Questions_Answers.docx

DOCX document 14 KB Posted

Attached to
Awarded NKRD Maintenance Repairs
Solicitation number
127EAX24Q0028
Issued by

About this file

This document contains Questions and Answers related to a federal contract opportunity for maintenance repairs at the North Kaibab Ranger District (NKRD).

The key details are:

  • The contractor may secure a permit to allow camping on-site during the contract period, with the Forest Service designating the campsite location.
  • For the sewer line repair/replacement at the Big Springs Work Center, the contractor should plan to replace approximately 130 linear feet of 4-inch sanitary sewer line, with payment based on the actual amount replaced.
  • The contractor may submit alternative materials for the new electrical circuit at the Big Springs Lookout, as long as they meet NEC requirements.
  • For the backflow preventer assembly replacement, the contractor may use a different model than specified, as long as it is a 4-inch double check valve type with testable fittings.
  • The contract covers a variety of maintenance repairs and new improvements, including water system valves, electrical work, and sewer line repair/replacement.

View the file

Other files

File Type Posted
Award Notification.pdf PDF
127EAX24Q0028 Synopsis_Solicitation.pdf PDF
127EAX24Q0028 SF1442.pdf PDF
SPECIFICATIONS_summary of work.docx DOCX document
EX-3 BIG SPRINGS WORK CENTER - UTILITY PLAN SOUTH.pdf PDF
EX-2 BIG SPRINGS WORK CENTER - UTILITY PLAN NORTH.pdf PDF
127EAX24Q0028 Synopsis_Solicitation.pdf PDF
127EAX24Q0028 SF1442.pdf PDF
BioPreferred.pdf PDF
WD AZ20240043.txt TXT text file
EX-1 JACOB LAKE WORK CENTER - UTILITY PLAN.pdf PDF
Fire Plan.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions/Answers

Q1: Can the contractor and works bring a camper on-site/camp in the forest during the project.

A1: the contractor may secure a permit with the North Kaibab Ranger District to allow for camping in the forest during the contract period. The Forest service will work with the contractor to designate a camp site/multiple sites and will require that the maintain sanitary conditions at the site designated on the permit. Information regarding required fee will be determined prior to bid deadline

Q2: For item 009 (Sewer line repair/replace – Big Springs WC), how much sewer line should be replaced.

A2: due to the uncertain nature of the condition and location of the sanitary sewer to be replaced, offerors should plan to replace approximately 130 Linear Feet of 4” sanitary sewer line. The pay item will be paid based on the actual amount of sanitary sewer replaced measured by the horizontal linear foot.

Q3: Are there any alternative designs allowed for item number 006 (new electrical circuit – Big Springs LO)?

A3: the contractor shall provide a durable electrical circuit, appropriate for outdoor installation. The Specification allows for Galvanized Steel, Rigid PVC, and Flexible PVC conduit. The contractor may submit alternative materials such as heavy duty insulated electrical cable. Any alternative materials must meet requirements of NEC.

Q4: For item 013 (Back Flow Preventer Assembly replacement), can a different model of backflow preventer be used than what is provided in the specifications

A4: Yes, other Backflow Preventers may be used, any backflow preventer used must be a double check type, with testable fittings. The contractor is responsible for replacing the entire existing BFP assembly (4” Double Check Valve and two gate valves), if a different BFP is used than what is provided in the specifications, it will be the responsibility of the contractor to make any additional improvements to allow for satisfactory installation. BFP, Valves and Pipe shall be minimum 4” diameter.

File details come from the government source that posted it. Updated .