Additional follow up questions.pdf
PDF 62 KB Posted
- Attached to
- Boulder Reed Removal Federal contract opportunity
- Solicitation number
- 127EAX23Q0014
- Issued by
- Department of Agriculture Forest Service
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Award Notification.pdf | ||
| QandAs and Site Visit Sign In Sheet.pdf | ||
| AMENDMENT Solicitation 127EAX23Q0014.docx | DOCX document | |
| Attachment 4 - Tonto NF Fire Plan.pdf | ||
| Attachment 4 - GILA NF Fire Plan.pdf | ||
| Attachment 1 - Wage Determination.pdf | ||
| Attachment 5 - BioPreferred.pdf | ||
| 127EAX23Q0014 Boulder Reed Removal Solicitation.pdf | ||
| Attachment 2 - Boulder Reeds Removal Project SOW.pdf | ||
| Attachment 3 - Boulder Reeds Removal Project Maps.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Additional follow up questions:
1. What are the estimated square footage and sizes of the rip rap?
a. The area that the rip rap is located is approximately 530 linear feet. Rip rap is interspersed throughout with some being underwater or having reeds grown over top, preventing a more accurate estimate. Sizes of the majority of the rip rap range from 18- 30 inches, with some being smaller and some larger. Smaller “naturally found” rocks are not included in the rip rap relocation. These smaller, natural rocks may be used to help backfill when restoring grade.
2. What is the location of the previous/similar completed project? Who was the contractor that completed that project?
a. That project was located at Granite Reef recreation site. The company name was Blue World Construction