced 10 feet apart and embedded 2 feet deep; 8-foot game fence specifications per attached documents; buried animal fence details per provided examples; two gate areas with 20-foot openings on metal pipe posts with double gates preferred; and all related corner, end, and gate post specifications per attached pipe detail documents. The contractor is responsible for field verification of quantities, complete demolition and removal of existing fence materials, vegetation clearing, excavation, backfill, compaction, and final restoration. Work is restricted to Monday through Friday, 8 a.m. to 4 p.m., with USDA providing a designated staging/storage area. The contract is a firm-fixed price award anticipated off this RFP with a period of performance from October 1, 2026 to December 4, 2026. Davis Bacon wages apply. Offerors must submit cost proposals broken down in detail and send all responses to contracting officer Troy A. McCullough at troy.mccullough@usda.gov before the deadline. All invoices must be submitted through the Department of Treasury's Invoice Processing Platform (IPP). The bid due date will not be extended.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 00001 - Fencing Material CFTRL.pdf | ||
| Amendment 00001 - Fence Pipe Detail CFTRL.pdf | ||
| Amendment 00001 - Fence Detail CFTRL.pdf | ||
| Amendment 00001 - Perimeter Fence Example.pdf | ||
| Attachment 3 - Perimeter Fence Example.pdf | ||
| 127EAX26Q0094 Replace Perimeter Fence Pasture 7.pdf | ||
| Attachment 1 - Statement of Work.docx | DOCX document | |
| Attachment 2 - MAP Roughly 3500 linear feet.docx | DOCX document | |
| Attachment 4 - Fence buried to prevent animals from digging under Example.docx | DOCX document | |
| Attachment 5 - Wage Determination.pdf | ||
| New entrance to MAB ARS 6419 - 04AUG26.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
127EAX26Q0094
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
7EAX
ALBUQUERQUE NM 87102-3498
333 BROADWAY BLVD SE
USDA-FS CSA SOUTHWEST 7
09/10/20260001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/27/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Davis Bacon wages apply.
The government anticipates awarding a firm-fixed price contract off the RFP.
Offers or responses to the solicitation (include the solicitation number in the name of the document) should be sent to the contracting officer by email; troy.mccullough@usda.gov before the deadline.
Period of Performance: 10/01/2026 to 12/04/2026
The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice
Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in the previous communications from USDA and
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
TROY A. MCCULLOUGH
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
127EAX26Q0094/0001
Treasury. All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S.
Department of Treasury and you can find more information at this website https://www.ipp.gov/index.html.
Please make sure that your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm l to establish your account.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
The purpose for this amendment is to:
1) Add Questions and Answers as listed below.
2) Incorporate the following additional attachments into this solicitation.
a) Fence Detail CFTRL
b) Fence Pipe Detail CFTRL
c) Fencing Material CFTRL
d) Perimeter Fence Example
3) Bid Due date will not be extended.
No other changes have been made.
Questions and Answers incorporated into this solicitation.
1. Please confirm the required T-post length, size, spacing, and minimum embedment depth.
- 10 ft T-post spaced 10 feet apart and embedded 2 feet See fent detail
2. Please confirm the required 8-foot game fence specifications, including wire gauge, mesh opening size, and galvanization/coating requirements. The drawing identifies an 8-foot game fence but does not provide these details.
- Please see attachments
3. Please clarify the buried animal fence details, including material, gauge, mesh size, depth, horizontal width, and how it should be connected to the vertical fence.
- See perimeter fence example
4. What type of corner, end, and gate posts are required, including bracing and concrete footing requirements?
- Pipe in attached document
5. Are we required to remove and replace each section of existing fence on the same day to maintain the quarantine/biosecurity perimeter? If not, is temporary fencing required?
- Not required to remove and install the same day
6. Are there any special biosecurity requirements for workers, vehicles, tools, and equipment entering or leaving the facility?
- Not in this area
7. Please confirm the number, dimensions, type, and specifications of all replacement gates, including posts, hinges, latches, locks, and other hardware.
- Two gate areas with 20-foot opening. Double gate preferred on metal pipe post. Gate will be chained closed, hinge strong enough to withstand cattle.
8. Please confirm whether the approximately 3,500 LF of fencing is an estimated quantity or the actual quantity. Is the contractor responsible for field verification?
- Contractor is responsible for field verification
9. Will the new fence follow the exact existing fence alignment, or will USDA provide layout/staking for the new alignment?
- Exact fence line replacement
10. Is the contractor responsible for vegetation/brush clearing, excavation, backfill, compaction, and final restoration along the fence line?
- Contractor is responsible for turning over a finished product. This includes proper backfill, compaction, and restoration.
11. Is the contractor responsible for removing and disposing of all existing fencing, posts, gates, concrete, and related materials, or will USDA retain any materials?
- Contractor is responsible for removing the old fence, t-post, concrete, gates, and related materials.
12. Are there known underground utilities, drainage crossings, ditches, or other site conditions that may affect fence installation?
- No
13. What are the permitted working hours and days, and is weekend work allowed?
- Working hours are Monday through Friday 8am to 4pm
14. Will USDA provide a designated staging/storage area, and can equipment and materials remain onsite overnight?
- Yes
15. Is a bid guarantee/bid bond required? If yes, what percentage is required, and will USDA accept a certified or cashier¿s check instead of a bid bond?
- Refer to solicitation requirements
16. Are performance and payment bonds required after award? If yes, what percentage of the contract value is required for each?
- Refer to solicitation requirements
17. Are there any required inspections or hold points during fence installation before work can proceed?
- Facility personnel will survey the work several times a day and stop work if a problem occurs.
18. Should the price proposal be submitted as one lump sum, or does USDA want a detailed Schedule of Values for demolition, fencing, gates, and other work?
- Cost should be broken down in detail.
File details come from the government source that posted it. Updated .