This document is a comprehensive set of Questions and Answers (Q&A) for the Marshall Gulch Picnic Area & Trailhead renovation project issued by the Department of Agriculture Forest Service. The solicitation (Solicitation Number: 127EAX25R0015) involves constructing a 1,100-foot single-lane asphalt road with 32 parking spaces, installing two precast bridges (64 and 76 feet long), relocating a vault restroom, constructing/demolishing picnic areas, and performing various site improvements. Key project details include a proposal due date of September 22, 2025, a site visit on August 28, 2025, and a 20% bid bond requirement. The Q&A document addresses numerous technical inquiries covering bridge specifications, seeding quantities, construction timing constraints, material disposal, site access, and specific equipment specifications like picnic tables and grills, with clarifications provided by the contracting officer on each submitted request for information (RFI).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 127EAX25R0015 0001.pdf | ||
| MarshallGulch_SOI2025.xlsx | XLSX spreadsheet | |
| signup sheet 8_28_2025.jpg | JPG image | |
| All Mashall Questions up to date 9_3_2025.docx | DOCX document | |
| Staging Area Map_Marshall Gulch.pdf | ||
| 604269001 R Geotech Eval.pdf | ||
| 127EAX25R0015 Solicitation.pdf | ||
| Attachment 10 - Schedule of Items.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
All Mashall Questions up to date 9/3/2025
1. The bridge length shown in the Statement of Work (SOW) is different from the plans.
Statement of work describes a 64’ bridge. That is a typo, bridge length is 62’ according to plans
2. In Attachment 10, Pay item 20302 “Removal of Low Water Crossing and all retaining walls, Disposal Method” shows a quantity of 2. Can you please confirm this is a quantity of 1.
Quantity should be 1.
3. Please clarify the SWPPP requirement – Is contractor or Forest Service to provide?
Under FP-03 Section 157 (Storm Water Pollution Prevention) and Supplemental Specs, the contractor must prepare, submit for approval, and implement SWPPP.
4. Will sign-in sheet be posted/distributed by CO? Sign in sheet posted with Q&A’s
5. What is the due date for RFIs? 9/10/2025
6. For seeding quantities, is the square footage measured per item or in total?
Base Bid
| Seeding: 42,000 SF |
| Mulching: 42,000 SF |
Additive Bid Item 1
| Seeding: 3,600 SF |
| Mulching: 3,600 SF |
Additive Bid Item 2
| Seeding: 900 SF |
| Mulching: 900 SF |
Additive Bid Item 5
| Seeding: 7,300 SF |
| Mulching: 7,300 SF |
7. Can you please confirm the owner’s intent that the summary beneath Option 2 should include both Option 1 and Option 2? For all other options, the requirement is to show the cost of the particular option with and without mobilization, along with the total cost of the base, that option, and all previous options.
Each option is to be priced independently, option 2 should be priced independently and then summed up with the Main + Additive 1-2 Bid items Total.
8. According to Attachment 4, Paragraph 5, no construction activities are permitted between March 1 and August 1. However, average weather conditions in Summerhaven from October through March range from 57°F in October to 38°F in March. Per ADOT Standard Specifications for Road and Bridge Construction, the minimum temperature for placing standard asphaltic concrete (hot mix asphalt) is 65°F for both ambient air (rising at the start of placement) and surface temperature. Asphalt placement must cease if the ambient temperature falls to 70°F or below and is decreasing. Similarly, the American Concrete Institute (ACI) guidelines for cold weather concreting impose restrictions on placement and curing to ensure quality and durability.
As written, the prohibition on work between March and August overlaps with the only period when temperatures are suitable for asphalt and concrete placement. Does the Owner intend for work to occur during winter months, and if so, will specification variances be allowed for asphalt and concrete temperature requirements?
The Contractor shall submit a winter mix design for both asphalt and concrete for Government review and approval prior to placement. The winter mix design must demonstrate compliance with all applicable design standards (e.g., ADOT, ACI 306, ASTM/AASHTO).
The period of performance may be extended into an additional construction season, subject to CO approval.
9. Can you please provide geotechnical report for marshal gulch?
Yes, please see attached.
10. Please clarify if bid bond percentage rate of 20% is correct? Yes 20% is correct based on FAR guidance.
11. Can you please confirm that the contractor is permitted to stockpile excess earth material resulting from the site’s earth cut operations and tree stumps, without the need to haul these items down the mountain.
Site will be provided to buck and stack timber.
Excess Earth can be placed at the staging area at top of control road. Staging area map was provided in solicitation.
GEA BUILDERS RFI 9/3/2025
RFI-01
Pedestal Grill - Please confirm that Model No. A-20/S B2 refers to the series charcoal grill (A-20) with no shelf option (S) and embedded grill mount (B2). If not, please clarify the required configuration.
Confirmed. Model A-20/S B2 = Pilot Rock series A-20 charcoal grill, no shelf option, embedded grill mount (B2), or approved equal.
RFI-02
Picnic Tables - For Outdoor Creations Inc. Model No. 104FSS, please confirm whether the 92" Wood Grain Picnic Table is approved by the Government.
Additionally, please provide the required color.
Confirmed Model No. 104FSS. Color shall be concrete or brown tinting concrete. Final sample submittal required for CO approval after award of contract.
RFI-03
Superintendent/QCM Dual Role - Can the Contractor designate the Superintendent to also serve as the Quality Control Manager (QCM), provided that the individual meets the required qualifications and responsibilities outlined in the solicitation and Quality Control specification?
Yes, the same individual may serve as Superintendent and Quality Control Manager, provided they meet the qualifications in Spec 01060 -Quality Control Plan.
RFI-04
Proposal Timeline - Will the Government consider extending the proposal due date? Proposal due date is extended to 09/22/2025.
RFI-05
Water Access - Will there be access to a sufficient water source for compaction, erosion control, and other construction needs? If so, please identify the location(s).
The Coronado National Forest doesn’t not have a water source near Marshall Gulch. The closest water source is in the Town of Summerhaven. The water would be purchased from the Mount Lemmon Domestic Water Improvement District.
RFI-06
Demolition of Existing Materials - What are the requirements for handling demolition of existing boulders and asphalt? Specification did not specifically identify, please confirm disposal/handling expectations.
All demolition debris and asphalt must be removed from Forest Service land and legally disposed of offsite.
Boulders that are not to be re-used can be placed at the staging area at top of control road. Staging area map was provided in solicitation.
RFI-07
Picnic Tables and Stone Bases - Are the stone bases for the existing picnic tables to be demolished and replaced? Is off-road vehicle access permitted to pick up existing tables? Additionally, please clarify the requirements for removal/repair/remounting at the tables locations.
Existing stone bases to be demolished as shown in plans. Off-road equipment access for table removal requires COR approval and must avoid damage to retained vegetation/soil. New tables to be placed per drawings with concrete bases as required.
RFI-08
Disposal Requirements - Please confirm disposal requirements for demolished materials (e.g., asphalt, boulders, concrete, site furnishings). Are there any recycling, salvage, or specific disposal facility requirements
All asphalt, concrete, and furnishings designated for removal must be hauled off Forest Service land and disposed of legally. Recycling/salvage may be used if meeting state/county standards. No permanent onsite disposal allowed.
RFI-09
Site Grading - On page 79 of the drawings, the area appears flat, but during the site visit, elevation changes were observed. If an as-built survey reveals conditions significantly different from the drawings, will a change order be considered?
CO answer differing site conditions? Yes, the contract will have the differing site conditions clause included. All differing site conditions will be submitted to the COR and CO for review.
RFI-10
Tree and Stump Removal - How should the tree and stump removal line item be priced? Please confirm the approximate quantity or provide guidance for estimating.
No quantity is guaranteed, contractor must field-verify during site visit. Bid item should be priced as lump sum
RFI-11
Erosion Protection - In areas where boulders/rocks are visibly suspended (“in midair”) at the picnic areas, what is the required treatment? Please confirm if additional erosion control measures should be included.
Regrade slopes and stabilize with seeding, and mulch. Include erosion control measures necessary to ensure slope stability.